PROPERTY AND EQUIPMENT
12 Months Ended
Sep. 30, 2013
Property, Plant and Equipment [Abstract]  
PROPERTY AND EQUIPMENT
PROPERTY AND EQUIPMENT
A summary of property and equipment by classification is as follows:
 
 
September 30,
(In thousands)
2013
 
2012
Drilling vessels and equipment
$
2,979,503

 
$
2,523,895

Construction work in progress
715,320

 
438,081

Drill pipe
26,743

 
20,576

Office equipment and other
24,439

 
19,610

Cost
3,746,005

 
3,002,162

Less: Accumulated depreciation
(581,281
)
 
(464,822
)
Drilling and other property and equipment, net
$
3,164,724

 
$
2,537,340


Recently Completed Construction Projects
During fiscal year 2008, we entered into construction contracts with Jurong Shipyard Pte. Ltd. to construct two Friede & Goldman ExD Millennium semisubmersible drilling units (the Atwood Osprey and the Atwood Condor). The Atwood Osprey was delivered in April 2011, and the Atwood Condor was delivered in June 2012.
During fiscal year 2011, we entered into turnkey construction agreements with PPL Shipyard PTE LTD in Singapore (“PPL”) to construct three Pacific Class 400 jackup drilling units (the Atwood Mako, the Atwood Manta and the Atwood Orca). The Atwood Mako was delivered in August 2012, the Atwood Manta was delivered in November 2012, and the Atwood Orca was delivered in April 2013.
New Construction Projects
In January 2011, we entered into a turnkey construction contract with Daewoo Shipbuilding and Marine Engineering Co., Ltd (“DSME”) to construct an ultra-deepwater drillship, the Atwood Advantage, at the DSME yard in South Korea. The Atwood Advantage is scheduled for delivery in November 2013. In October 2011, we entered into a turnkey construction contract with DSME to construct an ultra-deepwater drillship, the Atwood Achiever, at the DSME yard in South Korea. The Atwood Achiever is scheduled for delivery in June 2014. In September 2012, we entered into a turnkey construction contract with DSME to construct a third ultra-deepwater drillship, the Atwood Admiral, at the DSME yard in South Korea. The Atwood Admiral is scheduled for delivery in March 2015. Most recently, in June 2013, we entered into a turnkey construction contract with DSME to construct a fourth ultra-deepwater drillship, the Atwood Archer, at the DSME yard in South Korea. The Atwood Archer is scheduled for delivery in December 2015.
As of September 30, 2013, we had expended approximately $732 million on our four ultra-deepwater drillships under construction. Total remaining firm commitments for these four drilling units under construction were approximately $1.5 billion at September 30, 2013.