Environmental
There were no significant updates to previously reported environmental matters included in Note 12 of FCX’s 2022 Form 10-K, other than the matter discussed below.

Historical Smelter Sites. On January 30, 2017, a putative class action titled Juan Duarte, Betsy Duarte and N.D., Infant, by Parents and Natural Guardians Juan Duarte and Betsy Duarte, Leroy Nobles and Betty Nobles, on behalf of themselves and all others similarly situated v. United States Metals Refining Company, Freeport-McMoRan Copper & Gold Inc. and Amax Realty Development, Inc., Docket No. 734-17, was filed in the Superior Court of New Jersey. In July 2023, the Court approved an agreement between the parties pursuant to which all claims were settled for an amount not material to FCX.
Litigation
There were no significant updates to previously reported legal proceedings included in Note 12 of FCX’s 2022 Form 10-K, other than the matter discussed below.

Louisiana Parishes Coastal Erosion Cases. Certain FCX affiliates were named as defendants, along with numerous co-defendants, in 13 cases out of a total of 42 cases filed in Louisiana state courts by 6 south Louisiana parishes (Cameron, Jefferson, Plaquemines, St. Bernard, St. John the Baptist and Vermilion), alleging that certain oil and gas exploration and production operations and sulfur mining and production operations in coastal Louisiana contaminated and damaged coastal wetlands and caused significant land loss along the Louisiana coast. In 2019, affiliates of FCX reached an agreement in principle to settle all 13 cases and, as of October 2022, all parties have executed the settlement agreement. On March 16, 2023, a non-plaintiff coastal parish included in the settlement (Terrebonne), filed an amended petition titled Terrebonne Parish Consolidated Government vs. Louisiana Department of Natural Resources et al., Docket No. 185576, in the 32nd Judicial District Court, Terrebonne Parish, State of Louisiana, adding the settling FCX affiliates to a lawsuit that challenges whether Terrebonne Parish is validly bound to the settlement agreement and seeks to have the court declare the settlement void. FCX is evaluating and exploring options to resolve this dispute and will vigorously defend this matter.

Other Matters
Indonesia Regulatory Matters
Over the past several years, the Indonesia government has enacted various laws and regulations to promote downstream processing of various minerals, including copper concentrates.

Export License. On June 10, 2023, export licenses for several exporters, including PT-FI, expired. During the second quarter and through July 2023, the Indonesia government issued various regulations to address exports of unrefined metals, including regulations by the Ministry of Energy and Mineral Resources (MEMR) to allow continued exports of copper concentrates through May 2024 for companies engaged in ongoing smelter development projects with construction progress greater than 50%, and regulations by the Ministry of Trade on the permitted export of various products, including copper concentrates.

On July 24, 2023, PT-FI was granted an export license through May 2024 for 1.7 million metric tons of copper concentrate. PT-FI will continue to work with the Indonesia government to obtain approvals to continue exports until the Manyar smelter is fully commissioned and has reached designed operating conditions.

Export Duties. Under PT-FI’s special mining license (IUPK), export duties are determined based on regulations that were in effect in 2018, which provided that no duties are required after smelter construction progress reached 50%. In March 2023, the Indonesia government verified that construction progress on the Manyar smelter exceeded 50% and PT-FI's export duties were eliminated effective March 29, 2023.

In July 2023, the Ministry of Finance issued a revised regulation on duties for various exported products, including copper concentrates. The revised regulation assesses export duties for copper concentrates at 7.5% in the second half of 2023 and 10% in 2024 for companies with smelter progress of 70% to 90%. For companies with smelter progress above 90%, export duties would be 5% in the second half of 2023 and 7.5% in 2024. PT-FI is continuing to discuss the applicability of the revised regulation with the Indonesia government and will contest, and seek recovery of, any assessments.

Smelter Development Progress. In 2018, PT-FI agreed to expand its domestic smelting and refining capacity to process all of its copper concentrates in Indonesia. PT-FI is advancing the construction of the Indonesia smelter projects and expanding capacity at PT Smelting. PT-FI estimates construction of the Manyar smelter to be complete in mid-2024 followed by commissioning of the facilities and a ramp-up schedule through year-end 2024.

As disclosed in Note 12 of FCX’s 2022 Form 10-K, in March 2022, PT-FI paid the Indonesia government an administrative fine totaling $57 million (which included charges of $41 million recorded in first-quarter 2022) related to smelter development delays in light of the COVID-19 pandemic.

In May 2023, MEMR issued a decree prescribing a revised formula for administrative fines for delays in construction of smelter and refining facilities, taking into account allowances for certain delays associated with the COVID-19 pandemic as verified by a third-party. In mid-July 2023, PT-FI submitted its third-party verified calculation, which resulted in an accrual for a potential administrative fine of $55 million based on the formula prescribed by the decree related to the period from August 2020 through January 2022. PT-FI continues to discuss the applicability of this
administrative fine with MEMR. Based on PT-FI’s revised smelter construction schedule, which was accepted by the Indonesia government in connection with the renewal of PT-FI's export license in early 2022, PT-FI does not believe any additional fines should be assessed under the decree.

Smelter Bond. The May 2023 decree by MEMR also requires an assurance bond to be held in escrow until project completion. PT-FI has an existing assurance bond to support its commitment for additional smelter development in Indonesia, which totals $134 million at June 30, 2023 (refer to Note 7), and may be required to make an additional refundable deposit of approximately $250 million in connection with the May 2023 decree.

Export Proceeds. The Indonesia government issued a regulation that became effective August 1, 2023, that requires 30% of PT-FI’s gross export proceeds to be temporarily deposited into Indonesia banks for a period of 90 days before withdrawal. PT-FI is reviewing implementing guidelines associated with this regulation.