XML 61 R20.htm IDEA: XBRL DOCUMENT v3.22.4
CONTINGENCIES
12 Months Ended
Dec. 31, 2022
Commitments and Contingencies Disclosure [Abstract]  
CONTINGENCIES CONTINGENCIES
Environmental. FCX subsidiaries are subject to various national, state and local environmental laws and regulations that govern emissions of air pollutants; discharges of water pollutants; generation, handling, storage and disposal of hazardous substances, hazardous wastes and other toxic materials; and remediation, restoration and reclamation of environmental contamination. FCX subsidiaries that operate in the U.S. also are subject to potential liabilities arising under CERCLA and similar state laws that impose responsibility on current and previous owners and operators of a facility for the remediation of hazardous substances released from the facility into the environment, including damages to natural resources, in some cases irrespective of when the damage to the environment occurred or who caused it. Remediation liability also extends to persons who arranged for the disposal of hazardous substances or transported the hazardous substances to a disposal site selected by the transporter. These liabilities are often shared on a joint and several basis, meaning that each responsible party is fully responsible for the remediation if some or all of the other historical owners or operators no longer exist, do not have the financial ability to respond or cannot be found. As a result, because of FCX’s acquisition of FMC, many of the subsidiary companies FCX now owns are responsible for a wide variety of environmental remediation projects throughout the U.S., and FCX expects to spend substantial sums annually for many years to address those remediation issues. Certain FCX subsidiaries have been advised by the U.S. Environmental Protection Agency (EPA), the Department of the Interior, the Department of Agriculture and various state agencies that, under CERCLA or similar state laws and regulations, they may be liable for costs of responding to environmental conditions at a number of sites that have been or are being investigated to determine whether releases of hazardous substances have occurred and, if so, to develop and implement remedial actions to address environmental concerns. FCX is also subject to claims where the release of hazardous substances is alleged to have damaged natural resources (NRD) and to litigation by individuals allegedly exposed to hazardous substances. As of December 31, 2022, FCX had more than 100 active remediation projects, including NRD claims, in 24 U.S. states. The aggregate environmental obligation for approximately 60% of the active remediation projects totaled less than $20 million at December 31, 2022.

A summary of changes in estimated environmental obligations for the years ended December 31 follows:
 202220212020
Balance at beginning of year$1,664 $1,584 $1,561 
Accretion expensea
110 104 102 
Additionsb
57 60 38 
Reductionsb
(14)(20)(58)
Spending(77)(64)(59)
Balance at end of year1,740 1,664 1,584 
Less current portion(125)(64)(83)
Long-term portion$1,615 $1,600 $1,501 
a.Represents accretion of the fair value of environmental obligations assumed in the acquisition of FMC, which were determined on a discounted cash flow basis.
b.Adjustments to environmental obligations are charged to operating income. Adjustments primarily reflect revisions for changes in the anticipated scope and timing of projects and other noncash adjustments.

Estimated future environmental cash payments (on an undiscounted and de-escalated basis) total $3.7 billion, including $125 million in 2023, $120 million in 2024, $93 million in 2025, $100 million in 2026, $97 million in 2027 and $3.2 billion thereafter. The amount and timing of these estimated payments will change as a result of changes in regulatory requirements, changes in scope and timing of remediation activities, the settlement of environmental matters and as actual spending occurs.
At December 31, 2022, FCX’s environmental obligations totaled $1.7 billion, including $1.6 billion recorded on a discounted basis for those obligations assumed in the FMC acquisition at fair value. FCX estimates it is reasonably possible that these obligations could range between $3.3 billion and $4.1 billion on an undiscounted and de-escalated basis.

At December 31, 2022, the most significant environmental obligations were associated with the Pinal Creek site in Arizona; the Newtown Creek site in New York City; historical smelter sites principally located in Arizona, Indiana, Kansas, Missouri, New Jersey, Oklahoma and Pennsylvania; and uranium mining sites in the western U.S. The recorded environmental obligations for these sites totaled $1.5 billion at December 31, 2022. FCX may also be subject to litigation brought by private parties, regulators and local governmental authorities related to these historical sites. A discussion of these sites follows.

Pinal Creek. The Pinal Creek site was listed under the Arizona Department of Environmental Quality’s (ADEQ) Water Quality Assurance Revolving Fund program in 1989 for contamination in the shallow alluvial aquifers within the Pinal Creek drainage near Miami, Arizona. Since that time, environmental remediation has been performed by members of the Pinal Creek Group, consisting of Freeport-McMoRan Miami Inc. (Miami), an indirect wholly owned subsidiary of FCX, and two other companies. Pursuant to a 2010 settlement agreement, Miami agreed to take full responsibility for future groundwater remediation at the Pinal Creek site, with limited exceptions. Remediation work consisting of groundwater extraction and treatment plus source control capping is expected to continue for many years. FCX’s environmental liability balance for this site was $437 million at December 31, 2022.

Newtown Creek. From the 1930s until 1964, Phelps Dodge Refining Corporation (PDRC), an indirect wholly owned subsidiary of FCX, operated a copper smelter, and from the 1930s until 1984, a copper refinery, on the banks of Newtown Creek (the creek), which is a 3.5-mile-long waterway that forms part of the boundary between Brooklyn and Queens in New York City. Heavy industrial uses on and around the creek and discharges from the City of New York’s sewer system over more than a century resulted in significant environmental contamination of the waterway. In 2010, EPA notified PDRC, four other companies and the City of New York that EPA considers them PRPs under CERCLA. The notified parties began working with EPA to identify other PRPs. In 2010, EPA designated the creek as a Superfund site, and in 2011, PDRC and four other companies (the Newtown Creek Group, NCG) and the City of New York entered an Administrative Order on Consent to perform a remedial investigation/feasibility study (RI/FS) to assess the nature and extent of environmental contamination in the creek and identify remedial options. The NCG’s RI/FS work and efforts to identify other PRPs are ongoing. The NCG submitted a final draft RI report to EPA in December 2022. The NCG expects to submit a draft FS report to EPA in late 2025 and currently expects EPA to select a creek-wide remedy in 2028, with the actual remediation construction starting several years later. In early 2022, EPA asked the NCG to develop and evaluate remedial alternatives for an early action in the East Branch tributary of the creek. FCX’s environmental liability balance for this site was $338 million at December 31, 2022. The final costs of fulfilling this remedial obligation and the allocation of costs among PRPs are uncertain and subject to change based on the results of the RI/FS, the remedy ultimately selected by EPA and related allocation determinations. Changes to the overall cost of this remedial obligation and the portion ultimately allocated to PDRC could be material to FCX.

Historical Smelter Sites. FCX subsidiaries and their predecessors at various times owned or operated copper, zinc and lead smelters or refineries in states including Arizona, Indiana, Kansas, Missouri, New Jersey, Oklahoma and Pennsylvania. For some of these former processing sites, certain FCX subsidiaries have been advised by EPA or state agencies that they may be liable for costs of investigating and, if appropriate, remediating environmental conditions associated with these former processing facilities. At other sites, certain FCX subsidiaries have entered into state voluntary remediation programs to investigate and, if appropriate, remediate on-site and off-site conditions associated with the facilities. The historical processing sites are in various stages of assessment and remediation. At some of these sites, disputes with local residents and elected officials regarding alleged health effects or the effectiveness of remediation efforts have resulted in litigation of various types, and similar litigation at other sites is possible.

From 1920 until 1986, United States Metals Refining Company (USMR), an indirect wholly owned subsidiary of FCX, owned and operated a copper smelter and refinery in the Borough of Carteret, New Jersey. Since the early 1980s, the site has been the subject of environmental investigation and remediation, under the direction and supervision of the New Jersey Department of Environmental Protection (NJDEP). On-site contamination is in the later stages of remediation. In 2012, after receiving a request from NJDEP, USMR also began investigating and remediating off-site properties, which is ongoing. As a result of off-site soil sampling in public and private areas near the former Carteret smelter, FCX established an environmental obligation for known and potential off-site
environmental remediation. Assessments of sediments in the adjacent Arthur Kill and sampling and analysis within the offsite area as we obtain access to residential properties are ongoing and could result in additional adjustments to the related environmental remediation obligation in future periods. The extent of contamination and potential remedial actions are uncertain and may take several years to evaluate.

FCX’s environmental liability balance for historical smelter sites, including in the Borough of Carteret, New Jersey, was $268 million at December 31, 2022.

On January 30, 2017, a putative class action titled Juan Duarte, Betsy Duarte and N.D., Infant, by Parents and Natural Guardians Juan Duarte and Betsy Duarte, Leroy Nobles and Betty Nobles, on behalf of themselves and all others similarly situated v. United States Metals Refining Company, Freeport-McMoRan Copper & Gold Inc. and Amax Realty Development, Inc., Docket No. 734-17, was filed in the Superior Court of New Jersey against USMR, FCX, and Amax Realty Development, Inc. The defendants removed this litigation to the U.S. District Court for the District of New Jersey, where it remains pending, and FMC was added as a defendant. The suit alleges that USMR generated and disposed of smelter waste at the site and allegedly released contaminants on-site and off-site through discharges to surface water and air emissions over a period of decades and seeks unspecified compensatory and punitive damages for economic losses, including diminished property values, additional soil investigation and remediation and other damages. In September 2022, the parties completed re-briefing on the plaintiffs’ motion for class certification. The judge indicated in late 2022 that there likely would not be a decision on class certification until late 2023 or 2024. In December 2022, the parties reached an agreement in principle to settle the class action suit and individual claims by some property owners outside the settlement class area. The potential settlement (if effected in accordance with the agreement in principle) would not have a material effect on our financial condition, results of operations or cash flows. However, there can be no assurance that a settlement will be reached and, if an agreement among the parties is reached, the implementation of a settlement would require, among other things, court approval. Given the uncertainties and complexities involved, FCX continues to prepare for trial and intends to vigorously defend the matter.

Uranium Mining Sites. During a period between 1940 and the early 1980s, certain FCX subsidiaries and their predecessors were involved in uranium exploration and mining in the western U.S., primarily on federal and tribal lands in the Four Corners region of the southwest. Similar exploration and mining activities by other companies have also caused environmental impacts warranting remediation.

In 2017, the Department of Justice, EPA, Navajo Nation, and two FCX subsidiaries reached an agreement regarding the financial contribution of the U.S. Government and the FCX subsidiaries and the scope of the environmental investigation and remediation work for 94 former uranium mining sites on tribal lands. Under the terms of the Consent Decree executed in May 2017, and approved by the U.S. District Court for the District of Arizona, the U.S. contributed $335 million into a trust fund to cover the government’s initial share of the costs, and FCX’s subsidiaries are proceeding with the environmental investigation and remediation work at the 94 sites. The program is expected to take more than 20 years to complete. In 2020, FCX reduced its associated obligation and recorded a $47 million credit to operating income to reflect the discounting effect of the recent and expected pace of project work under post-COVID-19 pandemic conditions. By letter dated September 29, 2021, EPA informed an FCX subsidiary that it does not expect to have funds sufficient to remediate sites covered by a bankruptcy settlement with Tronox and EPA considers a subsidiary of FCX to be potentially liable for 23 of these sites. However, based on recently available information from EPA, it is currently considered unlikely that EPA will deplete the available settlement dollars, at least in the near-term, and seek additional funds from FCX.

FCX is also conducting site surveys of historical uranium mining claims associated with FCX subsidiaries on non-tribal federal lands in the Four Corners region. Under a memorandum of understanding with the U.S. Bureau of Land Management (BLM), site surveys are being performed on approximately 15,000 mining claims, ranging from undisturbed claims to claims with mining features. Based on these surveys, BLM has issued no further action determinations for certain undisturbed claims. A similar agreement is in place with the U.S. Forest Service for mine features on U.S. Forest Service land. Either BLM or the U.S. Forest Service may request additional assessment or remediation activities for other claims with mining features. FCX will update this obligation when it has a sufficient number of remedy decisions from the BLM or the U.S. Forest Service to support a reasonably certain range of outcomes. FCX expects it will take several years to complete this work.

FCX’s environmental liability balance for the uranium mining sites was $439 million at December 31, 2022.
AROs. FCX’s ARO estimates are reflected on a third-party cost basis and are based on FCX’s legal obligation to retire tangible, long-lived assets. A summary of changes in FCX’s AROs for the years ended December 31 follows:
 202220212020
Balance at beginning of year$2,716 $2,472 $2,505 
Liabilities incurred
Settlements and revisions to cash flow estimates, net381 
a
331 
a
(13)
Accretion expense134 112 131 
Dispositions— 

— (2)
Spending(197)(201)(156)
Balance at end of year3,043 2,716 2,472 
Less current portion(195)(200)(268)
Long-term portion$2,848 $2,516 $2,204 
a.Includes adjustments at PT-FI, Morenci and Bagdad totaling $314 million for the year 2022 and adjustments at PT-FI totaling $397 million for the year 2021, see further discussion below.

ARO costs may increase or decrease significantly in the future as a result of changes in regulations, changes in engineering designs and technology, permit modifications or updates, changes in mine plans, settlements, inflation or other factors and as reclamation (concurrent with mining operations or post mining) spending occurs. ARO activities and expenditures for mining operations generally are made over an extended period of time commencing near the end of the mine life; however, certain reclamation activities may be accelerated if legally required or if determined to be economically beneficial. The methods used or required to plug and abandon non-producing oil and gas wellbores; remove platforms, tanks, production equipment and flow lines; and restore wellsites could change over time.

Financial Assurance. New Mexico, Arizona, Colorado and other states, as well as federal regulations governing mine operations on federal land, require financial assurance to be provided for the estimated costs of mine reclamation and closure, including groundwater quality protection programs. FCX has satisfied financial assurance requirements by using a variety of mechanisms, primarily involving parent company performance guarantees and financial capability demonstrations, but also including trust funds, surety bonds, letters of credit and other collateral. The applicable regulations specify financial strength tests that are designed to confirm a company’s or guarantor’s financial capability to fund estimated reclamation and closure costs. The amount of financial assurance FCX subsidiaries are required to provide will vary with changes in laws, regulations, reclamation and closure requirements, and cost estimates. At December 31, 2022, FCX’s financial assurance obligations associated with these U.S. mine closure and reclamation/restoration costs totaled $1.5 billion, of which $0.9 billion was in the form of guarantees issued by FCX and FMC. At December 31, 2022, FCX had trust assets totaling $0.2 billion (included in other assets), which are legally restricted to be used to satisfy its financial assurance obligations for its mining properties in New Mexico. In addition, FCX subsidiaries have financial assurance obligations for its oil and gas properties associated with plugging and abandoning wells and facilities totaling $0.4 billion. Where oil and gas guarantees associated with the Bureau of Ocean Energy Management do not include a stated cap, the amounts reflect management’s estimates of the potential exposure.

New Mexico Environmental and Reclamation Programs. FCX’s New Mexico operations are regulated under the New Mexico Water Quality Act and regulations adopted by the Water Quality Control Commission. In connection with discharge permits, the New Mexico Environment Department (NMED) has required each of these operations to submit closure plans for NMED’s approval. The closure plans must include measures to assure meeting applicable groundwater quality standards following the closure of discharging facilities and to abate groundwater or surface water contamination to meet applicable standards. FCX’s New Mexico operations also are subject to regulation under the 1993 New Mexico Mining Act (the Mining Act) and the related rules that are administered by the Mining and Minerals Division of the New Mexico Energy, Minerals and Natural Resources Department. Under the Mining Act, mines are required to obtain approval of reclamation plans. The agencies approved updates to the closure plan and financial assurance instruments and completed a permit renewal for Chino in 2020 and Tyrone in 2021. At December 31, 2022, FCX had accrued reclamation and closure costs of $534 million for its New Mexico operations. Additional accruals may be required based on the state’s periodic review of FCX’s updated closure plans and any resulting permit conditions, and the amount of those accruals could be material.
Arizona Environmental and Reclamation Programs. FCX’s Arizona operations are subject to regulatory oversight by the ADEQ. ADEQ has adopted regulations for its aquifer protection permit (APP) program that require permits for, among other things, certain facilities, activities and structures used for mining, leaching, concentrating and smelting, and require compliance with aquifer water quality standards during operations and closure. An application for an APP requires a proposed closure strategy that will meet applicable groundwater protection requirements following cessation of operations and an estimate of the implementation cost, with a more detailed closure plan required at the time operations cease. A permit applicant must demonstrate its financial ability to meet the closure costs approved by ADEQ. Closure costs for facilities covered by APPs are required to be updated every six years and financial assurance mechanisms are required to be updated every two years. During 2022, the Morenci and Bagdad mines increased their AROs by $118 million and $65 million, respectively, associated with their updated closure strategies and plans for stockpiles and tailings impoundments that were submitted to ADEQ for approval. FCX will continue evaluating and, as necessary, updating its closure plans and closure cost estimates at other Arizona sites, and any such updates may also result in increased costs that could be significant.

Portions of Arizona mining facilities that operated after January 1, 1986, also are subject to the Arizona Mined Land Reclamation Act (AMLRA). AMLRA requires reclamation to achieve stability and safety consistent with post-mining land use objectives specified in a reclamation plan. Reclamation plans must be approved by the State Mine Inspector and must include an estimate of the cost to perform the reclamation measures specified in the plan along with financial assurance. FCX will continue to evaluate options for future reclamation and closure activities at its operating and non-operating sites, which are likely to result in adjustments to FCX’s AROs, and those adjustments could be material.

At December 31, 2022, FCX had accrued reclamation and closure costs of $581 million for its Arizona operations.

Colorado Reclamation Programs. FCX’s Colorado operations are regulated by the Colorado Mined Land Reclamation Act (Reclamation Act) and regulations promulgated thereunder. Under the Reclamation Act, mines are required to obtain approval of plans for reclamation of lands affected by mining operations to be performed during mining or upon cessation of mining operations. In March 2020, the Division of Reclamation, Mining, and Safety (DRMS) approved Henderson’s proposed update to its closure plan and closure cost estimate.

In 2019, Colorado enacted legislation that requires proof of an end date for water treatment as a condition of permit authorizations for new mining operations and expansions beyond current permit authorizations. While this requirement does not apply to existing operations, it may lead to changes in long-term water management requirements at Climax and Henderson operations and AROs. In accordance with its permit from DRMS, Climax will submit an updated reclamation plan and cost estimate in 2024.

As of December 31, 2022, FCX had accrued reclamation and closure costs of $162 million for its Colorado operations

Chile Reclamation and Closure Programs. El Abra is subject to regulation under the Mine Closure Law administered by the Chile Mining and Geology Agency. In compliance with the requirement for five-year updates, in November 2018, El Abra submitted an updated plan with closure cost estimates based on the existing approved closure plan. Approval of the updated closure plan and cost estimates was received in August 2020, and did not result in a material increase to closure costs. At December 31, 2022, FCX had accrued reclamation and closure costs of $98 million for its El Abra operation.

Peru Reclamation and Closure Programs. Cerro Verde is subject to regulation under the Mine Closure Law administered by the Peru Ministry of Energy and Mines. Under the closure regulations, mines must submit a closure plan that includes the reclamation methods, closure cost estimates, methods of control and verification, closure and post-closure plans, and financial assurance. In compliance with the requirement for five-year updates, Cerro Verde is preparing to submit its updated closure plan and cost estimate in February 2023. At December 31, 2022, FCX had accrued reclamation and closure costs of $171 million for its Cerro Verde operation, which includes preliminary cost estimates associated with Cerro Verde’s updated closure plan.

Indonesia Reclamation and Closure Programs. The ultimate amount of reclamation and closure costs to be incurred at PT-FI’s operations will be determined based on applicable laws and regulations and PT-FI’s assessment of appropriate remedial activities under the circumstances, after consultation with governmental authorities, affected local residents and other affected parties and cannot currently be projected with precision. Some reclamation costs
will be incurred during mining activities, while the remaining reclamation costs will be incurred at the end of mining activities, which are currently estimated to continue through 2041. In 2021, the construction time frame for reclamation of the West Wanagon overburden stockpile was extended from 2025 to 2029 because safety constraints for working in steep and difficult terrain has reduced labor and equipment operating efficiencies. The time frame extension resulted in longer and escalating fixed costs, combined with additional anticipated volumes of stockpile material to be moved. In 2022, estimated costs associated with West Wanagon slope stabilization remediation and reclamation activities increased primarily as a result of increased material needed for stockpile stabilization and increased costs for equipment, operations and maintenance, increased manpower/headcount allocation and contractor/consultant cost impacts. As a result of these changes, ARO adjustments of $131 million were recorded in 2022 (of which $116 million related to the depleted Grasberg open pit and charged to production and delivery costs) and $397 million in 2021 (of which $340 million related to the depleted Grasberg open pit and charged to production and delivery costs). At December 31, 2022, FCX had accrued reclamation and closure costs of $1.1 billion for its PT-FI operations.

Indonesia government regulations issued in 2010 require a company to provide a mine closure guarantee in the form of a time deposit placed in a state-owned bank in Indonesia. At December 31, 2022, PT-FI had restricted time deposits totaling $103 million for mine closure and reclamation guarantees.

Oil and Gas Properties. Substantially all of FM O&G’s oil and gas leases require that, upon termination of economic production, the working interest owners plug and abandon non-producing wellbores, remove equipment and facilities from leased acreage, and restore land in accordance with applicable local, state and federal laws. Following several sales transactions, FM O&G’s remaining operating areas primarily include offshore California and the Gulf of Mexico (GOM). As of December 31, 2022, FM O&G AROs cover approximately 110 wells and 105 platforms and other structures and it had accrued reclamation and closure costs of $328 million.

Litigation. In addition to the material pending legal proceedings discussed below and above under “Environmental,” we are involved periodically in ordinary routine litigation incidental to our business, some of which may result in adverse judgments, settlements, fines, penalties, injunctions or other relief. SEC regulations require us to disclose environmental proceedings involving a governmental authority if we reasonably believe that such proceedings may result in monetary sanctions above a stated threshold. Pursuant to the SEC regulations, we use a threshold of $1 million for purposes of determining whether disclosure of any such environmental proceedings is required. Management does not believe, based on currently available information, that the outcome of any current pending legal proceeding will have a material adverse effect on FCX’s financial condition, although individual or cumulative outcomes could be material to FCX’s operating results for a particular period, depending on the nature and magnitude of the outcome and the operating results for the period.

Louisiana Parishes Coastal Erosion Cases. Certain FCX affiliates were named as defendants, in 13 cases filed in Louisiana state courts by six south Louisiana parishes (Cameron, Jefferson, Plaquemines, St. Bernard, St. John the Baptist and Vermilion), alleging that certain oil and gas exploration and production operations and sulfur mining and production operations in coastal Louisiana contaminated and damaged coastal wetlands and caused significant land loss along the Louisiana coast. The state of Louisiana, through the Attorney General and separately through the Louisiana Department of Natural Resources, intervened in the litigation in support of the parishes’ claims. Certain FCX affiliates were named as defendants in two of the five cases that had been set for trial, both originally filed on November 8, 2013: Parish of Plaquemines v. ConocoPhillips Company et al., 25th Judicial District Court, Plaquemines Parish, Louisiana; No. 60-982, Div. B and Parish of Plaquemines v. Hilcorp Energy Company et al., 25th Judicial District Court, Plaquemines Parish, Louisiana; No. 60-999, Div. B. In 2019, affiliates of FCX reached an agreement in principle to settle all 13 cases, and as of October 2022, all parties have executed the settlement agreement. The settlement agreement does not include any admission of liability by FCX or its affiliates. FCX recorded a charge in 2019 for the initial payment of $15 million, which FCX expects to pay in trust to later be deposited into a newly formed Coastal Zone Recovery Fund (the Fund) if the state of Louisiana passes enabling legislation to establish the Fund within three years of execution of the settlement agreement. Upon payment of the $15 million, the FCX affiliates will be fully released and dismissed from all 13 pending cases. The maximum out-of-pocket settlement payment will be $23.5 million, including the initial $15 million payment. The settlement agreement will also require the FCX affiliates to pay into the Fund twenty annual installments of $4.25 million beginning in 2023 provided the state of Louisiana passes the enabling legislation. The first two of those annual installments are conditioned only on the enactment of the enabling legislation within three years of execution of the settlement agreement, but all subsequent installments are also conditioned on the FCX affiliates receiving simultaneous reimbursement on a dollar-for-dollar basis from the proceeds of environmental credit sales generated by the Fund, resulting in the $23.5 million maximum total payment obligation.
Asbestos and Talc Claims. Since approximately 1990, various FCX affiliates have been named as defendants in a large number of lawsuits alleging personal injury from exposure to asbestos or talc allegedly contained in industrial products such as electrical wire and cable, raw materials such as paint and joint compounds, talc-based lubricants used in rubber manufacturing or from asbestos contained in buildings and facilities located at properties owned or operated by affiliates of FCX. Many of these suits involve a large number of codefendants. Based on litigation results to date and facts currently known, FCX believes there is a reasonable possibility that losses may have been incurred related to these matters; however, FCX also believes that the amounts of any such losses, individually or in the aggregate, are not material to its consolidated financial statements. There can be no assurance that future developments will not alter this conclusion.

There has been a significant increase in the number of cases alleging the presence of asbestos contamination in talc-based cosmetic and personal care products and in cases alleging exposure to talc products that are not alleged to be contaminated with asbestos. The primary targets have been the producers of those products, but defendants in many of these cases also include talc miners. Cyprus Amax Minerals Company (CAMC), an indirect wholly owned subsidiary of FCX, and Cyprus Mines Corporation (Cyprus Mines), a wholly owned subsidiary of CAMC, are among those targets. Cyprus Mines was engaged in talc mining and processing from 1964 until 1992 when it exited its talc business by conveying it to a third party in two related transactions. Those transactions involved (1) a transfer by Cyprus Mines of the assets of its talc business to a newly formed subsidiary that assumed all pre-sale and post-sale talc liabilities, subject to limited reservations, and (2) a sale of the stock of that subsidiary to the third party. In 2011, the third party sold that subsidiary to Imerys Talc America (Imerys), an affiliate of Imerys S.A. In accordance with the terms of the 1992 transactions and subsequent agreements, Imerys undertook the defense and indemnification of Cyprus Mines and CAMC in talc lawsuits.

Cyprus Mines has contractual indemnification rights, subject to limited reservations, against Imerys, which historically acknowledged those indemnification obligations and took responsibility for all cases tendered to it. However, in February 2019, Imerys filed for Chapter 11 bankruptcy protection, which triggered an immediate automatic stay under the federal bankruptcy code prohibiting any party from continuing or initiating litigation or asserting new claims against Imerys. As a result, Imerys stopped defending the talc lawsuits against Cyprus Mines and CAMC. In addition, Imerys took the position that it alone owns, and has the sole right to access, the proceeds of the legacy insurance coverage of Cyprus Mines and CAMC for talc liabilities. In March 2019, Cyprus Mines and CAMC challenged this position and obtained emergency relief from the bankruptcy court to gain access to the insurance until the question of ownership and contractual access could be decided in an adversary proceeding before the bankruptcy court, which is currently on hold.

In January 2021, Imerys filed the form of a settlement and release agreement to be entered into by CAMC, Cyprus Mines, FCX, Imerys and the other debtors, tort claimants’ committee and future claims representative in the Imerys bankruptcy. In accordance with the global settlement, among other things, (1) CAMC will pay a total of $130 million in cash to a settlement trust in seven annual installments, which will be guaranteed by FCX, and (2) CAMC and Cyprus Mines and their affiliates will contribute to the settlement trust all rights that they have to the proceeds of certain legacy insurance policies as well as indemnity rights they have against Johnson & Johnson, and Imerys also obtained an injunction temporarily staying approximately 950 talc lawsuits against CAMC and Cyprus Mines, which has been extended through July 2023. The interim stay is a component of the global settlement but there can be no assurance that the bankruptcy court will continue to impose the interim stay.

As part of the global settlement, Cyprus Mines filed for Chapter 11 bankruptcy protection in February 2021. In connection with executing the settlement and release agreement, FCX concluded that it has a probable loss and, in 2020, recorded a $130 million charge to environmental obligations and shutdown costs.

Mediation to resolve open issues in the Imerys and Cyprus Mines bankruptcy cases, including the adequacy of the global settlement, is ongoing, and FCX expects it to continue at least through first-quarter 2023.

FCX’s global settlement is subject to, among other things, votes by claimants in both the Imerys and Cyprus Mines bankruptcy cases as well as bankruptcy court approvals in both cases, and there can be no assurance that the global settlement will be successfully implemented. FCX has a $130 million liability balance at December 31, 2022, associated with the proposed settlement.

Tax and Other Matters. FCX’s operations are in multiple jurisdictions where uncertainties arise in the application of complex tax regulations. Some of these tax regimes are defined by contractual agreements with the local government, while others are defined by general tax laws and regulations. FCX and its subsidiaries are subject to
reviews of its income tax filings and other tax payments, and disputes can arise with the taxing authorities over the interpretation of its contracts or laws. The final taxes paid may be dependent upon many factors, including negotiations with taxing authorities. In certain jurisdictions, FCX pays a portion of the disputed amount before formally appealing an assessment. Such payment is recorded as a receivable if FCX believes the amount is collectible.

Cerro Verde Royalty Dispute. SUNAT (National Superintendency of Customs and Administration) assessed mining royalties on ore processed by the Cerro Verde concentrator for the period from December 2006 to December 2013. No royalty assessments were issued for the years after 2013, as Cerro Verde began paying royalties on all of its production in January 2014 under its new 15-year stability agreement. Cerro Verde contested each of these assessments because it believes that its 1998 stability agreement exempts from royalties all minerals extracted from its mining concession, irrespective of the method used for processing such minerals. During 2021, Cerro Verde paid the balance of its royalty dispute liabilities and has no remaining exposure associated with the royalty dispute with the Peruvian tax authorities.

On February 28, 2020, FCX filed on its own behalf and on behalf of Cerro Verde international arbitration proceedings against the Peruvian government under the United States-Peru Trade Promotion Agreement. The hearing on the merits is scheduled to take place in May 2023. In April 2020, SMM Cerro Verde Netherlands B.V. (SMM Cerro Verde), another shareholder of Cerro Verde, filed parallel international arbitration proceedings against the Peruvian government under the Netherlands-Peru Bilateral Investment Treaty. SMM Cerro Verde’s hearing on the merits took place in February 2023. No amounts have been recorded for potential gain contingencies associated with the international arbitration proceedings.
    
Other Peru Tax Matters. Cerro Verde has also received assessments from SUNAT for additional taxes, penalties and interest related to various audit exceptions for income and other taxes. Cerro Verde has filed or will file objections to the assessments because it believes it has properly determined and paid its taxes. A summary of these assessments follows:
Tax YearTax Assessment
Penalties and Interest
Total
2003 to 2008$48 $130 $178 
200956 52 108 
201054 125 179 
2011 and 201242 73 115 
201348 66 114 
2014 to 201773 30 103 
$321 $476 $797 

As of December 31, 2022, Cerro Verde had paid $741 million on these disputed tax assessments. A reserve has been applied against these payments totaling $408 million, resulting in a net receivable of $333 million (included in other assets), which Cerro Verde believes is collectible.

Cerro Verde’s income tax assessments, penalties and interest included in the table above totaled $0.7 billion at December 31, 2022, of which $0.4 billion has not been charged to expense.

Indonesia Tax Matters. PT-FI has received assessments from the Indonesia tax authorities for additional taxes and interest related to various audit exceptions for income and other taxes. PT-FI has filed objections to the assessments because it believes it has properly determined and paid its taxes. Excluding surface water tax assessments discussed below and the Indonesia government’s previous imposition of a 7.5% export duty that PT-FI paid under protest during the period April 2017 to December 21, 2018 (refer to Note 13), a summary of these assessments, including potential penalties follows:
Tax YearTax AssessmentPenalties and InterestTotal
2005$62 $29 $91 
200745 22 67 
2012 and 201341 41 82 
2014 and 2015108 — 108 
2016257 336 593 
2017
$520 $430 $950 
As of December 31, 2022, PT-FI had paid $193 million on these disputed tax assessments. A reserve has been applied against these payments totaling $181 million, resulting in a net receivable of $12 million (included in other assets), which PT-FI believes is collectible.

PT-FI’s income tax assessments, penalties and interest included in the table above totaled $0.9 billion at December 31, 2022, of which $0.4 billion has not been charged to expense.

Surface Water Taxes. PT-FI received assessments from the local regional tax authority in Central Papua, Indonesia, for additional taxes and penalties related to surface water taxes for the period from January 2011 through December 2018. As a result, PT-FI offered to pay one trillion rupiah to settle these historical surface water tax disputes and charged $69 million to production and delivery costs in 2018. In 2019, PT-FI agreed to a final settlement of 1.394 trillion rupiah (approximately $99 million) and recorded an incremental charge of $28 million. PT-FI paid 708.5 billion rupiah ($50 million) in October 2019, and paid the balance of 685.5 billion rupiah ($48 million) during 2021.

Withholding Tax Assessments. In January 2019, the Indonesia Supreme Court rendered an unfavorable decision related to a PT-FI 2005 withholding tax matter. PT-FI had also received an unfavorable Indonesia Supreme Court decision in November 2017. PT-FI currently has other pending cases at the Indonesia Supreme Court related to withholding taxes for employees and other service providers for the year 2005 and the year 2007, which total $42 million (based on the exchange rate as of December 31, 2022, and included in accounts payable and accrued liabilities in the consolidated balance sheet at December 31, 2022), including penalties and interest.

Smelter Development Progress. In January 2021, the Indonesia government levied an administrative fine of $149 million for the period from March 30, 2020, through September 30, 2020, on PT-FI for failing to achieve physical development progress on its greenfield smelter as of July 31, 2020. On January 13, 2021, PT-FI responded to the Indonesia government objecting to the fine because of events outside of its control causing a delay of the greenfield smelter’s development progress. PT-FI believes that its communications during 2020 with the Indonesia government were not properly considered before the administrative fine was levied.

In June 2021, the Indonesia government issued a ministerial decree for the calculation of an administrative fine for lack of smelter development in light of the COVID-19 pandemic, and in 2021, PT-FI recorded charges totaling $16 million for a potential settlement of the administrative fine. In January 2022, the Indonesia government submitted a new estimate of the administrative fine totaling $57 million, and in March 2022, PT-FI paid the administrative fine and recorded an additional charge of $41 million. Based on PT-FI’s revised smelter construction schedule, PT-FI does not believe any additional fines should be applied and will dispute any attempts by the Indonesia government to levy additional fines, which could be significant.

PT-FI and PT Smelting Export Licenses. Indonesia regulations require PT-FI and PT Smelting to renew their export licenses annually (PT-FI’s export license for copper concentrate is subject to review by the Indonesia government every six months, depending on greenfield smelter construction progress). PT-FI’s current export license is scheduled for renewal in March 2023, and PT-FI is preparing its renewal application. PT Smelting’s current anodes slimes export license expires in November 2023.

While PT-FI's special mining license (IUPK) provides that exports continue through 2023 (subject to force majeure considerations), recent press reports have indicated that the Indonesia government is considering a ban of copper concentrate exports effective in June 2023 under regulations that were issued in 2020 and 2021. In addition, PT Smelting exports may also be restricted (contrary to the expiration date of PT Smelting’s current export license noted above). PT-FI plans to work cooperatively with the Indonesia government to continue exports as required until the smelter is fully commissioned.

Letters of Credit, Bank Guarantees and Surety Bonds.  Letters of credit and bank guarantees totaled $312 million at December 31, 2022, primarily associated with environmental obligations, AROs and for copper concentrate shipments from PT-FI to Atlantic Copper as required by Indonesia regulations. In addition, FCX had surety bonds totaling $488 million at December 31, 2022, primarily associated with environmental obligations and AROs.

Insurance.  FCX purchases a variety of insurance products to mitigate potential losses, which typically have specified deductible amounts or self-insured retentions and policy limits. FCX generally is self-insured for U.S. workers’ compensation, but purchases excess insurance up to statutory limits. An actuarial analysis is performed twice a year on the various casualty insurance programs covering FCX’s U.S.-based mining operations, including
workers’ compensation, to estimate expected losses. At December 31, 2022, FCX’s liability for expected losses under these insurance programs totaled $62 million, which consisted of a current portion of $10 million (included in accounts payable and accrued liabilities) and a long-term portion of $52 million (included in other liabilities). In addition, FCX has receivables of $23 million (a current portion of $5 million included in other accounts receivable and a long-term portion of $18 million included in other assets) for expected claims associated with these losses to be filed with insurance carriers. FCX’s oil and gas operations are subject to all of the risks normally incidental to the production of oil and gas, including well blowouts, cratering, explosions, oil spills, releases of gas or well fluids, fires, pollution and releases of toxic gas, each of which could result in damage to or destruction of oil and gas wells, production facilities or other property, or injury to persons. While FCX is not fully insured against all risks related to its oil and gas operations, its insurance policies provide limited coverage for losses or liabilities relating to pollution, with broader coverage for sudden and accidental occurrences. FCX is self-insured for named windstorms in the GOM.