XML 51 R10.htm IDEA: XBRL DOCUMENT v2.4.0.8
Note 4 - Inventories, net
6 Months Ended
Jun. 30, 2014
Inventories [Abstract]  
Inventories, net
Inventories, net
Inventories consist of the following:
 
 
 
June 30, 2014
 
December 31, 2013
Raw materials
 
$
915,578

 
$
947,765

Work-in-process
 
827,759

 
266,431

Finished goods
 
1,344,220

 
1,121,095

Total
 
$
3,087,557

 
$
2,335,291


The cost of silver in inventory that is included in raw materials, work-in-process and finished goods had an estimated cost of $480,600 and $382,332 as of June 30, 2014 and December 31, 2013, respectively. Work-in-process increased $561,328 from December 31, 2013 to June 30, 2014. This increase is primarily due to in-process tooling of $431,660.