NOTE 2 – LEASES

For the three-month periods ended March 29, 2024 and March 31, 2023, cash paid for amounts included in the measurement of operating lease liabilities was $86 and $83, respectively, and lease right-of-use assets obtained in exchange for new operating lease liabilities were $105 and $108, respectively. The weighted-average remaining lease term and weighted-average discount rate were four years and 3.7%, respectively, as of both March 29, 2024 and December 31, 2023.

The following table summarizes the Partnership's operating lease cost, variable lease cost not included in the lease liability and total lease cost for the:

 

 

Three Months Ended

 

 

 

March 29, 2024

 

 

March 31, 2023

 

Operating lease cost

 

$

86

 

 

$

83

 

Variable lease cost

 

 

17

 

 

 

17

 

Total lease cost

 

$

103

 

 

$

100

 

 

The Partnership's future undiscounted cash outflows for operating leases are summarized below as of:

 

March 29, 2024

 

2024

$

253

 

2025

 

296

 

2026

 

240

 

2027

 

177

 

2028

 

112

 

Thereafter

 

109

 

Total lease payments

 

1,187

 

Less: Interest

 

105

 

Total present value of lease liabilities

$

1,082

 

 