On March 12, 2015, the Company announced the selection of St. Pauls and Robeson County, North Carolina, for the construction of a new poultry processing complex. The completed complex will consist of a hatchery, processing plant, waste water treatment facility, and an expansion of the Company's existing feed mill in Kinston, North Carolina. Construction commenced in July 2015, and initial operations of the new complex are expected to begin during the first quarter of fiscal 2017. The Company estimates the total investment in the complex will be approximately $153.0 million. As of April 30, 2016, the Company has incurred costs of approximately $46.3 million on the project, including approximately $265,000 of capitalized interest.
During fiscal 2015, the Company began construction on a new office building at the site of its corporate headquarters in Laurel, Mississippi. The Company estimates the total investment in the project will be approximately $10.0 million. As of April 30, 2016, the Company has incurred costs of approximately $9.6 million on the project, including approximately $185,000 of capitalized interest.
The Company is involved in various claims and litigation incidental to its business. Although the outcome of these matters cannot be determined with certainty, management, upon the advice of counsel, is of the opinion that the final outcome of currently pending matters should not have a material effect on the Company’s consolidated results of operations or financial position.
The Company recognizes the costs of legal defense for the legal proceedings to which it is a party in the periods incurred. After a considerable analysis of each case, the Company determines the amount of reserves required, if any. At this time, the Company has not accrued any reserve for any matters. Future reserves may be required if losses are deemed reasonably estimable and probable due to changes in the Company’s assumptions, the effectiveness of legal strategies, or other factors beyond the Company’s control. Future results of operations may be materially affected by the creation of reserves or by accruals of losses to reflect any adverse determinations in these legal proceedings.