XML 31 R11.htm IDEA: XBRL DOCUMENT v3.2.0.727
COMMITMENTS AND CONTINGENCIES
9 Months Ended
Jul. 31, 2015
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES
COMMITMENTS AND CONTINGENCIES
On September 19, 2013, the Company announced plans for construction of a new feed mill, hatchery, poultry processing plant and waste water facility on separate sites in Palestine, Anderson County, and Freestone County, Texas, and construction commenced in October 2013. The Company has substantially completed funding the project, and as of July 31, 2015, the Company has spent approximately $160.4 million on the project. Of the amount spent to date, approximately $50.1 million, including $335,000 of capitalized interest, was spent during the nine months ended July 31, 2015.
On March 12, 2015, the Company announced selection of St. Pauls and Robeson County, North Carolina, for the construction of a new poultry processing complex. The completed complex will consist of a hatchery, processing plant, waste water treatment facility, and an expansion of the Company's existing feed mill in Kinston, North Carolina. Construction commenced in July 2015, and initial operations of the new complex are expected to begin during the fourth quarter of fiscal 2016. The Company has entered into construction agreements related to the new complex totaling approximately $7.7 million. The Company's fiscal 2015 budget for the project is approximately $27.5 million, and as of July 31, 2015, the Company has spent approximately $11.4 million. The Company estimates the total cost of the project will be approximately $159.0 million.
The Company is involved in various claims and litigation incidental to its business. Although the outcome of these matters cannot be determined with certainty, management, upon the advice of counsel, is of the opinion that the final outcome should not have a material effect on the Company’s consolidated results of operations or financial position.
The Company recognizes the costs of legal defense for the legal proceedings to which it is a party in the periods incurred. After a considerable analysis of each case, the Company determines the amount of reserves required, if any. At this time, the Company has not accrued any reserve for any of these matters. Future reserves may be required if losses are deemed reasonably estimable and probable due to changes in the Company’s assumptions, the effectiveness of legal strategies, or other factors beyond the Company’s control. Future results of operations may be materially affected by the creation of reserves or by accruals of losses to reflect any adverse determinations in these legal proceedings.