XML 79 R14.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
Utility Plant
12 Months Ended
Dec. 31, 2019
Utility Plant [Abstract]  
Utility Plant Utility Plant
The following table presents electric, natural gas and common utility plant classified by account:
Puget EnergyPuget Sound Energy
Utility PlantEstimated Useful LifeDecember 31, December 31,
(Dollars in Thousands)(Years)2019201820192018
Distribution plant20-65$6,602,934  $6,122,739  $8,185,700  $7,722,024  
Production plant12-903,066,792  3,099,805  3,743,493  3,974,250  
Transmission plant43-751,463,288  1,442,854  1,571,186  1,550,950  
General plant5-75698,275  682,976  731,279  718,105  
Intangible plant (including capitalized software)1
3-50735,826  662,328  726,383  652,942  
Plant acquisition adjustmentN/A242,826  242,826  282,792  282,792  
Underground storage25-6037,511  35,404  50,963  48,874  
Liquefied natural gas storage25-6012,628  12,628  14,498  14,498  
Plant held for future useN/A46,233  39,384  46,385  39,536  
Recoverable Cushion GasN/A8,655  8,655  8,655  8,655  
Plant not classifiedN/A316,923  239,857  316,923  239,857  
Finance leases, net of accumulated amortization2
N/A1,488  1,315  1,488  1,315  
Less: accumulated provision for depreciation(3,236,240) (2,832,321) (5,682,606) (5,495,348) 
Subtotal$9,997,139  $9,758,450  $9,997,139  $9,758,450  
Construction work in progress591,199  550,466  591,199  550,466  
Net utility plant$10,588,338  $10,308,916  $10,588,338  $10,308,916  
_______________________
1.Intangible assets include capitalized software and franchise agreements with useful lives ranging between 3-10 years and 10-50 years, respectively.
2.At December 31, 2019, and 2018, accumulated amortization of capital leases at Puget Energy and PSE was $1.0 million and $1.3 million, respectively.

Jointly owned generating plant service costs are included in utility plant service cost at the Company's ownership share.  The Company provides financing for its ownership interest in the jointly owned utility plants. The following tables indicate the Company’s percentage ownership and the extent of the Company’s investment in jointly owned generating plants in service at December 31, 2019.  These amounts are also included in the Utility Plant table above. The Company's share of fuel costs and operating expenses for plant in service are included in the corresponding accounts in the Consolidated Statements of Income.

Puget Energy
Jointly Owned Generating Plants
(Dollars in Thousands)
Energy Source (Fuel)Company’s Ownership SharePlant in Service at CostConstruction Work in ProgressAccumulated Depreciation
Colstrip Units 3 & 4Coal25.00%  $323,100  $—  $(138,827) 
Frederickson 1Natural Gas49.85  61,820  —  (10,995) 
Jackson PrairieNatural Gas33.34  36,837  119  (8,452) 
Tacoma LNGNatural Gasvarious—  362,684  —  
Puget Sound Energy
Jointly Owned Generating Plants
(Dollars in Thousands)
Energy Source (Fuel)Company’s Ownership SharePlant in Service at CostConstruction Work in ProgressAccumulated Depreciation
Colstrip Units 3 & 4Coal25.00%  $582,372  $—  $(398,099) 
Frederickson 1Natural Gas49.85  67,888  —  (17,063) 
Jackson PrairieNatural Gas33.34  50,963  119  (22,578) 
Tacoma LNGNatural Gasvarious—  162,820  —  


In June 2019, Talen, the plant operator of Colstrip 1&2, announced a plan to shut down as of December 31, 2019. The Company retired Colstrip 1&2 from Utility Plant and transferred the unrecovered plant amount of $126.5 million to regulatory assets. Consistent with the GRC settlement in 2017, monetization of the PTCs will fund the following: (i) Colstrip Community Transition Fund, (ii) unrecovered Colstrip plant and (iii) incurred decommissioning and remediation costs for Colstrip. At December 31, 2019, the unrecovered plant for Colstrip 1&2 was fully offset with PTCs.

Asset Retirement Obligation
The Company has recorded liabilities for steam generation sites, combustion turbine generation sites, wind generation sites, distribution and transmission poles, natural gas mains, and leased facilities where disposal is governed by ASC 410 “Asset Retirement and Environmental Obligations" (ARO).
On April 17, 2015, the EPA published a final rule, effective October 19, 2015, that regulates Coal Combustion Residuals (CCR) under the Resource Conservation and Recovery Act, Subtitle D. The CCR ruling requires the Company to perform an extensive study on the effects of coal ash on the environment and public health. The rule addresses the risks from coal ash disposal, such as leaking of contaminants into ground water, blowing of contaminants into the air as dust, and the catastrophic failure of coal ash surface impoundments.
The CCR rule and two new legal agreements which include a consent decree with the Sierra Club and a settlement agreement with the Sierra Club and the National Wildlife Federation in 2016 make significant changes to the Company’s Colstrip operations and those changes were reviewed by the Company and the plant operator in 2015 and 2016. PSE had previously recognized a legal obligation in 2003 under the EPA rules to dispose of coal ash material at Colstrip.
The actual ARO costs related to the CCR rule requirements may vary substantially from the estimates used to record the increased obligation due to uncertainty about the compliance strategies that will be used and the preliminary nature of available data used to estimate costs. We will continue to gather additional data and coordinate with the plant operator to make decisions about compliance strategies and the timing of closure activities. As additional information becomes available, the Company will update the ARO obligation for these changes, which could be material.
For the twelve months ended December 31, 2019, the Company reviewed the estimated remediation costs at Colstrip and increased the Colstrip ARO liability by $4.2 million for Colstrip Units 1 and 2 and $0.5 million for Colstrip Units 3 and 4. The 2019 increase to the Colstrip ARO liability are primarily due to accelerated timing of activities due to the closure of Colstrip Units 1 and 2 at the end of 2019. For the twelve months ended December 31, 2018, the company reduced the Colstrip ARO liability by $11.0 million for Colstrip Units 1 and 2, and increased $1.8 million for Colstrip Units 3 and 4. The 2018 change to the Colstrip ARO liability is primarily based on the plant site remedy report approved by the Montana Department of Environmental Quality. For the twelve months ended December 31, 2019 and 2018, the Company also recorded the Colstrip relief of liability of $12.4 million and $4.8 million, respectively. In addition, the Company recorded Tacoma LNG facility ARO liability of $3.0 million and $2.7 million for PSE and $4.3 million and $1.7 million for Puget LNG as of December 31, 2019 and December 31, 2018, respectively. The 2019 increase to the Tacoma LNG facility ARO liability is primarily due to continued construction of the plant.
Puget Energy and Puget Sound EnergyDecember 31,
(Dollars in Thousands)20192018
Asset retirement obligation at beginning of the period$182,203  $191,176  
New asset retirement obligation recognized in the period—  501  
Relief of liability(12,449) (4,750) 
Revisions in estimated cash flows5,922  (10,512) 
Accretion expense5,677  5,788  
Asset retirement obligation at end of period1
$181,353  $182,203  
___________________
1.Asset retirement obligations include $4.3 million and $1.7 million for Puget LNG held only at PE as of December 31, 2019, and 2018, respectively.

The Company has identified the following obligations, as defined by ASC 410, “ARO,” which were not recognized because the liability for these assets cannot be reasonably estimated at December 31, 2019:
A legal obligation under Federal Dangerous Waste Regulations to dispose of asbestos-containing material in facilities that are not scheduled for remodeling, demolition or sales. The disposal cost related to these facilities could not be measured since the retirement date is indeterminable; therefore, the liability cannot be reasonably estimated;
An obligation under Washington state law to decommission the wells at the Jackson Prairie natural gas storage facility upon termination of the project.  Since the project is expected to continue as long as the Northwest pipeline continues to operate, the liability cannot be reasonably estimated;
An obligation to pay its share of decommissioning costs at the end of the functional life of the major transmission lines.  The major transmission lines are expected to be used indefinitely; therefore, the liability cannot be reasonably estimated;
A legal obligation under Washington state environmental laws to remove and properly dispose of certain under and above ground fuel storage tanks.  The disposal costs related to under and above ground storage tanks could not be measured since the retirement date is indeterminable; therefore, the liability cannot be reasonably estimated;
An obligation to pay decommissioning costs at the end of utility service franchise agreements to restore the surface of the franchise area. The decommissioning costs related to facilities at the franchise area could not be measured since the decommissioning date is indeterminable; therefore, the liability cannot be reasonably estimated; and
A potential legal obligation may arise upon the expiration of an existing FERC hydropower license if FERC orders the project to be decommissioned, although PSE contends that FERC does not have such authority.  Given the value of ongoing generation, flood control and other benefits provided by these projects, PSE believes that the potential for decommissioning is remote and cannot be reasonably estimated.