XML 59 R22.htm IDEA: XBRL DOCUMENT v3.23.3
RESTRUCTURING-RELATED ACTIVITIES
9 Months Ended
Sep. 24, 2023
Restructuring and Related Activities [Abstract]  
RESTRUCTURING-RELATED ACTIVITIES RESTRUCTURING-RELATED ACTIVITIES
In 2022, the Company began restructuring initiatives to phase out and reduce processing volumes at multiple production facilities throughout the U.K. and Europe reportable segment. Implementation of these initiatives is expected to result in total pre-tax charges of approximately $69.7 million, and approximately $45.1 million of these charges are estimated to result in cash outlays. These activities were initiated in the fourth quarter of 2022 and were nearing completion by the end of the third quarter of 2023.
The following table provides a summary of our estimates of costs associated with these restructuring initiatives by major type of cost:
Moy ParkPilgrim’s Pride Ltd.Pilgrim’s Food MastersTotal
(In thousands)
Earliest implementation dateOctober 2022November 2022December 2022
Expected predominant completion dateJune 2023July 2023July 2023
Costs incurred and expected to be incurred:
Employee-related costs$10,972 $19,400 $12,633 $43,005 
Asset impairment costs3,236 — 4,141 7,377 
Contract termination costs248 — 24 272 
Other exit and disposal costs (a)
6,601 6,427 5,998 19,026 
Total exit and disposal costs$21,057 $25,827 $22,796 $69,680 
Cost incurred since earliest implementation date:
Employee-related costs$10,972 $19,400 $12,420 $42,792 
Asset impairment costs3,236 — 4,141 7,377 
Contract termination costs248 — — 248 
Other exit and disposal costs (a)
6,224 6,510 5,998 18,732 
Total exit and disposal costs$20,680 $25,910 $22,559 $69,149 
(a)Comprised of other costs directly related to the restructuring initiatives including Moy Park flock depletion, the write-off of Pilgrim’s Pride Ltd. prepaid maintenance costs and Pilgrim’s Food Masters consulting fees.
During the nine months ended September 24, 2023, the Company recognized the following expenses and paid the following cash related to each restructuring initiative:
ExpensesCash Outlays
(In thousands)
Moy Park$1,355 $6,855 
Pilgrim’s Pride Ltd.15,771 19,517 
Pilgrim’s Food Masters21,558 19,496 
$38,684 $45,868 
These expenses are reported in the line item Restructuring activities on the Condensed Consolidated Statements of Income.
The following table reconciles liabilities and reserves associated with each restructuring initiative from its respective inception to September 24, 2023. Ending liability balances for employee termination benefits and other charges are reported in the line item Accrued expenses and other current liabilities in our Condensed Consolidated Balance Sheets. The ending reserve balance for inventory adjustments is reported in the line item Inventories in our Condensed Consolidated Balance Sheets. The ending reserve balance for asset impairments is reported in the line item Property, plant and equipment, net in our Condensed Consolidated Balance Sheets.
Moy Park
Liability or reserve as of December 25, 2022Restructuring charges incurredCash payments and disposalsCurrency translationLiability or reserve as of September 24, 2023
(In thousands)
Asset impairment$2,391 $(323)$(2,514)$446 $— 
Inventory adjustments47 (48)— — 
Other charges6,025 141 (2,819)(329)3,018 
Other employee costs— 1,364 (1,364)— — 
Contract termination122 126 (110)— 138 
Total$8,539 $1,355 $(6,855)$117 $3,156 
Pilgrim’s Pride Ltd.
Liability or reserve as of December 25, 2022Restructuring charges incurredCash payments and disposalsCurrency translationLiability or reserve as of September 24, 2023
(In thousands)
Employee retention benefits$— $1,838 $(1,800)$$43 
Severance5,503 9,355 (14,083)158 933 
Inventory adjustments615 372 (722)18 283 
Lease termination800 (67)— 15 748 
Other charges501 4,273 (2,912)(10)1,852 
Total$7,419 $15,771 $(19,517)$186 $3,859 
Pilgrim’s Food Masters
Liability or reserve as of December 25, 2022Restructuring charges incurredCash payments and disposalsCurrency translationLiability or reserve as of September 24, 2023
(In thousands)
Severance$639 $11,457 $(11,975)$48 $169 
Asset impairment— 4,141 (4,143)— 
Inventory adjustments— 793 (728)(4)61 
Lease termination— 1,219 — 27 1,246 
Other charges— 3,948 (2,650)(12)1,286 
Total$639 $21,558 $(19,496)$61 $2,762