XML 19 R9.htm IDEA: XBRL DOCUMENT v2.4.0.6
OIL AND GAS CONCESSIONS
9 Months Ended
Jun. 30, 2012
OIL AND GAS CONCESSIONS [Abstract]  
OIL AND GAS CONCESSIONS
NOTE 3 - OIL AND GAS CONCESSIONS

The following is an analysis of the cost of oil and gas concessions at June 30, 2012 and September 30, 2011:

 
 
June 30,
2012
 
 
September 30,
2011
 
 
 
 
 
 
 
 
DRSTP concession
 
$
2,840,700
 
 
$
2,839,500
 
Chad concession
 
 
1,792,600
 
 
 
1,760,000
 
Kenya concession
310,000
-
Pending concessions in other African countries
 
 
70,430
 
 
 
21,031
 
 
 
 
 
 
 
 
 
 
 
 
$
5,013,730
 
 
$
4,620,531
 

Kenya Concession Fees and Other Financial Commitments

On June 28, 2012, ERHC entered into a production sharing contract ("PSC") with the Government of the Republic of Kenya for certain land based hydrocarbon exploration and development.

As of June 30, 2012, the Company had paid in full the requisite signature bonus of $310,000 and is committed under terms of the PCS to spend at least $10,250,000 over the first two years on a minimum work program and an additional $60,000,000 in each of the following two periods of two years each.
 
Additionally, ERHC will pay surface fees per square kilometer per annum as follows:
 
 
 
USD
 
 
 
 
Initial Exploration Term
 
$
5.00
 
First Additional Exploration Period
 
 
10.00
 
Second Additional Exploration Period
15.00
Development and Production Periods
 
 
100.00
 
 
Republic of Chad Concession Fees and Other Financial Commitments

On June 30, 2011, ERHC entered into a PSC with Chad for certain land based hydrocarbon exploration and development.

As of June 30, 2012, the Company has paid or incurred:

a.
$1,000,000 out of a signature bonus commitment of $6,000,000 under the PSC (leaving a balance of $5,000,000 to be completed within 90 days of the publication of Approval Law in the  Journel Officiel,  an official publication of the Government of Chad (which has occurred as of the date hereof)
b.
$480,000 as legal fees and costs for the drafting and negotiation of the PSC, as provided for in the PSC
c.
$312,600 in advisers' and ancillary costs related to the PSC

ERHC is also committed under the PSC to spend at least $15,000,000 over the first five years on a minimum work program and at least an additional $1,000,000 over a further period of up to three years.

Sao Tome Concession

In April 2003, the Company and the DRSTP entered into an Option Agreement (the "2003 Option Agreement") in which the Company relinquished certain financial interests in the JDZ in exchange for exploration rights in the JDZ.  The Company additionally entered into an administration agreement with the Nigeria-Sao Tome and Principe JDA.  The administration agreement is the formal agreement by the JDA that it will fully implement ERHC's preferential rights to working interests in the JDZ acreage as set forth in the 2003 Option Agreement and describes certain procedures regarding the exercising of these rights.  However, ERHC retained under a previous agreement the following rights to participate in exploration and production activities in the EEZ subject to certain restrictions:  (a) the right to receive 100% working interest signature free bonus of two blocks of ERHC's choice and (b) the option to acquire up to a 15% paid working interest in up to two additional blocks of ERHC's choice in the EEZ.  The Company would be responsible for its proportionate share of exploration and exploitation costs in the EEZ blocks.
 
The following represents ERHC's current rights in the JDZ and EEZ blocks:
 
Block
ERHC Original
Participating
Interest
ERHC Joint Bid
Participating
Interest
Participating
Interest(s) Sold
Current ERHC
 Retained
Participating
Interest
 
Remaining
Cost
Allocated to
Blocks
 
 
 
 
 
 
 
 
 
JDZ 2
30.00%
35.00%
43.00%
22.00%
 
$
-
 
JDZ 3
20.00%
5.00%
15.00%
10.00%
 
 
-
 
JDZ 4
25.00%
35.00%
40.50%
19.50%
 
 
-
 
JDZ 5
15.00%
-
-
15.00% (in arbitration)
 
 
567,900
 
JDZ 6
15.00%
-
-
15.00% (in arbitration)
 
 
567,900
 
JDZ 9
20.00%
-
-
20.00%
 
 
567,900
 
EEZ 4
100.00%
 
 
 
 
 
567,900
 
EEZ 11
100.00%
 
 
 
 
 
567,900
 

The Original Participating Interest is the interest granted pursuant to the Option Agreement, dated April 2, 2003, between DRSTP and ERHC (the "2003 Option Agreement").

Under the terms each of the Participation Agreements Sinopec and Addax agreed to pay all of ERHC's future costs for petroleum operations ("the carried costs") in respect of ERHC's retained interests in JDZ blocks 2,3 and 4. Additionally, Sinopec and Addax are entitled to 100% of ERHC's allocation of cost oil plus up to 50% of ERHC's allocation of profit oil from the retained interests on individual blocks until Sinopec and Addax Sub recover 100% of ERHC's carried costs.

The remaining $2,839,500 of cost related to the DRSTP concession, as shown on the Company's balance sheet at June 30, 2012 and September 30, 2011, relate to blocks 5, 6 and 9 of the JDZ, and the Company's EEZ blocks on which Production Sharing Contracts are yet to be signed by ERHC.