XML 71 R57.htm IDEA: XBRL DOCUMENT v3.3.1.900
Commitments and Contingent Liabilities (Additional Information) (Details)
$ in Millions
1 Months Ended 3 Months Ended 105 Months Ended
Dec. 31, 2008
USD ($)
shares
May. 14, 2002
USD ($)
shares
Mar. 31, 2016
USD ($)
Location
LegalMatter
Mar. 31, 2015
USD ($)
Mar. 31, 2000
USD ($)
Sep. 30, 2014
LegalMatter
Dec. 31, 2015
USD ($)
Dec. 31, 2014
USD ($)
Jun. 30, 2013
LegalMatter
Dec. 31, 2011
Location
Commitments and Contingencies Disclosure [Line Items]                    
Interest Penalty Asserted by a Foreign Tax Authority       $ 70.0            
Reserves for environmental contingencies     $ 227.0       $ 233.0      
Accrual for Environmental Loss Contingencies, Component Amount     3.6              
Reserves for environmental contingencies classified as current liabilities     57.0       51.0      
Unreserved loss contingencies related to environmental matters, low estimate     75.0              
Unreserved loss contingencies related to environmental matters, high estimate     200.0              
Outstanding letters of credit     175.0              
Guarantees     25.0              
Payments for Environmental Liabilities     14.0 36.0            
Jersey City Manufacturing Plant [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
Reserves for environmental contingencies     $ 126.0       133.0      
Orphan Sites Settlement [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
Total number of sites to be remediated | Location     6              
Judicial Consent Order [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
Total number of sites to be remediated | Location     19             20
Other Environmental Contingencies [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
Reserves for environmental contingencies     $ 101.0       $ 100.0      
Environmental remediation charge     $ 5.0 $ 4.0            
Asbestos Issue [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
Number of pending cases | LegalMatter     114,000           114,000  
Loss Contingency, Claims Settled, Number | LegalMatter           580        
Loss Contingency, Number of Plaintiffs | LegalMatter           255        
Loss Contingency Claims in the Process of Being Settled | LegalMatter           45        
Loss Contingency Number of Claims not in the Process of Being Settled. | LegalMatter           210        
Loss Contingency Claims Being Litigated. | LegalMatter     115              
Reduction in cash obligation to the Trust, corresponding increase in reserve for PPG claims responsibility $ 162.0                  
PPG's reserve for asbestos-related claims that will not be channeled to the Trust     $ 162.0         $ 162.0    
Asbestos Issue [Member] | Maximum [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
Percentage of premises claims currently comprised of the total of asbestos related claims against PPG     2.00%              
Soil Treatment, Transportation And Disposal Of Excavated Soil [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
Percentage of the total remaining reserve     38.00%              
Construction Services (Related To Soil Excavation, Groundwater Management And Site Security) [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
Percentage of the total remaining reserve     34.00%              
Pittsburgh Corning Corporation [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
PPG percent ownership interest     50.00%              
After-tax charge, write-off of investment in PC, related to PC filing for chapter 11 bankruptcy         $ 35.0          
Number of days after effective date of a confirmed reorganization plan         30 days          
Pittsburgh Corning Corporation [Member] | Asbestos Issue [Member]                    
Commitments and Contingencies Disclosure [Line Items]                    
Number of days after second amended reorganization plan   30 days                
Agreement to convey assets to the PC asbestos settlement trust (the "Trust"), shares of PPG common stock | shares 2,777,778 2,777,778                
Future PPG cash payments to the Trust $ 825.0 $ 998.0                
Future PPG cash payments to the Trust, prepayment discount rate 5.50% 5.50%                
Future PPG legal fees and expenses on behalf of the Trust   $ 30.0                
Fixed payment schedule, period   21 years                
Fixed payment schedule, effective date   June 30, 2003                
Future cash payments to the Trust by PPG's participating historical insurance carriers $ 1,700.0 $ 1,700.0                
Future cash payments to the Trust by PPG's participating historical insurance carriers, prepayment discount rate 5.50% 5.50%                
Period of funding effective date     30 days