XML 30 R22.htm IDEA: XBRL DOCUMENT v3.24.4
LEASES
6 Months Ended
Dec. 31, 2024
Leases [Abstract]  
LEASES

NOTE 13 LEASES

We have operating and finance leases for datacenters, corporate offices, research and development facilities, Microsoft Experience Centers, and certain equipment. Our leases have remaining lease terms of less than 1 year to 20 years, some of which include options to extend the leases for up to 5 years, and some of which include options to terminate the leases within 1 year.

The components of lease expense were as follows:

 

(In millions)

Three Months Ended

December 31,

 

 

 

Six Months Ended

December 31,

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2024

2023

 

 

 

2024

 

 

 

2023

 

 

 

 

 

 

 

 

 

 

 

 

Operating lease cost

 

$

1,293

$

817

 

 

$

2,453

 

 

$

1,591

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Finance lease cost:

 

 

 

 

 

 

 

 

 

 

 

 

Amortization of right-of-use assets

$

830

$

408

 

 

$

1,524

 

 

$

788

 

Interest on lease liabilities

337

168

 

 

 

611

 

 

 

317

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total finance lease cost

$

1,167

$

576

 

 

$

2,135

 

 

$

1,105

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Supplemental cash flow information related to leases was as follows:

 

(In millions)

 

Three Months Ended

December 31,

 

 

 

Six Months Ended

December 31,

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2024

2023

 

 

2024

 

 

 

2023

 

 

 

 

 

 

 

 

 

 

 

 

Cash paid for amounts included in the measurement of lease liabilities:

 

 

 

 

 

 

 

 

 

 

 

 

Operating cash flows from operating leases

 

$

962

 

 

$

803

 

$

2,169

 

 

$

1,597

 

Operating cash flows from finance leases

 

 

319

168

 

 

594

 

 

 

317

 

Financing cash flows from finance leases

 

 

480

288

 

 

 

1,282

 

 

 

573

 

 

 

 

 

 

 

 

 

 

 

 

Right-of-use assets obtained in exchange for lease obligations:

 

 

 

 

 

 

 

 

 

 

 

 

Operating leases

 

3,098

847

 

 

4,991

 

 

 

2,651

 

Finance leases

 

6,435

1,796

 

 

10,767

 

 

 

3,500

 

 

 

 

 

 

 

 

 

 

 

Supplemental balance sheet information related to leases was as follows:

 

(In millions, except lease term and discount rate)

December 31,

2024

June 30,

2024

Operating Leases

 

 

 

 

Operating lease right-of-use assets

$

22,816

$

18,961

 

 

 

 

Other current liabilities

$

4,608

$

3,580

Operating lease liabilities

17,254

15,497

 

 

 

 

Total operating lease liabilities

 

$

21,862

 

 

$

19,077

 

 

 

 

 

Finance Leases

 

 

 

 

Property and equipment, at cost

$

42,539

 

 

$

32,248

 

Accumulated depreciation

(7,650

)

 

 

(6,386

)

 

 

 

 

Property and equipment, net

$

34,889

$

25,862

 

 

 

 

 

Other current liabilities

 

$

2,673

$

2,349

Other long-term liabilities

33,404

24,796

 

 

 

 

Total finance lease liabilities

$

36,077

$

27,145

 

 

 

 

Weighted Average Remaining Lease Term

 

 

 

 

Operating leases

7 years

7 years

Finance leases

12 years

12 years

 

 

Weighted Average Discount Rate

 

 

 

 

Operating leases

3.4%

3.3%

Finance leases

4.0%

3.9%

 

 

 

The following table outlines maturities of our lease liabilities as of December 31, 2024:

 

(In millions)

Year Ending June 30,

Operating Leases

Finance Leases

2025 (excluding the six months ended December 31, 2024)

$

2,726

$

1,979

2026

4,920

4,149

2027

 

4,063

 

 

4,180

2028

3,025

4,175

2029

 

2,203

 

3,528

Thereafter

7,433

28,350

 

 

 

 

Total lease payments

24,370

 

46,361

Less imputed interest

(2,508

)

(10,284

)

 

 

 

 

Total

$

21,862

$

36,077

 

 

 

As of December 31, 2024, we had additional operating and finance leases, primarily for datacenters, that had not yet commenced of $6.0 billion and $99.4 billion, respectively. These operating and finance leases will commence between fiscal year 2025 and fiscal year 2030 with lease terms of 1 year to 25 years.