Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4 - USD ($)
$ in Millions
9 Months Ended
Feb. 18, 2019
Sep. 30, 2023
Actual Costs    
Proceeds from guarantee agreement   $ 1,100
Global Amendments to Term Sheet    
Project Budget    
Total Project Costs   17,100
Actual Costs    
Additional construction costs $ 800  
Financial Exposure Term Two | Maximum | Global Amendments to Term Sheet    
Actual Costs    
Additional construction costs $ 2,100  
Jointly Owned Nuclear Power Plant    
Project Budget    
Construction Costs   6,208
Financing Costs   2,046
Subtotal   8,254
Deferred Training Costs   46
Total Project Costs   8,300
Actual Costs    
Construction Costs   6,413
Financing Costs   1,974
Subtotal   8,387
Deferred Training Costs   47
Total Project Costs   8,434
Jointly Owned Nuclear Power Plant | Global Amendments to Term Sheet    
Project Budget    
Total Project Costs   $ 17,100