Vogtle Units No. 3 and No. 4 Construction Project (Tables)
9 Months Ended
Sep. 30, 2023
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our current project budget and actual costs through September 30, 2023 for our share of the project.
(in millions)
Project BudgetActual Costs at
September 30, 2023
Construction Costs (1)
$6,208 $6,413 
Financing Costs2,046 1,974 
   Subtotal$8,254 $8,387 

Deferred Training Costs46 47 
Total Project Costs$8,300 $8,434 
(1) Construction costs are net of $1.1 billion we received from Toshiba Corporation under a Guarantee Settlement Agreement.