Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4 - USD ($)
$ in Millions
6 Months Ended
Feb. 18, 2019
Jun. 30, 2023
Actual Costs    
Proceeds from guarantee agreement   $ 1,100
Cost sharing benefits   99
Investment in excess of tender option   300
Global Amendments To Term Sheet    
Project Budget    
Totals   17,100
Actual Costs    
Additional construction costs $ 800  
Financial Exposure Term Two | Maximum | Global Amendments To Term Sheet    
Actual Costs    
Additional construction costs $ 2,100  
Jointly Owned Nuclear Power Plant    
Project Budget    
Construction Costs   6,559
Freeze Capital Credit   (532)
Financing Costs   2,038
Subtotal   8,065
Deferred Training Costs   47
Total Project Costs Before Contingency   8,112
Oglethorpe Contingency   3
Totals   8,115
Actual Costs    
Construction Costs   6,393
Freeze Capital Credit   0
Financing Costs   1,925
Subtotal   8,318
Deferred Training Costs   47
Total Project Costs Before Contingency   8,365
Oglethorpe Contingency   0
Totals   8,365
Jointly Owned Nuclear Power Plant | Global Amendments To Term Sheet    
Project Budget    
Totals   $ 17,100