Vogtle Units No. 3 and No. 4 Construction Project (Tables)
6 Months Ended
Jun. 30, 2023
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our project budget and actual costs through June 30, 2023 for our share of the project.
(in millions)
Project BudgetActual Costs at
June 30, 2023
Construction Costs (1)
$6,559 $6,393 
Freeze Capital Credit (2)
(532)— 
Financing Costs2,038 1,925 
   Subtotal$8,065 $8,318 
(3)
Deferred Training Costs47 47 
   Total Project Costs Before Contingency $8,112 $8,365 
Oglethorpe Contingency$$— 
Totals$8,115 $8,365 
(1) Construction costs are net of $1.1 billion we received from Toshiba Corporation under a Guarantee Settlement Agreement and $99 million in cost sharing benefits associated with the Global Amendments to the Joint Ownership Agreements.
(2) As described below, we exercised the tender option to cap our capital costs at the EAC in VCM 19 plus $2.1 billion, the freeze tender threshold. The freeze capital credit reflects our share of budgeted amounts that exceed this threshold.
(3) At June 30, 2023, approximately $300 million relates to costs that exceed the tender option threshold that is the subject of litigation between us and Georgia Power.