Vogtle Units No. 3 and No. 4 Construction Project (Tables)
3 Months Ended
Mar. 31, 2023
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our project budget and actual costs through March 31, 2023 for our share of the project.
(in millions)
Project BudgetActual Costs at
March 31, 2023
Construction Costs (1)
$6,559 $6,286 
Freeze Capital Credit (2)
(532)— 
Financing Costs2,038 1,844 
   Subtotal$8,065 $8,130 
(3)
Deferred Training Costs47 47 
   Total Project Costs Before Contingency $8,112 $8,177 
Oglethorpe Contingency$$— 
Totals$8,115 $8,177 
(1) Construction costs are net of $1.1 billion we received from Toshiba Corporation under a Guarantee Settlement Agreement and $99 million in cost sharing benefits associated with the Global Amendments to the Joint Ownership Agreements.
(2) As described below, we exercised the tender option to cap our capital costs at the EAC in VCM 19 plus $2.1 billion, the freeze tender threshold. The freeze capital credit reflects our share of budgeted amounts that exceed this threshold.
(3) At March 31, 2023, approximately $200 million relates to costs that exceed the tender option threshold that is the subject of litigation between us and Georgia Power.