XML 124 R72.htm IDEA: XBRL DOCUMENT v3.23.1
Electric plant, construction and related agreements - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4 - USD ($)
$ in Millions
12 Months Ended
Feb. 18, 2019
Dec. 31, 2022
Actual Costs at December 31, 2022    
Proceeds from guarantee agreement   $ 1,100
Cost sharing benefits   99
Global Amendments to Term Sheet    
Project Budget (Tender)    
Totals   17,100
Actual Costs at December 31, 2022    
Additional construction costs $ 800  
Financial Exposure Term Two | Maximum | Global Amendments to Term Sheet    
Actual Costs at December 31, 2022    
Additional construction costs $ 2,100  
Jointly Owned Nuclear Power Plant    
Project Budget (Tender)    
Construction Costs   6,554
Freeze Capital Credit   (528)
Financing Costs   2,025
Subtotal   8,051
Deferred Training Costs   47
Total Project Costs Before Contingency   8,098
Oglethorpe Contingency   2
Totals   8,100
Actual Costs at December 31, 2022    
Construction Costs   6,147
Freeze Capital Credit   0
Financing Costs   1,770
Subtotal   7,917
Deferred Training Costs   46
Total Project Costs Before Contingency   7,963
Oglethorpe Contingency   0
Totals   7,963
Jointly Owned Nuclear Power Plant | Global Amendments to Term Sheet    
Project Budget (Tender)    
Totals   $ 17,100