XML 123 R71.htm IDEA: XBRL DOCUMENT v3.23.1
Electric plant, construction and related agreements - Narrative (Details)
$ in Millions
12 Months Ended
Feb. 18, 2019
USD ($)
Dec. 31, 2022
USD ($)
unit
MW
Dec. 31, 2021
USD ($)
Loan Guarantee Agreement      
Public Utility Property Plant and Equipment      
Term of debt   5 years  
Vogtle Units No. 3 & No. 4      
Public Utility Property Plant and Equipment      
Total investment in additional Vogtle units   $ 8,000  
Ownership interest (as a percent)   30.00%  
Monthly delay cost, exercise of tender option   $ 30  
Remaining share paid by counterparty upon exercise of tender option (as a percent)   100.00%  
Budget increases since the nineteenth VCM     $ 3,400
Percentage of disallowed costs excluded from adverse event triggers   6.00%  
Vogtle Units No. 3 & No. 4 | Jointly Owned Nuclear Power Plant      
Public Utility Property Plant and Equipment      
Release of generating capacity with exercise of tender option (in megawatts) | MW   55  
Proportionate ownership share with exercise of tender option (as a percent)   27.50%  
Total project cost   $ 8,100  
Vogtle Units No. 3 & No. 4 | Financial Exposure Term One      
Public Utility Property Plant and Equipment      
Ownership interest (as a percent)   30.00%  
Vogtle Units No. 3 & No. 4 | Financial Exposure Term Two      
Public Utility Property Plant and Equipment      
Ownership interest (as a percent)   30.00%  
Vogtle Units No. 3 & No. 4 | Minimum      
Public Utility Property Plant and Equipment      
COVID related costs   $ 350  
Vogtle Units No. 3 & No. 4 | Maximum      
Public Utility Property Plant and Equipment      
COVID related costs   $ 438  
Vogtle Units No. 3 & No. 4 | EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.      
Public Utility Property Plant and Equipment      
Number of nuclear units | unit   2  
Generating capacity (in megawatts) | MW   1,100  
Vogtle Units No. 3 & No. 4 | Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.      
Public Utility Property Plant and Equipment      
Written notice period for termination of agreement   30 days  
Vogtle Units No. 3 & No. 4 | Ownership participation agreement      
Public Utility Property Plant and Equipment      
Project budget   $ 8,100  
Project budget had tender option not been exercised   $ 8,650  
Ownership share, generating capacity (in megawatts) | MW   660  
Construction cost savings due to exercise of tender option   $ 530  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet      
Public Utility Property Plant and Equipment      
Project budget $ 8,400    
Additional construction costs $ 800    
Total project cost   17,100  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Jointly Owned Nuclear Power Plant      
Public Utility Property Plant and Equipment      
Total project cost   17,100  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Jointly Owned Nuclear Power Plant | Georgia Power      
Public Utility Property Plant and Equipment      
Project budget   8,650  
Total project cost   18,380  
Increase in project budget based on Georgia Power's interpretation   $ 530  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Financial Exposure Term One      
Public Utility Property Plant and Equipment      
Proportionate share of construction costs, co-owner (as a percent) 55.70%    
Additional construction costs, responsibility of co-owner $ 80    
Proportionate share of additional construction costs $ 44    
Proportionate share of construction costs, remaining co-owners (as a percent) 44.30%    
Proportionate share of construction costs (as a percent) 24.50%    
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Financial Exposure Term Two      
Public Utility Property Plant and Equipment      
Proportionate share of construction costs, co-owner (as a percent) 65.70%    
Additional construction costs, responsibility of co-owner $ 100    
Proportionate share of additional construction costs $ 55    
Proportionate share of construction costs, remaining co-owners (as a percent) 34.30%    
Proportionate share of construction costs (as a percent) 19.00%    
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Financial Exposure Term Three      
Public Utility Property Plant and Equipment      
Additional construction costs triggering option to tender ownership $ 2,100    
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum      
Public Utility Property Plant and Equipment      
Ownership approval to change primary construction contractor (as a percent)   90.00%  
Ownership approval required to continue construction (as a percent)   90.00%  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | Financial Exposure Term One      
Public Utility Property Plant and Equipment      
Additional construction costs 800    
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | Financial Exposure Term Two      
Public Utility Property Plant and Equipment      
Additional construction costs 1,600    
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | Financial Exposure Term Three      
Public Utility Property Plant and Equipment      
Additional construction costs triggering option to tender ownership 800    
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | Financial Exposure Term One      
Public Utility Property Plant and Equipment      
Additional construction costs 1,600    
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | Financial Exposure Term Two      
Public Utility Property Plant and Equipment      
Additional construction costs 2,100    
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | Financial Exposure Term Three      
Public Utility Property Plant and Equipment      
Additional construction costs triggering option to tender ownership $ 2,100    
Vogtle Unit Number 4      
Public Utility Property Plant and Equipment      
Monthly delay cost, exercise of tender option   $ 13