Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4
$ in Millions
9 Months Ended
Sep. 30, 2022
USD ($)
Actual Costs  
Proceeds from guarantee agreement $ 1,100
Cost sharing benefits 99
Jointly Owned Nuclear Power Plant  
Project Budget (Tender)  
Construction Costs 6,025
Financing Costs 1,974
Subtotal 7,999
Deferred Training Costs 49
Total Project Costs Before Contingency 8,048
Oglethorpe-Level Contingency 52
Total Contingency 52
Totals 8,100
Actual Costs  
Construction Costs 6,000
Financing Costs 1,695
Subtotal 7,695
Deferred Training Costs 46
Total Project Costs Before Contingency 7,741
Oglethorpe-Level Contingency 0
Total Contingency 0
Totals $ 7,741