Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4
$ in Millions
6 Months Ended
Jun. 30, 2022
USD ($)
Actual Costs at June 30, 2022  
Proceeds from guarantee agreement $ 1,100
Cost sharing benefits 99
Jointly Owned Nuclear Power Plant  
Project Budget (Tender)  
Construction Costs 6,021
Financing Costs 1,966
Subtotal 7,987
Deferred Training Costs 54
Total Project Costs Before Contingency 8,041
Oglethorpe-Level Contingency 59
Total Contingency 59
Totals 8,100
Actual Costs at June 30, 2022  
Construction Costs 5,842
Financing Costs 1,626
Subtotal 7,468
Deferred Training Costs 46
Total Project Costs Before Contingency 7,514
Oglethorpe-Level Contingency 0
Total Contingency 0
Totals $ 7,514