Vogtle Units No. 3 and No. 4 Construction Project (Tables)
6 Months Ended
Jun. 30, 2022
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our project budget and actual costs through June 30, 2022 for our share of the project.
(in millions)
Project Budget (Tender)Actual Costs at
June 30, 2022
Construction Costs (1)
$6,021 $5,842 
Financing Costs1,966 1,626 
   Subtotal$7,987 $7,468 
Deferred Training Costs54 46 
   Total Project Costs Before Contingency $8,041 $7,514 
Oglethorpe-Level Contingency59 — 
   Total Contingency$59 $— 
Totals$8,100 $7,514 
(1) Construction costs are net of $1.1 billion we received from Toshiba Corporation under a Guarantee Settlement Agreement and $99 million in cost sharing benefits associated with the Global Amendments to the Joint Ownership Agreements.