Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4
$ in Millions
3 Months Ended
Mar. 31, 2022
USD ($)
Actual Costs at March 31, 2022  
Proceeds from guarantee agreement $ 1,100
Jointly Owned Nuclear Power Plant  
Project Budget - No Tender  
Construction Costs 6,487
Financing Costs 1,922
Total Costs 8,409
Project-Level Contingency 70
Oglethorpe-Level Contingency 21
Total Contingency 91
Totals 8,500
Project Budget - Tender  
Construction Costs 6,096
Financing Costs 1,914
Total Costs 8,010
Project-Level Contingency 70
Oglethorpe-Level Contingency 20
Total Contingency 90
Totals 8,100
Actual Costs at March 31, 2022  
Construction Costs 5,621
Financing Costs 1,561
Total Costs 7,182
Project-Level Contingency 0
Oglethorpe-Level Contingency 0
Total Contingency 0
Totals $ 7,182