Electric plant, construction and related agreements - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4
$ in Millions
12 Months Ended
Dec. 31, 2021
USD ($)
Project Budget - No Tender  
Project-Level Contingency $ 65
Actual Costs at December 31, 2021  
Proceeds from guarantee agreement 1,100
Jointly Owned Nuclear Power Plant  
Project Budget - No Tender  
Construction Costs 6,459
Financing Costs 1,922
Total Costs 8,381
Project-Level Contingency 98
Oglethorpe-Level Contingency 21
Total Contingency 119
Totals 8,500
Project Budget - Tender  
Construction Costs 6,068
Financing Costs 1,914
Total Costs 7,982
Project-Level Contingency 98
Oglethorpe-Level Contingency 20
Total Contingency 118
Totals 8,100
Actual Costs at December 31, 2021  
Construction Costs 5,483
Financing Costs 1,502
Total Costs 6,985
Project-Level Contingency 0
Oglethorpe-Level Contingency 0
Total Contingency 0
Totals $ 6,985