Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4 - USD ($)
$ in Millions
3 Months Ended 9 Months Ended
Sep. 30, 2021
Jun. 30, 2021
Mar. 31, 2021
Dec. 31, 2020
Sep. 30, 2021
Project Budget          
Project-Level Contingency $ 90.0 $ 78.0 $ 32.0 $ 112.5  
Actual Costs          
Totals         $ 17,100.0
Remaining Project Budget          
Proceeds from guarantee agreement         1,100.0
Jointly Owned Nuclear Power Plant          
Project Budget          
Construction Costs         6,140.0
Financing Costs         1,778.0
Total Costs         7,918.0
Project-Level Contingency         90.0
Oglethorpe-Level Contingency         242.0
Total Contingency         332.0
Totals         8,250.0
Actual Costs          
Construction Costs         5,342.0
Financing Costs         1,443.0
Total Costs         6,785.0
Project-Level Contingency         0.0
Oglethorpe-Level Contingency         0.0
Total Contingency         0.0
Totals         6,785.0
Remaining Project Budget          
Construction Costs         798.0
Financing Costs         335.0
Total Costs         1,133.0
Project-Level Contingency         90.0
Oglethorpe-Level Contingency         242.0
Total Contingency         332.0
Totals         $ 1,465.0