Vogtle Units No. 3 and No. 4 Construction Project - Narrative (Details)
$ in Millions
3 Months Ended 9 Months Ended 12 Months Ended
Feb. 18, 2019
USD ($)
Sep. 30, 2021
USD ($)
Jun. 30, 2021
USD ($)
Mar. 31, 2021
USD ($)
Dec. 31, 2020
USD ($)
Sep. 30, 2021
USD ($)
unit
Dec. 31, 2008
unit
MW
Vogtle Units No. 3 & No. 4              
Public Utility Property Plant and Equipment              
Ownership interest (as a percent)   30.00%       30.00%  
Total investment in additional Vogtle units   $ 6,800.0       $ 6,800.0  
Additional construction contingency, total   300.0 $ 260.0 $ 106.0 $ 375.0    
Project-Level Contingency   90.0 78.0 32.0 $ 112.5    
Additional construction contingency, construction productivity and field support   278.0 746.0 183.0      
Ownership amount of additional construction contingency, construction productivity and field support   $ 83.0 224.0 $ 55.0      
Project level contingency     300.0        
Ownership amount of project level contingency     $ 90.0        
Monthly delay cost           55.0  
Total project costs           17,100.0  
Total budget revisions           $ 2,400.0  
Vogtle Units No. 3 & No. 4 | Financial Exposure Term One              
Public Utility Property Plant and Equipment              
Ownership interest (as a percent)   30.00%       30.00%  
Vogtle Units No. 3 & No. 4 | Financial Exposure Term Two              
Public Utility Property Plant and Equipment              
Ownership interest (as a percent)   30.00%       30.00%  
Vogtle Units No. 3 & No. 4 | Minimum              
Public Utility Property Plant and Equipment              
COVID related costs           $ 350.0  
Ownership amount of COVID related costs           105.0  
Vogtle Units No. 3 & No. 4 | Maximum              
Public Utility Property Plant and Equipment              
COVID related costs           438.0  
Ownership amount of COVID related costs           $ 131.0  
Vogtle Units No. 3 & No. 4 | Ownership participation agreement              
Public Utility Property Plant and Equipment              
Number of additional nuclear units | unit           2  
Ownership interest (as a percent)   30.00%       30.00%  
Project budget           $ 8,250.0  
Vogtle Units No. 3 & No. 4 | EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.              
Public Utility Property Plant and Equipment              
Number of nuclear units | unit             2
Generating capacity of each nuclear unit (in megawatts) | MW             1,100
Vogtle Units No. 3 & No. 4 | Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.              
Public Utility Property Plant and Equipment              
Written notice period for termination of agreement           30 days  
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet              
Public Utility Property Plant and Equipment              
Project budget $ 8,400.0            
Construction contingency estimate $ 800.0            
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Financial Exposure Term One              
Public Utility Property Plant and Equipment              
Proportionate share of construction costs, Co-Owner 55.70%            
Proportionate share of additional construction costs, Co-Owner $ 80.0            
Proportionate share of additional construction costs $ 44.0            
Proportionate share of construction costs, remaining co-owners 44.30%            
Proportionate share of construction costs 24.50%            
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Financial Exposure Term Two              
Public Utility Property Plant and Equipment              
Proportionate share of construction costs, Co-Owner 65.70%            
Proportionate share of additional construction costs, Co-Owner $ 100.0            
Proportionate share of additional construction costs $ 55.0            
Proportionate share of construction costs, remaining co-owners 34.30%            
Proportionate share of construction costs 19.00%            
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Financial Exposure Term Three              
Public Utility Property Plant and Equipment              
Additional construction costs that triggers option to tender ownership $ 2,100.0            
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Minimum              
Public Utility Property Plant and Equipment              
Percentage of ownership approval to change primary construction contractor   90.00%       90.00%  
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Minimum | Financial Exposure Term One              
Public Utility Property Plant and Equipment              
Construction contingency estimate 800.0            
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Minimum | Financial Exposure Term Two              
Public Utility Property Plant and Equipment              
Construction contingency estimate $ 1,600.0            
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Minimum | Financial Exposure Term Three              
Public Utility Property Plant and Equipment              
One time option to tender portion of ownership, exercise period 120 days            
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Maximum | Financial Exposure Term One              
Public Utility Property Plant and Equipment              
Construction contingency estimate $ 1,600.0            
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Maximum | Financial Exposure Term Two              
Public Utility Property Plant and Equipment              
Construction contingency estimate $ 2,100.0            
Vogtle Units No. 3 & No. 4 | Global Amendments To Term Sheet | Maximum | Financial Exposure Term Three              
Public Utility Property Plant and Equipment              
One time option to tender portion of ownership, exercise period 180 days            
Vogtle Unit Number 4              
Public Utility Property Plant and Equipment              
Monthly delay cost           $ 25.0