Vogtle Units No. 3 and No. 4 Construction Project (Tables)
9 Months Ended
Sep. 30, 2021
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our project budget and actual costs through September 30, 2021 for our 30% interest in the project.
(in millions)
Project BudgetActual Costs at September 30, 2021Remaining Project Budget
Construction Costs (1)
$6,140 $5,342 $798 
Financing Costs1,778 1,443 335 
   Total Costs$7,918 $6,785 $1,133 
Project-Level Contingency$90 $— $90 
Oglethorpe-Level Contingency242 — 242 
   Total Contingency$332 $— $332 
Totals$8,250 $6,785 $1,465 
(1) Construction costs are net of $1.1 billion received from Toshiba Corporation under a Guarantee Settlement Agreement.