Vogtle Units No. 3 and No. 4 Construction Project (Tables)
6 Months Ended
Jun. 30, 2021
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our project budget and actual costs through June 30, 2021 for our 30% interest in the project.
(in millions)
Project BudgetActual Costs at June 30, 2021Remaining Project Budget
Construction Costs (1)
$6,013 $5,145 $868 
Financing Costs1,735 1,385 350 
   Total Costs$7,748 $6,530 $1,218 
Project-Level Contingency$78 $— $78 
Oglethorpe-Level Contingency424 — 424 
   Total Contingency$502 $— $502 
Totals$8,250 $6,530 $1,720 
(1) Construction costs are net of $1.1 billion received from Toshiba Corporation under a Guarantee Settlement Agreement.
T