Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4 - USD ($)
$ in Millions
3 Months Ended
Mar. 31, 2021
Dec. 31, 2020
Project Budget    
Project-Level Contingency $ 32.0 $ 112.5
Remaining Project Budget    
Proceeds from guarantee agreement 1,100.0  
Jointly Owned Nuclear Power Plant    
Project Budget    
Construction Costs 5,614.0  
Financing Costs 1,592.0  
Total Costs 7,206.0  
Project-Level Contingency 90.0  
Oglethorpe-Level Contingency 204.0  
Total Contingency 294.0  
Total Contingency 7,500.0  
Actual Costs    
Construction Costs 4,947.0  
Financing Costs 1,328.0  
Total Costs 6,275.0  
Project-Level Contingency 0.0  
Oglethorpe-Level Contingency 0.0  
Total Contingency 0.0  
Totals 6,275.0  
Remaining Project Budget    
Construction Costs 667.0  
Financing Costs 264.0  
Total Costs 931.0  
Project-Level Contingency 90.0  
Oglethorpe-Level Contingency 204.0  
Total Contingency 294.0  
Totals $ 1,225.0