Vogtle Units No. 3 and No. 4 Construction Project (Tables)
3 Months Ended
Mar. 31, 2021
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our project budget and actual costs through March 31, 2021 for our 30% interest in the project.
(in millions)
Project BudgetActual Costs at March 31, 2021Remaining Project Budget
Construction Costs (1)
$5,614 $4,947 $667 
Financing Costs1,592 1,328 264 
   Total Costs$7,206 $6,275 $931 
Project-Level Contingency$90 $— $90 
Oglethorpe-Level Contingency204 — 204 
   Total Contingency$294 $— $294 
Totals$7,500 $6,275 $1,225 
(1) Construction costs are net of $1.1 billion received from Toshiba Corporation under a Guarantee Settlement Agreement.