Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4 - USD ($)
$ in Millions
6 Months Ended 9 Months Ended
Jun. 30, 2020
Sep. 30, 2020
Project Budget    
Project-Level Contingency $ 75  
Remaining Project Budget    
Proceeds from guarantee agreement   $ 1,100
Jointly Owned Nuclear Power Plant    
Project Budget    
Construction Costs   5,501
Financing Costs   1,557
Total Costs   7,058
Project-Level Contingency   72
Oglethorpe-Level Contingency   370
Total Contingency   442
Total Contingency   7,500
Actual Costs    
Construction Costs   4,536
Financing Costs   1,204
Total Costs   5,740
Project-Level Contingency   0
Oglethorpe-Level Contingency   0
Total Contingency   0
Totals   5,740
Remaining Project Budget    
Construction Costs   965
Financing Costs   353
Total Costs   1,318
Project-Level Contingency   72
Oglethorpe-Level Contingency   370
Total Contingency   442
Totals   $ 1,760