Vogtle Units No. 3 and No. 4 Construction Project (Tables)
9 Months Ended
Sep. 30, 2020
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our project budget and actual costs through September 30, 2020 for our 30% interest in the project.
(in millions)
Project Budget           Actual Costs at September 30, 2020Remaining Project Budget
Construction Costs (1)
$5,501 $4,536 $965 
Financing Costs1,557 1,204 353 
   Total Costs$7,058 $5,740 $1,318 
Project-Level Contingency$72 $— $72 
Oglethorpe-Level Contingency370 — 370 
   Total Contingency$442 $— $442 
Totals$7,500 $5,740 $1,760 
(1) Construction costs are net of $1.1 billion received from Toshiba Corporation under a Guarantee Settlement Agreement.