Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4
$ in Millions
6 Months Ended
Jun. 30, 2020
USD ($)
Project Budget  
Project-Level Contingency $ 75
Oglethorpe-Level Contingency 325
Remaining Project Budget  
Proceeds from guarantee agreement 1,100
Jointly Owned Nuclear Power Plant  
Project Budget  
Construction Costs 5,524
Financing Costs 1,576
Total Costs 7,100
Project-Level Contingency 75
Oglethorpe-Level Contingency 325
Total Contingency 400
Total Contingency 7,500
Actual Costs  
Construction Costs 4,303
Financing Costs 1,151
Total Costs 5,454
Project-Level Contingency 0
Oglethorpe-Level Contingency 0
Total Contingency 0
Totals 5,454
Remaining Project Budget  
Construction Costs 1,221
Financing Costs 425
Total Costs 1,646
Project-Level Contingency 75
Oglethorpe-Level Contingency 325
Total Contingency 400
Totals $ 2,046