Vogtle Units No. 3 and No. 4 Construction Project - Narrative (Details) - Vogtle Units No. 3 & No. 4
$ in Millions
1 Months Ended 6 Months Ended 12 Months Ended
Apr. 30, 2020
Aug. 31, 2018
USD ($)
Jun. 30, 2020
USD ($)
unit
Dec. 31, 2008
unit
MW
Public Utility Property Plant and Equipment        
Ownership interest (as a percent)     30.00%  
Total investment in additional Vogtle units     $ 5,500  
Construction contingency estimate   $ 800 800  
Estimated project-level construction contingency   $ 240    
Allocated project level contingency     425  
Allocated project level contingency from interest in project level budget     128  
Excess project contingency, total     75  
Ownership amount of excess project contingency     23  
Additional construction contingency, total     250  
Ownership amount of additional project level contingency     75  
Company level contingency     325  
Workforce reduction, percent 20.00%      
Minimum        
Public Utility Property Plant and Equipment        
COVID related costs     150  
Ownership amount of COVID related costs     45  
Maximum        
Public Utility Property Plant and Equipment        
COVID related costs     250  
Ownership amount of COVID related costs     $ 75  
Ownership participation agreement        
Public Utility Property Plant and Equipment        
Number of additional nuclear units | unit     2  
Ownership interest (as a percent)     30.00%  
Project budget     $ 7,500  
Project extension term     1 year  
EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.        
Public Utility Property Plant and Equipment        
Number of nuclear units | unit       2
Generating capacity of each nuclear unit | MW       1,100
Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.        
Public Utility Property Plant and Equipment        
Written notice period for termination of agreement     30 days  
Global Amendments To Term Sheet        
Public Utility Property Plant and Equipment        
Percentage of costs disallowed for recovery     6.00%  
Global Amendments To Term Sheet | Minimum        
Public Utility Property Plant and Equipment        
Percentage of ownership approval to change primary construction contractor     90.00%