Vogtle Units No. 3 and No. 4 Construction Project (Tables)
6 Months Ended
Jun. 30, 2020
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our project budget and actual costs through June 30, 2020 for our 30% interest in the project.
(in millions)
Project Budget           Actual Costs at June 30, 2020Remaining Project Budget
Construction Costs (1)
$5,524  $4,303  $1,221  
Financing Costs1,576  1,151  425  
   Total Costs$7,100  $5,454  $1,646  
Project-Level Contingency$75  $—  $75  
Oglethorpe-Level Contingency325  —  325  
   Total Contingency$400  $—  $400  
Totals$7,500  $5,454  $2,046  
(1) Construction costs are net of $1.1 billion received from Toshiba Corporation under a Guarantee Settlement Agreement.