Vogtle Units No. 3 and No. 4 Construction Project (Details) - Vogtle Units No. 3 & No. 4
$ in Thousands
3 Months Ended 12 Months Ended
Apr. 15, 2020
Mar. 31, 2020
USD ($)
unit
Dec. 31, 2008
unit
MW
Public Utility Property Plant and Equipment      
Ownership interest (as a percent)   30.00%  
Total investment in additional Vogtle units   $ 5,200,000  
Estimated project-level construction contingency   240,000  
Allocated project level contingency   451,000  
Allocated project level contingency from interest in project level budget   135,000  
Incremental Allocation   144,000  
Interest in project level budget, incremental allocation   43,000  
Expected restructuring cost   $ 13,000  
Subsequent Event      
Public Utility Property Plant and Equipment      
Workforce reduction, percent 20.00%    
Ownership participation agreement      
Public Utility Property Plant and Equipment      
Number of additional nuclear units | unit   2  
Ownership interest (as a percent)   30.00%  
Project budget   $ 7,500,000  
Project extension term   1 year  
EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.      
Public Utility Property Plant and Equipment      
Number of nuclear units | unit     2
Generating capacity of each nuclear unit | MW     1,100
Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.      
Public Utility Property Plant and Equipment      
Written notice period for termination of agreement   30 days  
Global Amendments To Term Sheet      
Public Utility Property Plant and Equipment      
Percentage of costs disallowed for recovery   6.00%  
Global Amendments To Term Sheet | Minimum      
Public Utility Property Plant and Equipment      
Construction contingency estimate   $ 800,000  
Percentage of ownership approval to change primary construction contractor   90.00%