Electric plant, construction and related agreements - Construction (Details)
12 Months Ended
Dec. 31, 2019
USD ($)
unit
petition
Dec. 31, 2008
unit
MW
Mar. 22, 2019
USD ($)
Feb. 20, 2014
USD ($)
Long-term debt        
Electric plant, construction and related agreements        
Ownership interests voting required to continue construction (as a percent) 90.00%      
Long-term debt | FFB        
Electric plant, construction and related agreements        
Maximum borrowing capacity $ 4,633,028,088   $ 1,619,679,706 $ 3,057,069,461
Aggregate Department of Energy-guaranteed borrowings $ 3,000,000,000.0      
Global Amendments to Term Sheet | Long-term debt        
Electric plant, construction and related agreements        
Term of credit facility (in years) 5 years      
Vogtle Units No. 3 & No. 4        
Electric plant, construction and related agreements        
Number of additional nuclear units | unit 2      
Ownership interest (as a percent) 30.00%      
Estimated construction project-level contingency $ 240,000,000      
Allocated project level contingency 307,000,000      
Allocated project level contingency from interest in project level budget $ 92,000,000      
Number of petitions filed by parties | petition 2      
Capital market debt issuances $ 1,900,000,000      
Vogtle Units No. 3 & No. 4 | Long-term debt | FFB        
Electric plant, construction and related agreements        
Term of credit facility (in years) 5 years      
Vogtle Units No. 3 & No. 4 | EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.        
Electric plant, construction and related agreements        
Number of nuclear units | unit   2    
Generating capacity of each nuclear unit (in megawatts) | MW   1,100    
Vogtle Units No. 3 & No. 4 | Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.        
Electric plant, construction and related agreements        
Written notice period for termination of agreement 30 days      
Vogtle Units No. 3 & No. 4 | Ownership participation agreement        
Electric plant, construction and related agreements        
Project budget $ 7,500,000,000      
Total investment in additional Vogtle units $ 4,900,000,000      
Vogtle Units No. 3 & No. 4 | Ownership participation agreement | Occurrence of certain adverse events        
Electric plant, construction and related agreements        
Project extension term 1 year      
Vogtle Units No. 3 & No. 4 | Ownership participation agreement | Minimum | Occurrence of certain adverse events        
Electric plant, construction and related agreements        
Ownership interests voting required to continue construction (as a percent) 90.00%      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet        
Electric plant, construction and related agreements        
Project budget $ 8,400,000,000      
Additional construction costs $ 800,000,000      
Percentage of number of Co-owners 67.00%      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Occurrence of certain adverse events        
Electric plant, construction and related agreements        
Percentage of costs disallowed for recovery 6.00%      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | EAC exceeds by $800 million to $1.6 billion        
Electric plant, construction and related agreements        
Percentage of construction costs to be responsible by each Co-owner 24.50%      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | EAC exceeds by $1.6 billion to $2.1 billion        
Electric plant, construction and related agreements        
Percentage of construction costs to be responsible by each Co-owner 19.00%      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | Occurrence of certain adverse events        
Electric plant, construction and related agreements        
Ownership interests voting required to continue construction (as a percent) 90.00%      
Ownership approval required for material amendments (as a percent) 67.00%      
Ownership approval to change primary construction contractor (as a percent) 90.00%      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | EAC exceeds by $800 million to $1.6 billion        
Electric plant, construction and related agreements        
Additional construction costs exceeds EAC $ 800,000,000      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | EAC exceeds by $1.6 billion to $2.1 billion        
Electric plant, construction and related agreements        
Additional construction costs exceeds EAC 1,600,000,000      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | EAC exceeds more than $2.1 billion        
Electric plant, construction and related agreements        
Additional construction costs exceeds EAC 2,100,000,000      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | EAC exceeds by $800 million to $1.6 billion        
Electric plant, construction and related agreements        
Additional construction costs exceeds EAC 1,600,000,000      
Construction costs savings 44,000,000      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | EAC exceeds by $1.6 billion to $2.1 billion        
Electric plant, construction and related agreements        
Additional construction costs exceeds EAC 2,100,000,000      
Construction costs savings 55,000,000      
Co-owners | Vogtle Units No. 3 & No. 4        
Electric plant, construction and related agreements        
Estimated construction project-level contingency $ 800,000,000      
Georgia Power | Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | EAC exceeds by $800 million to $1.6 billion        
Electric plant, construction and related agreements        
Percentage of construction costs to be responsible by each Co-owner 55.70%      
Georgia Power | Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | EAC exceeds by $1.6 billion to $2.1 billion        
Electric plant, construction and related agreements        
Percentage of construction costs to be responsible by each Co-owner 65.70%      
Georgia Power | Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | EAC exceeds more than $2.1 billion        
Electric plant, construction and related agreements        
Percentage of construction costs to be responsible by each Co-owner 100.00%      
Georgia Power | Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Actual cost at completion less than EAC        
Electric plant, construction and related agreements        
Percentage of cost savings entitled 60.70%      
Georgia Power | Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | EAC exceeds by $800 million to $1.6 billion        
Electric plant, construction and related agreements        
Potential additional costs $ 80,000,000      
Georgia Power | Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | EAC exceeds by $1.6 billion to $2.1 billion        
Electric plant, construction and related agreements        
Potential additional costs $ 100,000,000      
Co-owners excluding Georgia Power | Global Amendments to Term Sheet | Actual cost at completion less than EAC        
Electric plant, construction and related agreements        
Percentage of cost savings entitled 39.30%      
Co-owners excluding Georgia Power | Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | EAC exceeds by $800 million to $1.6 billion        
Electric plant, construction and related agreements        
Percentage of construction costs to be responsible by each Co-owner 44.30%      
Co-owners excluding Georgia Power | Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | EAC exceeds by $1.6 billion to $2.1 billion        
Electric plant, construction and related agreements        
Percentage of construction costs to be responsible by each Co-owner 34.30%