XML 32 R18.htm IDEA: XBRL DOCUMENT v3.19.1
Vogtle Units No. 3 and No. 4 Construction Project
3 Months Ended
Mar. 31, 2019
Vogtle Units No. 3 and No. 4 Construction Project  
Vogtle Units No. 3 and No. 4 Construction Project

(M)    Vogtle Units No. 3 and No. 4 Construction Project.  We, Georgia Power, the Municipal Electric Authority of Georgia, and the City of Dalton, Georgia, acting by and through its Board of Water, Light and Sinking Fund Commissioners, doing business as Dalton Utilities (collectively, the Co-owners) are parties to an Ownership Participation Agreement that, along with other agreements, governs our participation in two additional nuclear units under construction at Plant Vogtle, Units No. 3 and No. 4. The Co-owners appointed Georgia Power to act as agent under this agreement. Our ownership interest and proportionate share of the cost to construct these units is 30%. Pursuant to this agreement, Georgia Power has designated Southern Nuclear Operating Company, Inc. as its agent for licensing, engineering, procurement, contract management, construction and pre-operation services. As of March 31, 2019, our total investment in the additional Vogtle units was approximately $4,113,511,000.

In 2008, Georgia Power, acting for itself and as agent for the Co-owners, entered into an Engineering, Procurement and Construction Agreement (the EPC Agreement) with Westinghouse Electric Company LLC and Stone & Webster, Inc., which was subsequently acquired by Westinghouse and changed its name to WECTEC Global Project Services Inc. (collectively, Westinghouse). Pursuant to the EPC Agreement, Westinghouse agreed to design, engineer, procure, construct and test two 1,100 megawatt nuclear units using the Westinghouse AP1000 technology and related facilities at Plant Vogtle

Until March 2017, construction on Units No. 3 and No. 4 continued under the substantially fixed price EPC Agreement. In March 2017, Westinghouse filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. Effective in July 2017, Georgia Power, acting for itself and as agent for the other Co-owners, and Westinghouse entered into a services agreement (the Services Agreement), pursuant to which Westinghouse is providing facility design and engineering services, procurement and technical support and staff augmentation on a time and materials cost basis. The Services Agreement provides that it will continue until the start-up and testing of Vogtle Units No. 3 and No. 4 is complete and electricity is generated and sold from both units. The Services Agreement is terminable by the Co-owners upon 30 days’ written notice.

In October 2017, Georgia Power, acting for itself and as agent for the other Co-owners, entered into a construction completion agreement with Bechtel Power Corporation, pursuant to which Bechtel serves as the primary contractor for the remaining construction activities for Vogtle Units No. 3 and No. 4 (the Bechtel Agreement). The Bechtel Agreement is a cost reimbursable plus fee arrangement, whereby Bechtel is reimbursed for actual costs plus a base fee and an at-risk fee, which is subject to adjustment based on Bechtel’s performance against cost and schedule targets. Each Co-owner is severally, and not jointly, liable for its proportionate share, based on its ownership interest, of all amounts owed to Bechtel under the Bechtel Agreement. The Co-owners may terminate the Bechtel Agreement at any time for their convenience, provided that the Co-owners will be required to pay amounts related to work performed prior to the termination (including the applicable portion of the base fee), certain termination-related costs and, at certain stages of the work, the applicable portion of the at-risk fee. Bechtel may terminate the Bechtel Agreement under certain circumstances, including certain Co-owner suspensions of work, certain breaches of the Bechtel Agreement by the Co-owners, Co-owner insolvency and certain other events.

In April 2019, Georgia Power and Southern Nuclear completed a cost and schedule validation process to verify and update quantities of commodities remaining to install, labor hours to install remaining quantities and related productivity, testing and system turnover requirements, and forecasted staffing needs and related costs. This process confirmed the total estimated project capital cost forecast for Vogtle Units No. 3 and No. 4. Accordingly, we did not change our $7.5 billion project budget, which includes capital costs, allowance for funds used during construction, our allocation of the project-level contingency and a separate Oglethorpe-level contingency. There was also no change to the in-service dates of November 2021 for Unit No. 3 and November 2022 for Unit No. 4 previously approved by the Georgia Public Service Commission following the validation process. The schedule being utilized to manage construction at the Vogtle site was adjusted following the validation process and will continue to target in-service dates in advance of November 2021 and November 2022 in order to maintain margin to the approved in-service dates.

As construction continues, risks remain that construction-related challenges, including management of contractors, subcontractors and vendors; supervision of craft labor and related craft labor productivity, ability to attract and retain craft labor and/or related cost escalation; procurement, fabrication, delivery, assembly and/or installation and the initial testing and start-up, including any required engineering changes, of plant systems, structures or components, any of which may require additional labor and/or materials; or other issues could arise and further impact the projected schedule and estimated cost. Monthly construction production targets established as part of a strategy to maintain margin to the approved in-service dates will continue to increase significantly throughout 2019. To meet these increasing monthly targets, existing craft construction productivity must improve and additional craft laborers must be retained and deployed.

The Co-owners’ joint ownership agreements, as amended, provide that the holders of at least 90% of the ownership interests in Vogtle Units No. 3 and No. 4 must vote to continue construction, or can vote to suspend construction, if certain adverse events occur, including: (i) the bankruptcy of Toshiba Corporation; (ii) termination or rejection in bankruptcy of certain agreements, including the Services Agreement, the Bechtel Agreement or the agency agreement with Southern Nuclear; (iii) Georgia Power publicly announces its intention not to submit for rate recovery any portion of its investment in Vogtle Units No. 3 and No. 4 (or associated financing costs) or the Georgia Public Service Commission determines that any of Georgia Power's costs relating to the construction of Vogtle Units No. 3 and No. 4 will not be recovered in retail rates, excluding any additional amounts paid by Georgia Power on behalf of the other Co-owners pursuant to the Joint Ownership Agreement provisions described above and the first 6% of costs during any six-month VCM reporting period that are disallowed by the Public Service Commission for recovery, or for which Georgia Power elects not to seek cost recovery, through retail rates or (iv) an incremental extension of one year or more over the most recently approved schedule (each, a Project Adverse Event).

The ultimate outcome of these matters cannot be determined at this time. See Note 8 in Item 8 Notes to Audited Consolidated Financial Statements in our 2018 Form 10-K for additional information about Vogtle Units No. 3 and No. 4.