Vogtle Units No. 3 and No. 4 Construction Project (Details)
1 Months Ended 9 Months Ended 12 Months Ended
Sep. 30, 2018
USD ($)
Nov. 30, 2017
Sep. 30, 2018
USD ($)
item
Dec. 31, 2008
item
MW
Sep. 28, 2017
USD ($)
Loan Guarantee Agreement          
Electric plant, construction and related agreements          
Aggregate Department of Energy-guaranteed borrowings $ 1,779,626,000   $ 1,779,626,000    
Term of credit facility (in years)     5 years    
Loan Guarantee Agreement | Maximum          
Electric plant, construction and related agreements          
Aggregate borrowings 3,057,069,461   $ 3,057,069,461    
Conditional commitment issued by guarantor under the Loan Guarantee Agreement         $ 1,619,679,706
Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.          
Electric plant, construction and related agreements          
Written notice period for termination of agreement     30 days    
Vogtle Units Number 3 And Number 4          
Electric plant, construction and related agreements          
Number of petitions filed by parties | item     2    
Estimated additional costs of completion     $ 450,000,000    
Estimated construction project-level contingency     800    
Estimated increase in construction contingency     240,000,000    
Project budget 7,500,000   7,500,000    
Estimated construction contingency 500,000,000        
Total investment in additional Vogtle units 3,621,928,000   3,621,928,000    
Capital market debt issuances $ 1,887,000,000   $ 1,887,000,000    
Vogtle Units Number 3 And Number 4 | Minimum          
Electric plant, construction and related agreements          
Construction percentage of completion 55.00%   55.00%    
Total project percentage of completion 70.00%   70.00%    
Vogtle Units Number 3 And Number 4 | Ownership participation agreement          
Electric plant, construction and related agreements          
Number of additional nuclear units | item     2    
Ownership interest (as a percent) 30.00%   30.00%    
Vogtle Units Number 3 And Number 4 | Ownership participation agreement | Occurrence of certain adverse events          
Electric plant, construction and related agreements          
Percentage of costs disallowed for recovery   6.00%      
Project extension term   1 year      
Vogtle Units Number 3 And Number 4 | Ownership participation agreement | Minimum | Occurrence of certain adverse events          
Electric plant, construction and related agreements          
Ownership interests voting required to continue construction (as a percent)   90.00%      
Ownership approval to change primary construction contractor (as a percent)   90.00%      
Ownership approval required for material amendments (as a percent)   67.00%      
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc.          
Electric plant, construction and related agreements          
Number of nuclear units | item       2  
Generating capacity of each nuclear unit | MW       1,100  
Vogtle Units Number 3 And Number 4 | The Term Sheet          
Electric plant, construction and related agreements          
Project budget $ 8,400,000,000   $ 8,400,000,000    
Additional construction costs     $ 800,000,000    
Percentage of number of Co-owners     67.00%    
Vogtle Units Number 3 And Number 4 | The Term Sheet | EAC exceeds by $800 million to $1.6 billion          
Electric plant, construction and related agreements          
Percentage of construction costs to be responsible by each Co-owner     24.50%    
Vogtle Units Number 3 And Number 4 | The Term Sheet | EAC exceeds by $1.6 billion to $2.1 billion          
Electric plant, construction and related agreements          
Percentage of construction costs to be responsible by each Co-owner     19.00%    
Vogtle Units Number 3 And Number 4 | The Term Sheet | Minimum | EAC exceeds by $800 million to $1.6 billion          
Electric plant, construction and related agreements          
Additional construction costs exceeds EAC     $ 800,000,000    
Vogtle Units Number 3 And Number 4 | The Term Sheet | Minimum | EAC exceeds by $1.6 billion to $2.1 billion          
Electric plant, construction and related agreements          
Additional construction costs exceeds EAC     1,600,000,000    
Vogtle Units Number 3 And Number 4 | The Term Sheet | Minimum | EAC exceeds more than $2.1 billion          
Electric plant, construction and related agreements          
Additional construction costs exceeds EAC     2,100,000,000    
Vogtle Units Number 3 And Number 4 | The Term Sheet | Maximum | EAC exceeds by $800 million to $1.6 billion          
Electric plant, construction and related agreements          
Additional construction costs exceeds EAC     1,600,000,000    
Construction costs savings     44,000,000    
Vogtle Units Number 3 And Number 4 | The Term Sheet | Maximum | EAC exceeds by $1.6 billion to $2.1 billion          
Electric plant, construction and related agreements          
Additional construction costs exceeds EAC     2,100,000,000    
Construction costs savings     55,000,000    
Co-owners | Vogtle Units Number 3 And Number 4          
Electric plant, construction and related agreements          
Estimated additional costs of completion     $ 1,500,000,000    
Georgia Power | Vogtle Units Number 3 And Number 4 | The Term Sheet | EAC exceeds by $800 million to $1.6 billion          
Electric plant, construction and related agreements          
Percentage of construction costs to be responsible by each Co-owner     55.70%    
Georgia Power | Vogtle Units Number 3 And Number 4 | The Term Sheet | EAC exceeds by $1.6 billion to $2.1 billion          
Electric plant, construction and related agreements          
Percentage of construction costs to be responsible by each Co-owner     65.70%    
Georgia Power | Vogtle Units Number 3 And Number 4 | The Term Sheet | EAC exceeds more than $2.1 billion          
Electric plant, construction and related agreements          
Percentage of construction costs to be responsible by each Co-owner     100.00%    
Georgia Power | Vogtle Units Number 3 And Number 4 | The Term Sheet | Actual cost at completion less than EAC          
Electric plant, construction and related agreements          
Percentage of cost savings entitled     60.70%    
Georgia Power | Vogtle Units Number 3 And Number 4 | The Term Sheet | Maximum | EAC exceeds by $800 million to $1.6 billion          
Electric plant, construction and related agreements          
Potential Additional Costs     $ 80,000,000    
Georgia Power | Vogtle Units Number 3 And Number 4 | The Term Sheet | Maximum | EAC exceeds by $1.6 billion to $2.1 billion          
Electric plant, construction and related agreements          
Potential Additional Costs     $ 100,000,000    
Co-owners excluding Georgia Power | Vogtle Units Number 3 And Number 4 | The Term Sheet | EAC exceeds by $800 million to $1.6 billion          
Electric plant, construction and related agreements          
Percentage of construction costs to be responsible by each Co-owner     44.30%    
Co-owners excluding Georgia Power | Vogtle Units Number 3 And Number 4 | The Term Sheet | EAC exceeds by $1.6 billion to $2.1 billion          
Electric plant, construction and related agreements          
Percentage of construction costs to be responsible by each Co-owner     34.30%    
Co-owners excluding Georgia Power | Vogtle Units Number 3 And Number 4 | The Term Sheet | Actual cost at completion less than EAC          
Electric plant, construction and related agreements          
Percentage of cost savings entitled     39.30%