Electric plant, construction and related agreements: Construction information (Details) - Vogtle Units Number 3 And Number 4
12 Months Ended
Jan. 01, 2016
USD ($)
Dec. 31, 2015
USD ($)
Dec. 30, 2015
USD ($)
Dec. 31, 2008
USD ($)
item
MW
Jan. 13, 2016
USD ($)
Jun. 30, 2015
USD ($)
Construction            
Number of Westinghouse AP1000 nuclear generating units | item       2    
Nominally rated generating capacity for each unit | MW       1,100    
Ownership interest of nuclear units (as a percent)       30.00%    
Amount to be paid to the Contractor and capitalized to the project, contingent upon acquisition   $ 230,000,000        
Payments for Legal Settlements $ 80,000,000   $ 80,000,000      
Project budget including capital costs, allowance for funds used during construction and contingency amount   5,000,000,000        
Total investment in additional vogtle units   $ 2,888,000,000        
Aggregate Damages Under Initial Complaint And Amended Counterclaim            
Construction            
Maximum additional capital cost under the provision           $ 470,000,000
Amended counterclaim associated with design changes, delays in Project Schedule and issuance of permits and operating licenses            
Construction            
Maximum additional capital cost under the provision       $ 75,000,000    
Toshiba Corporation | Letter of credit            
Construction            
Letters of credit         $ 900,000,000