Electric plant, construction and related agreements: (Details 2) (USD $)
12 Months Ended
Dec. 31, 2012
Dec. 31, 2011
Dec. 31, 2012
Vogtle Units No.3 and No.4
item
MW
Construction      
Number of Westinghouse AP1000 nuclear generating units     2
Nominally rated generating capacity for each unit     1,100
Ownership interest (as a percent)     30.00%
Revised Estimated proportionate share of construction cost     $ 4,500,000,000
Estimated proportionate share of construction cost     4,200,000,000
Total construction work in progress $ 2,240,920,000 $ 1,784,264,000 $ 1,689,000,000