XML 41 R28.htm IDEA: XBRL DOCUMENT v3.4.0.3
Balance Sheet Components Electric Utility Plant, Net (Details) - USD ($)
$ in Millions
3 Months Ended
Mar. 31, 2016
Dec. 31, 2015
Property, Plant and Equipment [Line Items]    
Derivative Liability, Fair Value of Collateral $ 15  
Capital Leases, Future Minimum Payments, Present Value of Net Minimum Payments 2  
Capital Leases, Future Minimum Payments, Interest Included in Payments 3  
Capital Leased Assets, Gross 54  
Electric utility plant 8,663 $ 8,560
Construction work-in-progress 647 545
Total cost 9,310 9,105
Less: accumulated depreciation and amortization (3,150) (3,093)
Electric utility plant, net 6,160 $ 6,012
Capital Leases, Lessee Balance Sheet, Assets by Major Class, Accumulated Depreciation 1  
Capital Lease Obligations, Current 2  
Capital Lease Obligations, Noncurrent 51  
Amortization of Leased Asset 1  
Capital Leases, Income Statement, Interest Expense $ 2