Commitments and Contingencies
12 Months Ended
Dec. 31, 2024
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES COMMITMENTS AND CONTINGENCIES
We and our subsidiaries have significant commitments and contingencies arising from our operations, including those related to unconditional purchase obligations, environmental matters, and enforcement and litigation matters.

Unconditional Purchase Obligations

Our electric utilities have obligations to distribute and sell electricity to their customers, and our natural gas utilities have obligations to distribute and sell natural gas to their customers. The utilities expect to recover costs related to these obligations in future customer rates. In order to meet these obligations, we routinely enter into long-term purchase and sale commitments for various quantities and lengths of time.

The renewable generation facilities that are part of our non-utility energy infrastructure segment have obligations to distribute and sell electricity through long-term offtake agreements with their customers for all of the energy produced. In order to support these sales obligations, these companies enter into easements and other service agreements associated with the generating facilities.

The following table shows our minimum future commitments related to these purchase obligations as of December 31, 2024, including those of our subsidiaries:
Payments Due By Period
(in millions)Date Contracts Extend ThroughTotal Amounts Committed20252026202720282029Later Years
Electric utility:
Nuclear2033$5,680.3 $634.5 $681.6 $730.4 $782.6 $838.5 $2,012.7 
Coal supply and transportation2029343.4 303.0 33.5 3.3 1.7 1.9 — 
Purchased power2063394.3 59.7 61.4 56.1 52.2 25.5 139.4 
Other204380.2 10.0 10.1 8.7 7.1 6.3 38.0 
Natural gas utility:
Supply and transportation20482,448.0 388.5 357.9 345.2 302.6 217.5 836.3 
Non-utility energy infrastructure:
Purchased power2051623.0 38.2 38.6 39.3 40.6 39.4 426.9 
Natural gas storage and transportation20484.8 4.0 — 0.1 — 0.1 0.6 
Total$9,574.0 $1,437.9 $1,183.1 $1,183.1 $1,186.8 $1,129.2 $3,453.9 

Environmental Matters

Consistent with other companies in the energy industry, we face significant ongoing environmental compliance and remediation obligations related to current and past operations. Specific environmental issues affecting us include, but are not limited to, current and future regulation of air emissions such as SO2, NOx, fine particulates, ozone, mercury, and GHGs; water intake and discharges; management of coal combustion products such as fly ash; and remediation of impacted properties, including former manufactured gas plant sites.

We have continued to pursue a proactive strategy to manage our environmental compliance obligations, including:

the development of additional sources of renewable electric energy supply, battery storage, and natural gas and LNG storage facilities;
the addition of improvements for water quality matters such as treatment technologies to meet regulatory discharge limits and improvements to our cooling water intake systems;
the addition of emission control equipment to existing facilities to comply with ambient air quality standards and federal clean air rules;
the protection of wetlands and waterways, biodiversity including threatened and endangered species, and cultural resources associated with construction projects;
the retirement of older coal-fired power plants and conversion to modern, efficient, natural gas generation, super-critical pulverized coal generation, and/or replacement with renewable generation;
the beneficial use of ash and other products from coal-fired and biomass generating units;
the remediation of former manufactured gas plant sites;
the reduction of methane emissions across our natural gas distribution system by upgrading infrastructure; and
the tracking and reporting of GHG emissions to comply with federal clean air rules.

Air Quality

Cross State Air Pollution Rule – Good Neighbor Rule

In March 2023, the EPA issued its final Good Neighbor Rule, which became effective in August 2023 and requires significant reductions in ozone-forming emissions of NOx from power plants and industrial facilities. After review of the final rule, we believe we are well positioned to meet the requirements.

Our RICE units in the Upper Peninsula of Michigan and Wisconsin are not currently subject to the final rule as each unit is less than 25 MWs. To the extent we use RICE engines for natural gas distribution operations, those engines not part of an LDC are subject to the emission limits and operational requirements of the rule beginning in 2026. The EPA has exempted LDCs from the final rule.

In February 2024, the Supreme Court heard oral arguments regarding stay applications related to the EPA's Good Neighbor Rule. In June 2024, the Supreme Court granted a stay of the Good Neighbor Rule pending disposition of the applicants' petitions for review at the D.C. Circuit Court of Appeals. The D.C. Circuit Court of Appeals litigation has been held in abeyance since September 2024, when the court granted the EPA's motion for partial voluntary remand so that it could address issues of severability raised in the Supreme Court's June 2024 opinion granting the petitions for stay of the rule. Pursuant to an order of the D.C. Circuit Court of Appeals, the parties filed motions to govern future proceedings in December 2024. In January 2025, the D.C. Circuit Court of Appeals issued an order returning the consolidated cases to the court's active docket and establishing a schedule for supplemental briefing on the issue of severability that extends through early March 2025. We will continue to monitor this case as arguments at the D.C. Circuit Court of Appeals move forward.

In November 2024, the EPA issued a Good Neighbor Interim Final Rule that administratively stayed the effectiveness of the Good Neighbor Rule in all states to which it originally applies and ensured implementation of good neighbor obligations previously established to address the 2008 ozone NAAQS while the process works through the courts. We are well positioned to comply with the rule's requirements.

Mercury and Air Toxics Standards

In 2012, the EPA issued the MATS to limit emissions of mercury, acid gases, and other hazardous air pollutants. In April 2023, the EPA issued the pre-publication version of a proposed rule to strengthen and update MATS to reflect recent developments in control technologies and performance of coal and oil-fired units. In May 2024, the EPA published a final rule in the Federal Register lowering the PM limit from 0.03 lb/MMBtu to 0.01 lb/MMBtu. We are well positioned to comply with the rule's requirements.

National Ambient Air Quality Standards

Ozone

After completing its review of the 2008 ozone standard, the EPA released a final rule in October 2015, creating a more stringent standard than the 2008 NAAQS. The 2015 ozone standard lowered the 8-hour limit for ground-level ozone. In November 2022, the EPA's 2022 CASAC Ozone Review Panel issued a draft report supporting reconsideration of the 2015 standard. The EPA staff initially issued a draft Policy Assessment in March 2023 that also supported the reconsideration; however, in August 2023, the EPA announced that it was instead restarting its ozone standard evaluation. The EPA released the first two volumes of its Integrated Review Plan in December 2024. This new review is anticipated to take 3 to 5 years to complete.

In February 2022, revisions to the Wisconsin Administrative Code to adopt the 2015 standard were finalized. The amended regulations incorporated by reference the federal air pollution monitoring requirements related to the standard. The WDNR submitted the rule updates as a SIP revision to the EPA, which the EPA approved in February 2023.

The EPA's initial nonattainment area designation was effective August 2018, and the attainment status is evaluated every 3 years thereafter until attainment is achieved. The Milwaukee, Sheboygan, and Chicago, IL-IN-WI nonattainment areas did not meet the marginal attainment deadline of August 2021, so in April 2022 the EPA proposed "moderate" nonattainment status based on the
2015 standard. In October 2022, the EPA published its final reclassifications from "marginal" to "moderate" for these areas, effective November 7, 2022.

The most recent attainment evaluation date was in August 2024. The moderate attainment deadline was not met, so in December 2024 the EPA published a final determination reclassifying the nonattainment areas in Wisconsin to a "serious" classification effective January 16, 2025. This nonattainment status could have a material adverse effect on future permitting activities for our facilities in applicable locations, including additional costs associated with more strenuous emission control requirements or the need to purchase additional emission reduction credits.

Particulate Matter

All counties within our service territories are in attainment with current 2012 standards for fine PM2.5. Under the Biden Administration's policy review, the EPA concluded that the scientific evidence and information from a December 2020 review of the 2012 standards supported revising the level of the annual standard for the PM2.5 NAAQS to below the current level of 12 µg/m3, while retaining the 24-hour standard of 35 µg/m3. In February 2024, the EPA finalized a rule which lowered the primary (health-based) annual PM2.5 NAAQS to 9 µg/m3. The secondary (welfare-based) PM2.5 standard and 24-hour standards (both primary and secondary) remain unchanged. The EPA has until February 2026 to designate areas as attainment and nonattainment with the new standard. The WDNR will need to draft and submit a SIP for the EPA's approval. A designation of nonattainment status could impact future permitting activities for facilities in applicable locations, including the potential need for improved or new air pollution control equipment. With our planned transition from coal-fired plants to natural gas-fired plants and renewable generating facilities, we do not expect this new standard to have a material impact on our units.

Climate Change

In May 2023, the EPA proposed GHG performance standards for fossil-fired steam generating and natural gas combustion units and also proposed to repeal the Affordable Clean Energy rule, which had replaced the Clean Power Plan. The final rule, known as the Greenhouse Gas Power Plant Rule, was published in May 2024. Pursuant to the final rule, there are no applicable standards for coal plants until the end of 2031 and after 2031, the applicable standard is dependent upon the unit's retirement date. Coal-fired units that are planned to refuel to natural gas-fired units must convert to natural gas and no longer retain the capability to burn coal by the end of 2029. For new combined cycle natural gas plants above a 40% capacity factor, the rule is dependent upon the implementation of carbon capture by the end of 2031. For new simple cycle natural gas-fired combustion turbines, there are no applicable limits as long as the capacity factor is less than 20%. Our RICE units in Michigan and the new Weston RICE units are not affected under the rule because the rule excludes RICE units that are less than 25 MWs. Numerous parties have challenged the Greenhouse Gas Power Plant Rule through litigation pending in the D.C. Circuit Court of Appeals.

In March 2024, the EPA announced it had removed regulations on existing natural gas combustion turbines from the rule. At that time, the EPA indicated it would work on new rulemaking phases, focusing on CO2 emissions, as well as NOx and hazardous air pollutants (formaldehyde) emissions. In November 2024, the EPA released the first proposed rule of the three rule "packages" to address NOx emissions from existing combustion turbines. The proposed rule for turbines that operate at a greater than 20% capacity factor, will require more stringent NOx limits and control requirements for new, modified, or reconstructed turbines. For turbines that operate at a capacity of 20% or lower, less restrictive standards and the use of combustion controls would apply. Our combined cycle facilities and the new Oak Creek combustion turbines are well positioned to comply with the proposed rule. As the EPA will not finalize this proposal until late 2025, it could be revised or repealed under the new presidential administration.

In April 2024, the EPA issued its final Mandatory Greenhouse Gas Reporting Rule, 40 CFR Part 98, which includes updates to the global warming potentials to determine CO2 equivalency for threshold reporting and the addition of a new section regarding energy consumption. The revisions will impact the reporting required for our electric generation facilities, LDCs, and underground natural gas storage facilities. In May 2024, the EPA also issued its final rule to amend reporting requirements for petroleum and natural gas systems. Under the final rule, new leak emission factors and reporting requirements for large release events will impact the reporting required for our LDCs and underground natural gas storage facilities.

Our capital plan includes the retirement of older, fossil-fueled generation, to be replaced with zero-carbon-emitting renewables and reliable, efficient natural gas-fueled generation. We have already retired nearly 2,500 MWs of fossil-fueled generation since the beginning of 2018, which includes the retirement of OCPP Units 5 and 6 in May 2024, the 2019 retirement of PIPP, and the 2018 retirements of the Pleasant Prairie power plant, the Pulliam power plant, and the jointly-owned Edgewater Unit 4 generating unit. We expect to retire approximately 1,200 MWs of additional coal-fired generation by the end of 2031, which includes the planned retirements of OCPP Units 7 and 8, the jointly-owned Columbia Units 1 and 2 while investigating conversion of at least one unit to
natural gas, and Weston Unit 3. See Note 7, Property, Plant, and Equipment, for more information related to planned power plant retirements. In May 2021, we announced goals to achieve reductions in carbon emissions from our electric generation fleet by 60% by the end of 2025 and by 80% by the end of 2030, both from a 2005 baseline. We expect to achieve these goals by continuing to make operating refinements, retiring less efficient generating units, and executing our capital plan. Over the longer term, the target for our generation fleet is to be net carbon neutral by 2050. We also believe we will be in a position to eliminate coal as an energy source by the end of 2032.

We will also continue to focus on methane emissions reductions by improving our natural gas distribution systems, and have set a target across our natural gas distribution operations to achieve net-zero methane emissions by the end of 2030. We plan to achieve our net-zero goal through an effort that includes continuous operational improvements and equipment upgrades, as well as the use of RNG throughout our natural gas utility distribution systems. In addition, subject to regulatory approval and market conditions, we expect to procure RTCs.

Water Quality

Clean Water Act Cooling Water Intake Structure Rule

Section 316(b) of the CWA became effective in October 2014 and requires the location, design, construction, and capacity of cooling water intake structures at existing power plants reflect the BTA for minimizing adverse environmental impacts. The rule applies to all of our existing generating facilities with cooling water intake structures, except for the ERGS units, which were permitted and received a final BTA determination under the rules governing new facilities.

Effective in June 2020, the requirements of federal Section 316(b) of the CWA were incorporated into the Wisconsin Administrative Code. The WDNR applies this rule when establishing BTA requirements for cooling water intake structures at existing facilities. These BTA requirements are incorporated into WPDES permits for WE and WPS facilities.

We have received final or interim BTA determinations for all generation facilities where Section 316(b) is applicable. The most recent BTA determination was for Weston Units 3 and 4. In accordance with the requirements in the CWA, the WDNR reissued the Weston WPDES permit in June 2024 (effective July 1, 2024) that includes a determination that existing technology (wet cooling towers) installed at the units represents BTA for minimizing adverse environmental impacts. With respect to OCPP Units 7 and 8, we believe the WDNR will reach the same BTA determination decision when the WPDES permit for those units is reissued, which is expected in 2025.

Steam Electric Effluent Limitation Guidelines

The EPA's 2015 final ELG rule, which took effect in January 2016 (2015 ELG rule), was modified in 2020 (2020 ELG rule), and again in 2024 with the May 2024 publication of the Supplemental ELG Rule. These rules establish federal technology-based requirements for several types of power plant wastewaters. The three requirements that affect WE and WPS facilities relate to discharge limits for BATW, FGD wastewater, and CRL (landfill leachate). Although our coal-fueled facilities were constructed with advanced wastewater treatment technologies that meet many of the discharge limits established by the 2015 rule, facility modifications were still necessary at OCPP, ERGS, and Weston to meet all of the 2015 ELG requirements and the additional ones established by the 2020 ELG rule. Through 2023, compliance costs associated with the 2015 and 2020 ELG rules required $105 million in capital investment.

The 2024 Supplemental ELG rule established zero discharge requirements for BATW, FGD, and CRL wastewaters at coal-fueled units with no planned retirement date. The Supplemental ELG Rule also kept one existing and created one new “permanent cessation of coal” subcategory. Those electing to cease coal combustion by either retiring or repowering a unit by December 31, 2028 or December 31, 2034 can limit ELG-related capital investments to what was required by either the 2015 or the 2020 ELG Rule, respectively. For units where cessation of coal is planned to occur no later than December 31, 2034, facility owners must complete all 2020 ELG rule required capital investments by December 31, 2025. All WE and WPS coal-fueled units fully meet the 2020 ELG rule requirements. Based on current electrical generation resource planning, we plan to file a Notice of Planned Participation by December 31, 2025 to opt into the "cessation of coal by December 31, 2034" subcategory for both the ERGS and Weston coal-fired facilities. A Notice of Privacy Practice also may be filed for the OCPP, PWGS, and VAPP facilities because this ELG rule option will allow the company to qualify for more reasonable requirements to address the CRL provisions at our landfills that served these former coal-fired facilities.
The final Supplemental ELG Rule allows owners of coal-fired units who opted into a cessation of coal subcategory to operate beyond the end of 2028 or 2034, required by either the 2015 or the 2020 ELG Rule, respectively, if needed for reliability concerns (i.e., energy emergencies, reliability must run agreements, etc.) as determined by the DOE, a public utility commission, or independent system operator.

We are still evaluating the Supplemental ELG Rule CRL provisions to determine the applicability and potential compliance costs for inactive/closed landfills. Numerous parties have challenged the rule through litigation pending in the U.S. Court of Appeals for the 8th Circuit. This rule remains in effect during the pendency of the legal challenge.

Land Quality

Manufactured Gas Plant Remediation

We have identified sites at which our utilities or a predecessor company owned or operated a manufactured gas plant or stored manufactured gas. We have also identified other sites that may have been impacted by historical manufactured gas plant activities. Our natural gas utilities are responsible for the environmental remediation of these sites, some of which are in the EPA Superfund Alternative Approach Program. We are also working with various state jurisdictions in our investigation and remediation planning. These sites are at various stages of investigation, monitoring, remediation, and closure.

In addition, we are coordinating the investigation and cleanup of some of these sites subject to the jurisdiction of the EPA under what is called a "multisite" program. This program involves prioritizing the work to be done at the sites, preparation and approval of documents common to all of the sites, and use of a consistent approach in selecting remedies. At this time, we cannot estimate future remediation costs associated with these sites beyond those described below.

The future costs for detailed site investigation, future remediation, and monitoring are dependent upon several variables including, among other things, the extent of remediation, changes in technology, and changes in regulation. Historically, our regulators have allowed us to recover incurred costs, net of insurance recoveries and recoveries from potentially responsible parties, associated with the remediation of manufactured gas plant sites. Accordingly, we have established regulatory assets for costs associated with these sites.

We have established the following regulatory assets and reserves for manufactured gas plant sites as of December 31:
(in millions)20242023
Regulatory assets$570.1 $596.8 
Reserves for future environmental remediation445.8 463.7 

Coal Combustion Residuals Rule

The EPA finalized a rule for CCR in April 2024 that would apply to landfills, historic fill sites, and projects where CCR was placed at a power plant site. The rule will regulate previously exempt closed landfills.

The final rule, which became effective in November 2024 will have an impact on some of our coal ash landfills, requiring additional remediation that is not currently required under the state programs. The rule is being challenged through litigation pending in the D.C. Circuit Court of Appeals. We expect the cost of the additional remediation would be recovered through future rates. See Note 9, Asset Retirement Obligations, for more information on the estimated cost of the additional remediation.

Renewables, Efficiency, and Conservation

Wisconsin Legislation

In 2005, Wisconsin enacted Act 141, which established a goal that 10% of all electricity consumed in Wisconsin be generated by renewable resources annually. WE and WPS have achieved their required renewable energy percentages of 8.27% and 9.74%, respectively, by constructing various wind parks, solar parks, a biomass facility, and by also relying on renewable energy purchases. WE and WPS continue to review their renewable energy portfolios and acquire cost-effective renewables as needed to meet their requirements on an ongoing basis. The PSCW administers the renewable program related to Act 141, and each utility funds the program based on 1.2% of its annual retail operating revenues.
Michigan Legislation

In December 2016, Michigan enacted Act 342, which required 12.5% of the state's electric energy to come from renewables for 2019 and 2020, and energy optimization (efficiency) targets up to 1% annually. The renewable requirement increased to 15.0% for 2021 and beyond. UMERC was in compliance with its requirements under this statute as of December 31, 2024. The legislation continues to allow recovery of costs incurred to meet the standards and provides for ongoing review and revision to assure the measures taken are cost-effective.

In November 2023, Michigan enacted Acts 229, 231 and 235. The acts require electric providers to file a renewable energy plan every two years and to set renewable energy portfolio targets from now until 2040. The proposed renewable energy targets include 15% through 2029, 50% from 2030 through 2034, and 60% renewable energy by 2035 and thereafter. The bill also sets clean energy standards of 80% from 2035 through 2039 and 100% after 2040. The acts only allow natural gas to count as clean energy if it is accompanied with carbon capture and storage. The new acts also revise the requirement a utility must meet in filing its energy waste reduction plans. They require a utility to file a plan every two years until 2025, then every three years thereafter.

Enforcement and Litigation Matters

We and our subsidiaries are involved in legal and administrative proceedings before various courts and agencies with respect to matters arising in the ordinary course of business. Although we are unable to predict the outcome of these matters, management believes that appropriate reserves have been established and that final settlement of these actions will not have a material impact on our financial condition or results of operations.

Consent Decrees

Wisconsin Public Service Corporation – Weston and Pulliam Power Plants

In November 2009, the EPA issued an NOV to WPS, which alleged violations of the CAA's New Source Review requirements relating to certain projects completed at the Weston and Pulliam power plants from 1994 to 2009. WPS entered into a Consent Decree with the EPA resolving this NOV. This Consent Decree was entered by the United States District Court for the Eastern District of Wisconsin in March 2013. With the retirement of Pulliam Units 7 and 8 in October 2018, WPS completed the mitigation projects required by the Consent Decree and received a completeness letter from the EPA in October 2018. See Note 6, Regulatory Assets and Liabilities, for more information about the retirement. Following our significant engagement with the EPA, the agency conditionally terminated the Consent Decree in December 2024.

Joint Ownership Power Plants – Columbia and Edgewater

In December 2009, the EPA issued an NOV to WPL, the operator of the Columbia and Edgewater plants, and the other joint owners of these plants, including MG&E, WE (former co-owner of an Edgewater unit), and WPS. The NOV alleged violations of the CAA's New Source Review requirements related to certain projects completed at those plants. WPS, along with WPL, MG&E, and WE, entered into a Consent Decree with the EPA resolving this NOV. This Consent Decree was entered by the United States District Court for the Western District of Wisconsin in June 2013. As a result of the continued implementation of the Consent Decree related to the jointly owned Columbia and Edgewater plants, the Edgewater Unit 4 generating unit was retired in September 2018. See Note 6, Regulatory Assets and Liabilities, for more information about the retirement. WPL started the process to close out this Consent Decree.