Public Utilities, General Disclosures                
Impairment related to ICC disallowances       $ 12.1 $ 178.9 $ 0.0    
2023 Rate Order | Illinois Commerce Commission (ICC)                
Public Utilities, General Disclosures                
Impairment related to ICC disallowances     $ 178.9          
2023 Rate Order | Illinois Commerce Commission (ICC) | PGL                
Public Utilities, General Disclosures                
Approved rate increase $ 1.6 $ 304.6            
Approved rate increase (as a percent)   43.50%            
Approved return on equity (as a percent)   9.38%            
Approved common equity component average (as a percent)   50.79%            
Disallowed capital costs   $ 236.2            
Additional capital spending approved $ 28.5              
Impairment related to ICC disallowances     177.2          
2023 Rate Order | Illinois Commerce Commission (ICC) | NSG                
Public Utilities, General Disclosures                
Approved rate increase   $ 11.0            
Approved rate increase (as a percent)   11.60%            
Approved return on equity (as a percent)   9.38%            
Approved common equity component average (as a percent)   52.58%            
Disallowed capital costs   $ 1.7            
Impairment related to ICC disallowances     $ 1.7          
2023 Rate Order | Illinois Appellate Court                
Public Utilities, General Disclosures                
Disallowed capital costs               $ 237.9
2023 Rate Order | Illinois Appellate Court | PGL                
Public Utilities, General Disclosures                
Disallowance of future SMP capital investments               $ 116.0
SMP Proceedings | Illinois Commerce Commission (ICC) | PGL | Subsequent event                
Public Utilities, General Disclosures                
Minimum diameter of pipe that does not require replacement | in             36