XML 49 R35.htm IDEA: XBRL DOCUMENT v3.22.0.1
Commitments and Contingencies
12 Months Ended
Dec. 31, 2021
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES COMMITMENTS AND CONTINGENCIES
We and our subsidiaries have significant commitments and contingencies arising from our operations, including those related to unconditional purchase obligations, environmental matters, and enforcement and litigation matters.

Unconditional Purchase Obligations

Our electric utilities have obligations to distribute and sell electricity to their customers, and our natural gas utilities have obligations to distribute and sell natural gas to their customers. The utilities expect to recover costs related to these obligations in future customer rates. In order to meet these obligations, we routinely enter into long-term purchase and sale commitments for various quantities and lengths of time.

The wind generation facilities that are part of our non-utility energy infrastructure segment have obligations to distribute and sell electricity through long-term offtake agreements with their customers for all of the energy produced. In order to support these sales obligations, these companies enter into easements and other service agreements associated with the wind generating facilities.
The following table shows our minimum future commitments related to these purchase obligations as of December 31, 2021, including those of our subsidiaries.
Payments Due By Period
(in millions)Date Contracts Extend ThroughTotal Amounts Committed20222023202420252026Later Years
Electric utility:
Nuclear2033$7,342.8 $531.2 $563.0 $596.8 $632.6 $677.9 $4,341.3 
Coal supply and transportation2025821.8 260.9 213.3 180.0 167.6 — — 
Purchased power2051316.5 65.5 60.7 53.2 46.9 43.8 46.4 
Natural gas utility:
Supply and transportation20481,704.4 349.4 264.7 201.0 128.9 109.2 651.2 
Non-utility energy infrastructure:
Purchased power2051396.3 20.6 22.5 20.6 21.0 21.4 290.2 
Natural gas storage and transportation20486.9 5.1 0.8 — — 0.1 0.9 
Total$10,588.7 $1,232.7 $1,125.0 $1,051.6 $997.0 $852.4 $5,330.0 

Environmental Matters

Consistent with other companies in the energy industry, we face significant ongoing environmental compliance and remediation obligations related to current and past operations. Specific environmental issues affecting us include, but are not limited to, current and future regulation of air emissions such as SO2, NOx, fine particulates, mercury, and GHGs; water intake and discharges; management of coal combustion products such as fly ash; and remediation of impacted properties, including former manufactured gas plant sites.

We have continued to pursue a proactive strategy to manage our environmental compliance obligations, including:

the development of additional sources of renewable electric energy supply;
the addition of improvements for water quality matters such as treatment technologies to meet regulatory discharge limits and improvements to our cooling water intake systems;
the addition of emission control equipment to existing facilities to comply with ambient air quality standards and federal clean air rules;
the protection of wetlands and waterways, biodiversity including threatened and endangered species, and cultural resources associated with utility construction projects;
the retirement of older coal-fired power plants and conversion to modern, efficient, natural gas generation, super-critical pulverized coal generation, and/or replacement with renewable generation;
the beneficial use of ash and other products from coal-fired and biomass generating units;
the remediation of former manufactured gas plant sites;
the reduction of methane emissions across our natural gas distribution system by upgrading infrastructure; and
the reporting of GHG emissions to comply with federal clean air rules.

Air Quality

National Ambient Air Quality Standards

Ozone

After completing its review of the 2008 ozone standard, the EPA released a final rule in October 2015, creating a more stringent standard than the 2008 NAAQS. The 2015 ozone standard lowered the 8-hour limit for ground-level ozone. In December 2020, the EPA completed its 5-year review of the ozone standard and issued a final decision to retain, without any changes, the existing 2015 standard. Under Executive Order 13990, the Biden Administration ordered that all agencies review existing regulations, orders, guidance documents, policies, and similar actions promulgated, issued, or adopted between January 20, 2017 and January 20, 2021. In October 2021, the EPA announced that it will reconsider the December 2020 decision to retain the 2015 ozone standards with no changes and that it is targeting the end of 2023 to complete this reconsideration.
The EPA issued final nonattainment area designations for the 2015 ozone standard in April 2018. The following counties within our Wisconsin service territories were designated as partial nonattainment: Door, Kenosha, Sheboygan, Manitowoc, and Northern Milwaukee/Ozaukee. This re-designation was challenged in the D.C. Circuit Court of Appeals in Clean Wisconsin et al. v. U.S. Environmental Protection Agency. A decision was issued in July 2020 remanding the rule to the EPA for further evaluation. As a result of the July 2020 remand, in June 2021, the EPA published its final action to revise the boundaries for 13 counties associated with six nonattainment areas, including several in Illinois and Wisconsin. Under the new designations, all of Milwaukee and Ozaukee counties are now listed as nonattainment and portions of Racine, Waukesha, and Washington counties have been added to the nonattainment area. Additionally, the Chicago, Illinois, Indiana, and Wisconsin nonattainment area now includes an expanded portion of Kenosha county, and the partial nonattainment areas of Sheboygan, Door, and Manitowoc counties have also been expanded. Preliminary 2019-2021 monitoring data indicates that the Milwaukee, Sheboygan, and Chicago nonattainment areas will likely be adjusted to "moderate" nonattainment for the 2015 standard.

In February 2021, the WDNR proposed draft revisions to the Wisconsin Administrative Code to adopt the 2015 ozone standard and incorporate by reference the federal air pollution monitoring requirements related to the NAAQS. The Natural Resources Board adopted the rule as proposed during their June 2021 meeting and the rule is now in legislative review. We believe that we are well positioned to meet the requirements associated with the 2015 ozone standard and do not expect to incur significant costs to comply with associated state or federal rules.

Particulate Matter

In addition to the 2015 ozone standard, in December 2020, the EPA completed its 5-year review of the 2012 standard for particulate matter, including fine particulate matter. The EPA determined that no revisions were necessary to the current standard. This determination was also subject to review under Executive Order 13990 and in June 2021, the EPA announced it would reconsider the December 2020 decision. Under the Biden Administration's policy review, the EPA concluded that the scientific evidence and information from the December 2020 determination supports revising the level of the annual standard for the particulate matter NAAQS to below the current level of 12 micrograms per cubic meter, while retaining the 24-hour standard. A proposed rule-making is expected in summer 2022, and a final rule is expected in spring 2023. All counties within our service territories are in attainment with the current 2012 standards. If the EPA lowers the standard to 10 or 11 micrograms per cubic meter, our service territories should remain in attainment. If the EPA lowers it below 10 micrograms per cubic meter, there could be some non-attainment areas that may affect permitting of some smaller ancillary equipment located at our facilities.

Climate Change

The ACE rule, effective since September 2019, was vacated by the D.C. Circuit Court of Appeals in January 2021. The ACE rule replaced the Clean Power Plan and provided existing coal-fired generating units with standards for achieving GHG emission reductions. In a memorandum issued to the EPA regional administrators in February 2021, the EPA stated that the D.C. Circuit Court decision meant that no existing rule regulates GHG emissions from electric generating units. The EPA is currently reviewing its options for such regulations and has signaled that a draft rule may be released in 2022 at the earliest. In October 2021, the Supreme Court agreed to review the D.C. Circuit Court's ruling vacating the EPA's ACE rule. The Supreme Court is expected to review a number of issues regarding the scope of the EPA's regulatory authority to utilize Section 111(d) of the CAA to address CO2 emissions. Arguments are expected to take place in early 2022 with a decision expected by the summer of 2022.

In January 2021, the EPA finalized a rule to revise the New Source Performance Standards for GHG emissions from new, modified, and reconstructed fossil-fueled power plants. The rule became effective in March 2021; however, it was vacated by the D.C. Circuit Court of Appeals in April 2021. The EPA has signaled that a rule replacement is expected by June 2022. We continue to move forward on the ESG Progress Plan, which is heavily focused on reducing GHG emissions.

Our ESG Progress Plan includes the retirement of older, fossil-fueled generation, to be replaced with zero-carbon-emitting renewables and clean natural gas-fueled generation. We have already retired more than 1,800 MW of coal-fired generation since the beginning of 2018. Through our ESG Progress Plan, we expect to retire approximately 1,600 MW of additional fossil-fueled generation by 2025, which includes the planned retirements in 2023-2024 of OCPP Units 5-8 and the jointly-owned Columbia Units 1-2. In May 2021, we announced goals to achieve reductions in carbon emissions from our electric generation fleet by 60% by 2025 and by 80% by 2030, both from a 2005 baseline. We expect to achieve these goals by making operating refinements, retiring less efficient generating units, and executing our capital plan. Over the longer term, the target for our generation fleet is net-zero CO2 emissions by 2050.
We also continue to reduce methane emissions by improving our natural gas distribution system. We set a target across our natural gas distribution operations to achieve net-zero methane emissions by 2030. We plan to achieve our net-zero goal through an effort that includes both continuous operational improvements and equipment upgrades, as well as the use of RNG throughout our utility systems.

We are required to report our CO2 equivalent emissions from the electric generating facilities we operate under the EPA Greenhouse Gases Reporting Program. Based upon our preliminary analysis of the data, we estimate that we will report CO2 equivalent emissions of approximately 22.0 million metric tonnes to the EPA for 2021. The level of CO2 and other GHG emissions varies from year to year and is dependent on the level of electric generation and mix of fuel sources, which is determined primarily by demand, the availability of the generating units, the unit cost of fuel consumed, and how our units are dispatched by MISO.

We are also required to report CO2 equivalent emissions related to the natural gas that our natural gas utilities distribute and sell. Based upon our preliminary analysis of the data, we estimate that we will report CO2 equivalent emissions of approximately 23.6 million metric tonnes to the EPA for 2021.

Water Quality

Clean Water Act Cooling Water Intake Structure Rule

In August 2014, the EPA issued a final regulation under Section 316(b) of the Clean Water Act that requires the location, design, construction, and capacity of cooling water intake structures at existing power plants to reflect the BTA for minimizing adverse environmental impacts. The federal rule became effective in October 2014 and applies to all of our existing generating facilities with cooling water intake structures, except for the ERGS units, which were permitted under the rules governing new facilities. In 2016, the WDNR initiated a state rulemaking process to incorporate the federal Section 316(b) requirements into the Wisconsin Administrative Code. This new state rule, NR 111, became effective in June 2020, and the WDNR will apply it when establishing BTA requirements for cooling water intake structures at existing facilities. These BTA requirements are incorporated into Wisconsin Pollutant Discharge Elimination System permits for WE and WPS facilities.

We have received BTA determinations for OC 5 through OC 8 and VAPP. Although we currently believe that existing technology at the PWGS satisfies the BTA requirements, a final determination will not be made until the discharge permit is renewed for this facility, which is expected to be in the second quarter of 2022. We have received interim BTA determinations for Weston Units 2, 3, and 4. A final BTA decision for the Weston facility is expected during its next permit renewal in late 2023.

As a result of past capital investments completed to address Section 316(b) compliance at WE and WPS, we believe our fleet overall is well positioned to continue to meet this regulation and do not expect to incur significant additional compliance costs.

Steam Electric Effluent Limitation Guidelines

The EPA's final 2015 ELG rule took effect in January 2016 and was modified in 2020 to revise the treatment technology requirements related to BATW and wet FGD wastewaters at existing facilities. This rule created new requirements for several types of power plant wastewaters. The two new requirements that affect WE and WPS relate to discharge limits for BATW and wet FGD wastewater. Our power plant facilities already have advanced wastewater treatment technologies installed that meet many of the discharge limits established by this rule. There will, however, need to be facility modifications to meet water permit requirements for the BATW systems at Weston Unit 3 (to be completed by December 2023) and OC 7 and OC 8 (completed and placed in-service in mid-2021). Wastewater treatment system modifications also will be required for wet FGD discharges and site wastewater from the OCPP and ERGS units. Based on engineering cost estimates, we expect that compliance with the ELG rule will require approximately $110 million in capital investment. In December 2021, the PSCW Division of Energy Regulation and Analysis issued a Certificate of Authority approving the ERGS FGD wastewater treatment system modification. The BATW modifications do not require PSCW approval prior to construction. All of these ELG required projects are either in-service or are on track for completion by the Wisconsin Pollutant Discharge Elimination System permit deadlines.

In July 2021, the EPA announced that it intends to initiate rulemaking to revise the ELG Rule as modified in 2020. The EPA has stated that the ELG Rule will continue to be implemented and enforced while the agency pursues this rulemaking process. The EPA plans to propose a revised rule in the fall of 2022.
Waters of the United States

In December 2021, the EPA and the United States Army Corps of Engineers together released a proposed rule to repeal the April 2020 Navigable Waters Protection Rule that defined WOTUS. The purpose of this proposed rule will be to restore regulations defining WOTUS that were in place prior to 2015 and to update certain provisions to be consistent with relevant Supreme Court decisions. The pre-2015 approach involves applying factors established through case law and agency precedents to determine whether a wetland or surface drainage feature is subject to federal jurisdiction. In January 2022, the Supreme Court granted certiorari in a case to evaluate the proper test for determining whether wetlands are WOTUS. At this point, our projects requiring federal permits are moving ahead, but we are monitoring to better understand potential future impacts.

Land Quality

Manufactured Gas Plant Remediation

We have identified sites at which our utilities or a predecessor company owned or operated a manufactured gas plant or stored manufactured gas. We have also identified other sites that may have been impacted by historical manufactured gas plant activities. Our natural gas utilities are responsible for the environmental remediation of these sites, some of which are in the EPA Superfund Alternative Approach Program. We are also working with various state jurisdictions in our investigation and remediation planning. These sites are at various stages of investigation, monitoring, remediation, and closure.

In addition, we are coordinating the investigation and cleanup of some of these sites subject to the jurisdiction of the EPA under what is called a "multisite" program. This program involves prioritizing the work to be done at the sites, preparation and approval of documents common to all of the sites, and use of a consistent approach in selecting remedies. At this time, we cannot estimate future remediation costs associated with these sites beyond those described below.

The future costs for detailed site investigation, future remediation, and monitoring are dependent upon several variables including, among other things, the extent of remediation, changes in technology, and changes in regulation. Historically, our regulators have allowed us to recover incurred costs, net of insurance recoveries and recoveries from potentially responsible parties, associated with the remediation of manufactured gas plant sites. Accordingly, we have established regulatory assets for costs associated with these sites.

We have established the following regulatory assets and reserves for manufactured gas plant sites as of December 31:
(in millions)20212020
Regulatory assets$630.9 $638.2 
Reserves for future environmental remediation532.6 532.9 

Renewables, Efficiency, and Conservation

Wisconsin Legislation

In 2005, Wisconsin enacted Act 141, which established a goal that 10% of all electricity consumed in Wisconsin be generated by renewable resources annually. WE and WPS have achieved their required renewable energy percentages of 8.27% and 9.74%, respectively, by constructing various wind parks, solar parks, a biomass facility, and by also relying on renewable energy purchases. WE and WPS continue to review their renewable energy portfolios and acquire cost-effective renewables as needed to meet their requirements on an ongoing basis. The PSCW administers the renewable program related to Act 141, and each utility funds the program based on 1.2% of its annual retail operating revenues.

Michigan Legislation

In December 2016, Michigan enacted Act 342, which required 12.5% of the state's electric energy to come from renewables for 2019 and 2020, and energy optimization (efficiency) targets up to 1% annually. The renewable requirement increased to 15.0% for 2021 and beyond. UMERC was in compliance with its requirements under this statute as of December 31, 2021. The legislation continues to allow recovery of costs incurred to meet the standards and provides for ongoing review and revision to assure the measures taken are cost-effective.
Enforcement and Litigation Matters

We and our subsidiaries are involved in legal and administrative proceedings before various courts and agencies with respect to matters arising in the ordinary course of business. Although we are unable to predict the outcome of these matters, management believes that appropriate reserves have been established and that final settlement of these actions will not have a material impact on our financial condition or results of operations.

Consent Decrees

Wisconsin Public Service Corporation – Weston and Pulliam Power Plants

In November 2009, the EPA issued an NOV to WPS, which alleged violations of the CAA's New Source Review requirements relating to certain projects completed at the Weston and Pulliam power plants from 1994 to 2009. WPS entered into a Consent Decree with the EPA resolving this NOV. This Consent Decree was entered by the United States District Court for the Eastern District of Wisconsin in March 2013.

With the retirement of Pulliam Units 7 and 8 in October 2018, WPS completed the mitigation projects required by the Consent Decree and received a completeness letter from the EPA in October 2018. See Note 6, Regulatory Assets and Liabilities, for more information about the retirement. We are working with the EPA on a closeout process for the Consent Decree.

Joint Ownership Power Plants – Columbia and Edgewater

In December 2009, the EPA issued an NOV to Wisconsin Power and Light Company, the operator of the Columbia and Edgewater plants, and the other joint owners of these plants, including Madison Gas and Electric Company, WE (former co-owner of an Edgewater unit), and WPS. The NOV alleged violations of the CAA's New Source Review requirements related to certain projects completed at those plants. WPS, along with Wisconsin Power and Light Company, Madison Gas and Electric Company, and WE, entered into a Consent Decree with the EPA resolving this NOV. This Consent Decree was entered by the United States District Court for the Western District of Wisconsin in June 2013. As a result of the continued implementation of the Consent Decree related to the jointly owned Columbia and Edgewater plants, the Edgewater 4 generating unit was retired in September 2018. See Note 6, Regulatory Assets and Liabilities, for more information about the retirement. Wisconsin Power and Light Company has started the process to close out this Consent Decree.