Facilities - Our corporate group and digital division together occupy approximately 5,700 square feet of commercial office space located at 200 Canal View Boulevard, Rochester, New York under a lease that expires in December 2020, at a rental rate of approximately $6,100 per month. Our Plastics division leases approximately 15,000 square feet under a lease that expires December 31, 2018 for approximately $13,000 per month. In addition, the Company owns a 40,000 square foot packaging and printing plant in Victor, New York, a suburb of Rochester, New York. The Company’s Technology Management division leases executive office space in Reston, Virginia under a 12 month lease that expires in December 2017 for approximately $600 per month, and also leases a sales and research and development facility in Plano, Texas under a 12 month lease that expires in December 2017 for approximately $1,200 per month. The Company believes that it can negotiate renewals or similar lease arrangements on acceptable terms when our current leases expire. We believe that our facilities are adequate for our current operations.

 

Equipment Leases – From time to time, the Company leases certain production and office equipment, digital and offset presses, laminating and finishing equipment for its various printing operations. The leases may be capital leases or operating leases and are generally for a term of 36 to 60 months. As of December 31, 2016 and 2015, the Company did not have any capitalized leases.

 

The following table summarizes the Company’s lease commitments.

 

    Operating Leases  
    Equipment     Facilities     Total  
                   
Payments made in 2016   $ 48,499     $ 247,937     $ 296,436  
Future minimum lease commitments:                        
2017   $ 44,131     $ 259,385     $ 303,516  
2018     43,258       243,002       286,260  
2019     14,419       68,820       83,239  
2020     14,419       68,820       83,239  
2021     -       -       -  
Total future minimum lease commitments   $ 116,227     $ 640,027     $ 756,254  

 

Employment Agreements - The Company has employment or severance agreements with five members of its management team with terms ranging from one to five years through December 2019. The employment or severance agreements provide for severance payments in the event of termination for certain causes. As of December 31, 2016, the minimum annual severance payments under these employment agreements are, in aggregate, approximately $840,000.

 

Related Party Payments - During 2015, the Company paid consulting fees of approximately $35,000 to Patrick White, its former CEO, under a consulting agreement that expired on February 28, 2015. The Company did not have any payments to Mr. White in 2016.

 

Contingent Litigation Payments - The Company retains the services of professional service providers, including law firms that specialize in intellectual property licensing, enforcement and patent law. These service providers are often retained on an hourly, monthly, project, contingent or a blended fee basis. In contingency fee arrangements, a portion of the legal fee is based on predetermined milestones or the Company’s actual collection of funds. The Company accrues contingent fees when it is probable that the milestones will be achieved and the fees can be reasonably estimated. As of December 31, 2016 and 2015, the Company has not accrued any contingent legal fees pursuant to these arrangements.

 

Legal Proceedings - On November 26, 2013, DSS Technology Management filed suit against Apple, Inc. (“Apple”), in the United States District Court for the Eastern District of Texas, for patent infringement (the “Apple Litigation”). The complaint alleges infringement by Apple of DSS Technology Management’s patents that relate to systems and methods of using low power wireless peripheral devices. DSS Technology Management is seeking a judgement for infringement, injunctive relief, and compensatory damages from Apple. On October 28, 2014, the case was stayed by the District Court pending a determination of Apple’s motion to transfer the case to the Northern District of California. On November 7, 2014, the case was transferred to the Northern District of California. In December 2014, Apple filed two IPR petitions with PTAB for review of the patents at issue in the case. The PTAB instituted the IPRs on June 25, 2015. The California District Court then stayed the case pending the outcome of those IPR proceedings. Oral arguments of the IPRs took place on March 15, 2016, and on June 17, 2016, PTAB ruled in favor of Apple on both IPR petitions. DSS Technology Management has filed an appeal with the Federal Circuit seeking reversal of the PTAB decisions. The appeal is still pending as of the date of this Report. The patent assets underlying this matter had no carrying value as of the date of the PTAB decision and therefore, there were no impairment considerations as a result of the decision.

 

On March 10, 2014, DSS Technology Management filed suit in the United States District Court for the Eastern District of Texas against Taiwan Semiconductor Manufacturing Company, TSMC North America, TSMC Development, Inc. (referred to collectively as TSMC), Samsung Electronics Co., Ltd, Samsung Electronics America, Inc., Samsung Telecommunications America L.L.C., Samsung Semiconductor, Inc., Samsung Austin Semiconductor LLC (referred to collectively as Samsung), and NEC Corporation of America (referred to as NEC), for patent infringement involving certain of its semiconductor patents. DSS Technology Management sought a judgment for infringement, injunctive relief, and money damages from each of the named defendants. On March 3, 2015, a Markman hearing was held in the Eastern District of Texas. Based on the District Court’s claim construction order issued on April 9, 2015, DSS Technology Management and TSMC entered in to a Joint Stipulation and Proposed Final Judgment of Non-Infringement dated May 4, 2015, subject to DSS Technology Management’s right to appeal the court’s claim construction order to the Federal Circuit. On March 22, 2016, the Federal Circuit ruled in favor of TSMC in the appeal, effectively ending the litigation with TSMC and Samsung. On April 28, 2015, DSS Technology Management reached a confidential settlement with NEC, ending the litigation with NEC.

  

On February 16, 2015, DSS Technology Management filed suit in the United States District Court, Eastern District of Texas, against defendants Intel Corporation, Dell, Inc., GameStop Corp., Conn’s Inc., Conn Appliances, Inc., NEC Corporation of America, Wal-Mart Stores, Inc., Wal-Mart Stores Texas, LLC, and AT&T, Inc. The complaint alleges patent infringement and seeks judgment for infringement of two of DSSTM’s patents, injunctive relief and money damages. On December 9, 2015, Intel filed IPR petitions with PTAB for review of the patents at issue in the case. Intel’s IPRs were instituted by PTAB on June 8, 2016. The Intel litigation has been stayed by the District Court pending final determination of the IPR proceedings.

 

On July 16, 2015, DSS Technology Management filed three separate lawsuits in the United States District Court for the Eastern District of Texas alleging infringement of certain of its semiconductor patents. The defendants are SK Hynix et al., Samsung Electronics et al., and Qualcomm Incorporated. Each respective complaint alleges patent infringement and seeks judgment for infringement, injunctive relief and money damages. On November 12, 2015, SK Hynix filed an IPR petition with PTAB for review of the patent at issue in their case. SK Hynix’s IPR was instituted by the PTAB on May 11, 2016. On August 16, 2016, DSS Technology Management and SK Hynix entered into a confidential settlement agreement ending the litigation between them. The pending SK Hynix IPR was then terminated by mutual agreement of the parties on August 31, 2016. On March 18, 2016, Samsung also filed an IPR petition. On September 23, 2016, Samsung’s IPR was instituted by PTAB. Qualcomm then filed its IPR proceeding on July 1, 2016, which was later joined with Intel’s IPRs in August 2016 by PTAB. As of the date of this Report, PTAB has not yet issued a decision on any of the pending IPR proceedings.

 

In addition to the foregoing, the Company may be subject to other legal proceedings that arise in the ordinary course of business and have not been finally adjudicated. Adverse decisions in the foregoing may have a material adverse effect on its results of operations, cash flows or our financial condition. The Company accrues for potential litigation losses when a loss is probable and reasonably estimable.