EX-99.1 2 a19-19176_3ex99d1.htm EX-99.1

Exhibit 99.1

 

Technical Report on the Shahuindo Mine

 

Cajabamba, Peru

 

 

Prepared by:

 

Carl E. Defilippi, SME Registered Member — Kappes, Cassiday & Associates

 

Charles V. Muerhoff, SME Registered Member — Tahoe Resources Inc.

 

Tim Williams, FAusIMM — Tahoe Resources Inc.

 

January 25, 2016

 


 

DATE AND SIGNATURE PAGE

 

The authors of this report, Technical Report on the Shahuindo Mine, Cajabamba, Peru, are Qualified Persons as defined by Canadian National Instrument 43-101. The effective date of this report is 01 January 2016. The effective date of the Mineral Resource estimate is 15 April 2015. The effective date of the Mineral Reserve estimate is 01 November 2015. The report was completed and signed on 25 January 2016.

 

Signed this 25th day of January, 2016

 

/s/ Carl E. Defilippi

 

Carl E. Defilippi, M.Sc., C.E.M.

 

SME Registered Member 775870RM

 

Project Manager

 

Kappes, Cassiday & Associates

 

 

 

/s/ Charles V. Muerhoff

 

Charles V. Muerhoff, B.Sc.

 

SME Registered Member 4182272RM

 

Vice President Technical Services

 

Tahoe Resources Inc.

 

 

 

/s/ Tim Williams

 

Tim Williams, M.Sc.

 

FAusIMM

 

Vice President Operations & Peru Country Manager

 

Tahoe Resources Inc.

 

 


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

CONTENTS

 

 

 

 

 

LIST OF FIGURES

XI

 

 

 

LIST OF TABLES

XIV

 

 

 

1.0

EXECUTIVE SUMMARY

1

 

 

 

1.1

Introduction

1

1.2

Principal Findings

1

1.3

Property Description and Location

3

1.4

Mineral Tenure

3

1.5

Permits

3

1.6

Environment

4

1.7

History

4

1.8

Geology and Mineralization

4

1.9

Drilling

5

1.10

Sample Preparation and Analysis

5

1.11

Data Verification

6

1.12

Mineral Processing and Metallurgical Testing

6

1.13

Mineral Resource and Mineral Reserve Estimates

7

1.13.1   Mineral Resources

8

1.13.2   Mineral Reserve Estimate

9

1.14

Mining Method and Mine Production Schedule

9

1.15

Processing

11

1.16

Infrastructure

12

1.17

Mine Closure

12

1.18

Capital and Operating Costs

13

1.18.1   Operating Costs

13

1.18.2   Capital Costs

13

1.18.3   Financial Analysis

14

1.19

Exploration Status

15

1.20

Conclusions and Recommendations

15

 

 

 

2.0

INTRODUCTION

17

 

 

 

2.1

Purpose and Basis of Report

17

2.2

Sources of Information

17

 

i


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

2.3

Qualified Persons and Site Visits

18

2.4

Effective Dates

18

2.5

Units of Measurements

19

2.6

Abbreviations and Acronyms

19

 

 

 

3.0

RELIANCE ON OTHER EXPERTS

21

 

 

 

4.0

PROPERTY DESCRIPTION AND LOCATION

22

 

 

 

4.1

Location

22

4.2

Mineral Tenure and Title

22

4.3

Surface Rights

25

4.4

Informal Mining Activity

25

4.5

Environmental Considerations

26

4.5.1   Environmental Regulations

26

4.6

Permits

27

4.6.1   Environmental Laws

29

4.6.2   Mine Development, Exploitation and Processing Activities

30

4.6.3   Mine Closure and Site Remediation

30

4.6.4   Existing Environmental Conditions

30

4.7

Royalties, Taxes and Fees

30

4.7.1   Maintenance Fees

30

4.7.2   Minimum Production Obligation

31

4.7.3   Royalties, OSINERGMIN Contribution and OEFA Contribution

31

4.7.4   Ownership of Mining Rights

32

4.7.5   Taxation and Foreign Exchange Controls

33

4.7.6   Worker Participation

33

4.7.7   Regulatory and Supervisory Bodies

34

4.8

Risks that may affect Access, Title, or the Right or Ability to Perform Work

34

 

 

 

5.0

ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY

36

 

 

 

5.1

Accessibility

36

5.2

Climate

37

5.3

Local Resources & Infrastructure

37

5.4

Physiography

38

5.5

Seismology

39

 

ii


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

5.6

Population Centers

39

5.7

Local Infrastructure and Services

40

 

 

 

6.0

HISTORY

42

 

 

 

 

6.1

Ownership History

42

6.2

Exploration History

42

6.3

Historical Mineral Resource and Mineral Reserve Estimates

44

6.3.1   Pre-NI 43-101 Mineral Resource Estimates

44

6.3.2   Prior NI 43-101 Mineral Resource Estimates

45

6.3.3   Prior NI 43-101 Mineral Reserve Estimates

49

6.4

Historical Production

51

 

 

 

7.0

GEOLOGICAL SETTING AND MINERALIZATION

52

 

 

 

7.1

Regional Geology

52

7.2

Project Geology

56

7.3

Mineralization

65

7.4

Structural Geology

66

7.5

Hydrothermal Alteration

69

7.6

Geometallurgy

73

 

 

 

8.0

DEPOSIT TYPES

74

 

 

 

8.1

Deposit Types

74

 

 

 

9.0

EXPLORATION

76

 

 

 

9.1

Exploration Strategy

76

9.2

Geophysical Surveys

76

9.3

Geochemistry

79

 

 

 

10.0

DRILLING

81

 

 

 

10.1

Introduction

81

10.2

Drilling Methods and Equipment

83

10.3

Collar Surveys

84

10.4

Downhole Surveys

85

10.5

Drill Logging

86

10.6

Drill Database

86

10.7

Core Recovery

86

10.8

Comparison of Core and Reverse Circulation Drilling

87

 

iii


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

10.9

Tahoe 2015 Drill Program

89

10.9.1   Infill Drilling

91

10.9.2   Step-Out Drilling

91

10.9.3   Exploration

91

10.9.4   Other Drilling

91

 

 

 

11.0

SAMPLE PREPARATION, ANALYSES AND SECURITY

93

 

 

 

11.1

Drill Sampling

93

11.1.1   Diamond Drill Core Sampling

93

11.1.2   Reverse Circulation Chip Sampling

93

11.1.3   Sample Storage

95

11.2

Sample Preparation and Analysis

95

11.2.1   Atimmsa

95

11.2.2   Asarco

95

11.2.3   Southern Peru

96

11.2.4   Sulliden

96

11.2.5   Rio Alto

97

11.3

Bulk Density Determinations

97

11.4

Sample Security

98

11.5

Quality Assurance/Quality Control

98

11.5.1   Asarco

98

11.5.2   Other Drilling Programs Prior to Sulliden

98

11.5.3   Sulliden

98

11.5.4   Rio Alto

100

11.5.5   Blanks

100

11.5.6   Field Duplicates

101

11.5.7   Standards

103

11.6

Summary Statement

106

 

 

 

12.0

DATA VERIFICATION

107

 

 

 

12.1

Met-Chem 2003/2004 Audit

107

12.2

AMEC 2009 Database Audit and Verification

107

12.3

MDA 2012 Database Audit

107

12.4

Tahoe 2015 Database Audit

108

12.5

Statement on Data Verification

108

 

iv


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

13.0

MINERAL PROCESSING AND METALLURGICAL TESTING

109

 

 

 

13.1

Metallurgical Testing Summary

109

13.2

Pre-2014 Metallurgical Test Summary

111

13.2.1   Heap Leach Consultants Test Program

111

13.2.2   2009 to 2012 Kappes, Cassiday & Associates Test Program

112

13.3

2014 Kappes, Cassiday & Associates Test Program

116

13.4

2014 and 2015 Test Programs

116

13.4.1   Rio Alto, Tahoe Resources and SGS Column Leach Tests

116

13.4.2   Discussion on the Results of the Rio Alto and SGS Column Leach Tests

121

13.4.3   SGS Bottle Roll Tests

123

13.4.4   Compacted Permeability Tests

124

13.5

Estimated Field Recoveries, Leach Times and Reagent Requirements

127

13.5.1   ROM Field Design Parameters

127

13.5.2   Primary Crushed Ore Field Design Parameters

130

13.6

Recommendations and Conclusions

133

 

 

 

14.0

MINERAL RESOURCES ESTIMATE

135

 

 

 

14.1

Introduction

135

14.2

Database

135

14.3

Geological Modeling

137

14.3.1   Lithologic Domains

137

14.3.2   Structural Domains

138

14.3.3   Oxidation Domains

139

14.4

Grade Estimation Domains

139

14.4.1   Gold Estimation Domains

139

14.4.2   Silver Estimation Domains

143

14.4.3   Other Estimation Domains

143

14.4.4   Sample Selection and Compositing

143

14.5

Statistics

144

14.5.1   Bulk Density

144

14.5.2   Gold Statistics

144

14.5.3   Silver Statistics

147

14.5.4   Minor Elements

149

14.6

Variography

151

 

v


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.7

Block Modelling

152

14.8

Grade Estimation

154

14.9

Mineral Resources

157

14.9.1   Mineral Resource Definitions

157

14.9.2   Shahuindo Mineral Resources

158

14.10

Resource Model Checks

162

14.10.1   Composites vs Model Grades

162

14.10.2   Nearest Neighbor Check Estimate

163

14.10.3   Visual Comparisons

165

14.10.4   Additional Information and Discussion

165

 

 

 

15.0

MINERAL RESERVE ESTIMATES

169

 

 

 

15.1

Mineral Reserves

169

15.1.1   Mineral Reserve Definitions

169

15.1.2   Shahuindo Mineral Reserves

170

15.2

Cut-off Grade

171

15.3

Assumptions and Parameters

172

15.4

Dilution

173

15.5

Pit Optimization

173

15.6

Pit Optimization Results

174

 

 

 

16.0

MINING METHODS

177

 

 

 

16.1

Geotechnical

177

16.2

Hydrogeology and Hydrology

179

16.3

Mine Layout

181

16.4

Mining

183

16.5

Pit Design

185

16.5.1   Bench Height

185

16.5.2   Final Pit Design

185

16.5.3   Comparison of Final Pit Design to the Optimum Whittle shell

185

16.6

In-pit Inferred Resources

187

16.7

Mine Production Schedule

187

16.7.1   Initial Mining Strategy: Phase 1

187

16.7.2   Mining Strategy: Phase 2

188

16.7.3   Mining Schedule

189

 

vi


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

16.8

Mining Equipment

191

 

 

 

17.0

RECOVERY METHODS

194

 

 

 

17.1

Phase 1 - Run of Mine Processing

194

17.1.1   Processing Flow Path — Run of Mine Material

194

17.1.2   Run of Mine Leach Process

197

17.1.3   Process Plant

198

17.2

Phase 2 — Crushing and Agglomeration

199

17.2.1   Process and Flow Path

199

17.2.2   Process Plant

202

17.3

Heap Leach Pad Design by Anddes

202

17.4

Phase 1 and 2 Process Parameters

203

 

 

 

18.0

PROJECT INFRASTRUCTURE

204

 

 

 

18.1

Services and Infrastructure

204

18.1.1   Roads

204

18.1.2   Power Supply

205

18.1.3   Water Supply

206

18.1.4   Sewage System

206

18.1.5   Solid Waste Disposal

207

18.2

Project Buildings

207

18.2.1   Truck Shop

207

18.2.2   Explosive Magazine

207

18.2.3   Warehouse and Process Maintenance

208

18.2.4   Fuel Stations

208

18.2.5   Offices

208

18.2.6   Construction and Operations Camps

208

18.2.7   Dining Facilities

209

18.3

Miscellaneous Site Services

209

18.3.1   Laboratory

209

18.3.2   Security

209

18.3.3   Medical Center/Clinic

209

18.3.4   Communications

210

 

 

 

19.0

MARKET STUDIES AND CONTRACTS

211

 

 

 

19.1

Metal Contracts

211

 

vii


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

19.2

Mining Alliance

211

 

 

 

20.0

ENVIRONMENTAL STUDIES, PERMITTING AND SOCIAL OR COMMUNITY IMPACT

213

 

 

 

20.1

Environmental Management Plan

213

20.2

Environmental Studies

213

20.2.1   Environmental Impact Statement

213

20.2.2   Geochemical Characterization

214

20.2.3   Site Monitoring

218

20.2.4   Closure Plan

218

20.2.5   Existing Environmental Conditions

220

20.3

Permits

220

20.3.1   Exploration

220

20.3.2   Mine Construction and Operations

221

20.4

Social Impact

223

20.4.1   Location of the Study Area

223

20.4.2   Social Baseline Study

223

20.4.3   Public Consultation and Engagement Plan

225

20.4.4   Community Development Program

225

 

 

 

21.0

CAPITAL AND OPERATING COSTS

227

 

 

 

21.1

Capital Cost Estimate

227

21.1.1   List of Areas

227

21.1.2   Basis of Estimate

227

21.1.3   Capital Estimate

227

21.2

Operating Cost Estimate

228

 

 

 

22.0

ECONOMIC ANALYSIS

230

 

 

 

22.1

Mine Production Statistics

230

22.2

Process Plant Production Statistics

230

22.3

Capital Expenditures

231

22.3.1   Project Capital

231

22.3.2   Sustaining Capital

231

22.3.3   Working Capital

231

22.4

Salvage Value

232

22.5

Revenue

232

 

viii


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

22.6

Shipping and Refining

232

22.7

Operating Costs

232

22.8

Total Cash Cost

233

22.8.1   Worker Profit Share and other production taxes

233

22.8.2   Reclamation and Closure

233

22.8.3   Depreciation

233

22.8.4   Taxation

233

22.9

Project Financing

234

22.10

Net Income After Tax

234

22.11

NPV and IRR

234

22.12

Sensitivities

234

22.13

Shahuindo Financial Model

236

 

 

 

23.0

ADJACENT PROPERTIES

240

 

 

 

24.0

OTHER RELEVANT DATA AND INFORMATION

241

 

 

 

24.1

Construction and Mining Activities through 01 January 2016

241

24.1.1   Construction

241

24.1.2   Mine and Plant Commissioning

250

24.2

Exploration Potential

253

24.2.1   San Lorenzo and Choloque

253

24.2.2   Shahuindo Southeast Extension and El Sauce

256

24.2.3   La Chilca Baja Cu-Au porphyry

257

24.2.4   La Chilca Alta

257

24.2.5   Azules

258

24.2.6   Algamarca Au-Ag-Cu Vein system

260

24.2.7   Cantera

262

24.2.8   Malvas

263

 

 

 

25.0

INTERPRETATION AND CONCLUSIONS

264

 

 

 

 

26.0

RECOMMENDATIONS

266

 

 

 

 

27.0

REFERENCES

269

 

 

 

28.0

AUTHORS CERTIFICATES

273

 

 

 

28.1

Certificate of Qualified Person — Carl E. Defilippi

274

 

ix


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

28.2

Certificate of Qualified Person — Charles V. Muerhoff

275

28.3

Certificate of Qualified Person — Tim Williams

276

 

 

Appendix

 

Post-Resource Drill Intercepts

 

 

x


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

LIST OF FIGURES

 

 

 

Figure 4.1-1

Shahuindo Project Location Map

22

Figure 4.2-1

Mineral Claim Location Map

24

Figure 5.1-1

Shahuindo Road Route from Cajamarca

36

Figure 7.1-1

Shahuindo Regional Geology

54

Figure 7.1-2

Shahuindo Regional Cross Section

55

Figure 7.2-1

Shahuindo Local Geology

57

Figure 7.2-2

Local Stratigraphic Column for the Carhuaz/Farrat Formations

58

Figure 7.2-3

Multiphase Intrusion Crosscutting Sedimentary Rocks (Section E1100)

61

Figure 7.2-4

Multiphase Intrusion Crosscutting the Sedimentary Rocks (Section X-X’)

62

Figure 7.2-5

Sedimentological Features for Determining Stratigraphic Sequencing

63

Figure 7.2-6

Intrusive Relationships

64

Figure 7.2-7

Monolithic-Clast Breccia

65

Figure 7.4-1

Combined Structure and Mineralization Map - Shahuindo Project

68

Figure 7.5-1

Jarosite in Outcrop

70

Figure 7.5-2

Hydrothermal Alteration Section — Shahuindo Project (Section E1100)

71

Figure 7.5-3

Hydrothermal Alteration Section — Shahuindo Project (Section XX’)

72

Figure 8.1-1

Spatial Relationship of Intermediate Sulfidation Deposits

75

Figure 9.2-1

Shahuindo — Magnetic Survey Results

77

Figure 9.2-2

Shahuindo — IP Survey Results

78

Figure 9.3-1

Shahuindo — Rock Geochemistry

79

Figure 10.1-1

Shahuindo Drill Hole Location Map

82

Figure 10.8-1

Comparative Plot of Core and RC Gold Assays

88

Figure 10.8-2

Comparison of RC to RC+DDH Model Estimates

89

Figure 10.9-1

Post-Resource Drilling

90

Figure 11.5-1

Blank Analyses 2015 Drill Program

101

Figure 11.5-2

Field Duplicates 2015 RC Drill Program - All Au Grade Ranges

102

Figure 11.5-3

Field Duplicates 2015 RC Drill Program - All Ag Grade Ranges

102

Figure 11.5-4

Field Duplicates 2015 RC Drill Program - Au Grade Range 0.1g/t to 0.3g/t

103

Figure 11.5-5

Chart of Au Analyses of Standard 05

104

Figure 11.5-6

Chart of Au Analyses of Standard 54

104

Figure 11.5-7

Chart of Ag Analyses of Standard 06

105

Figure 11.5-8

Chart of Ag Analyses of Standard 54

105

 

xi


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Figure 13.1-1

Location of Metallurgical Drill Holes

110

Figure 13.4-1

Permeability Rate and Fines Content at Various Simulated Heap Heights

126

Figure 13.4-2

Permeability Rate and Rock Type at Various Simulated Heap Heights

126

Figure 14.2-1

Plan Projection Displaying Zones of Infill Drilling at 25m x 25m Spacing

136

Figure 14.3-1

Lithologic Domains — Section E400

138

Figure 14.3-2

Plan Projection of Structural Domains

139

Figure 14.4-1

Au Interpretation - Southern Domains (Cross Section E1200)

141

Figure 14.4-2

Au Interpretation - Northern Domains (Cross Section E400)

142

Figure 14.5-1

Gold statistics plots for all domains

145

Figure 14.5-2

Silver statistics plots for all domains

147

Figure 14.6-1

Horizontal Variogram Fan for Gold Domain 1001

151

Figure 14.6-2

Variograms of Samples Along Strike

152

Figure 14.10-1

Inverse Distance (ID3) vs Nearest Neighbor Estimate by Easting

164

Figure 14.10-2

Inverse Distance (ID3) vs Nearest Neighbor Estimate by Northing

164

Figure 14.10-3

Inverse Distance (ID3) vs Nearest Neighbor Estimates by Elevation

164

Figure 14.10-4

Shahuindo Resource Model (Section 500N)

167

Figure 14.10-5

Shahuindo Resource Model - Section 1100N

168

Figure 15.6-1

Graph of Whittle Results

174

Figure 15.6-2

Plan of Whittle Shell 36

176

Figure 16.1-1

Geotechnical Zone Areas

179

Figure 16.3-1

Shahuindo Mine Layout Plan

183

Figure 16.5-1

LOM Pit Design

186

Figure 16.7-1

Site Plan at the end of 2017

188

Figure 16.7-2

Final Phase 2 Site Plan

189

Figure 17.1-1

ROM Process Flow Sheet

196

Figure 17.2-1

Crushing, Stockpile, Screening and Agglomeration Flow Sheet

200

Figure 17.2-2

Overland Conveyor and Stacking System Flow Sheet

201

Figure 18.1-1

Mine Access Road

205

Figure 20.2-1

Annual Distribution of Extracted GEU

217

Figure 20.4-1

Location of Direct Influence Area

224

Figure 24.1-1

Access Road Improvements

241

Figure 24.1-2

Water Storage Pond

242

Figure 24.1-3

Haul Road Construction

242

Figure 24.1-4

New Camp under Construction

243

 

xii


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Figure 24.1-5

Sewage Treatment Plant under Construction

243

Figure 24.1-6

Emulsion Silo

244

Figure 24.1-7

Temporary Workshop under Construction

245

Figure 24.1-8

Fuel Farm under Construction

245

Figure 24.1-9

Leach Pad 1A under Construction

246

Figure 24.1-10

Leach Pad 1A completed with Collection Piping

246

Figure 24.1-11

Leach Pad 1A with Overliner Being Placed

247

Figure 24.1-12

Lime Storage Shed

247

Figure 24.1-13

ADR Plant

248

Figure 24.1-14

PLS Pond

248

Figure 24.1-15

ADR Plant and PLS Pond

248

Figure 24.1-16

Leach Pad 2B Foundation and Sub-Drain Excavation

249

Figure 24.1-17

Leach Pad 2B Foundation Construction

250

Figure 24.1-18

Schematic of Starter Pit, ROM Pad and Haul Roads

251

Figure 24.1-19

Overview of Starter Pit, ROM Pad and Haul Roads

251

Figure 24.1-20

Initial Drill Pattern — November 2015

252

Figure 24.1-21

Ore Place on Pad 1A — December 2015

252

Figure 24.1-22

Pad 1A Irrigation Commissioning — December 2015

252

Figure 24.2-1

Major Exploration Targets around the Shahuindo Project

253

Figure 24.2-2

San Lorenzo and Choloque Drill Hole Location Map

255

Figure 24.2-3

Azules Drill Hole Location Map

260

Figure 24.2-4

Algamarca Sample Location Map (4 and 5 Levels)

261

Figure 24.2-5

Algamarca — Descubridora Vein on Levels 4 and 5

262

 

xiii


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

LIST OF TABLES

 

Table 1.12-1

Metallurgical Test Results

7

Table 1.13-1

Shahuindo Mineral Resources

8

Table 1.13-2

Shahuindo Mineral Reserve

9

Table 1.14-1

Life of Mine Mining Schedule

10

Table 1.15-1

Processing Design Parameters

11

Table 1.15-2

Life of Mine Process Plant Throughput

12

Table 1.18-1

Operating Cost Summary

13

Table 1.18-2

Project Capital

13

Table 1.18-3

Sensitivity Analysis — NPV and IRR after Taxes

14

Table 2.3-1

Qualified Persons — Site Visits and Report Responsibilities

18

Table 2.6-1

List of Abbreviations

20

Table 4.2-1

Mineral Title Summary

23

Table 4.5-1

Summary of Environmental Requirements for Mining Exploration Programs

27

Table 4.6-1

List of Permits and Status

28

Table 4.7-1

Corporate Income Tax

33

Table 5.5-1

Summary of PGA Values for Different Return Periods

39

Table 6.2-1

Summary of Prior Exploration Activities on the Shahuindo Property

43

Table 6.2-2

Summary of Sulliden Exploration Activities

44

Table 6.3-1

Pre-NI 43-101 Mineral Resource Estimates

45

Table 6.3-2

Prior NI 43-101 Mineral Resource Estimate Summary

45

Table 6.3-3

2004 Mineral Resource Estimate

46

Table 6.3-4

2005 Mineral Resource Estimate

46

Table 6.3-5

2009 Mineral Resource Estimate

47

Table 6.3-6

2011 Mineral Resource Estimate

48

Table 6.3-7

2012 Mineral Resource Estimate

49

Table 6.3-8

2012 Pit Optimization Parameters

50

Table 6.3-9

2012 Mineral Reserve Estimate

51

Table 7.1-1

Shahuindo Regional Stratigraphic Column

52

Table 10.1-1

Shahuindo Drilling Summary

81

Table 10.8-1

Core and RC Gold Analyses

87

Table 10.9-1

Post-Resource Drilling

90

Table 11.5-1

Summary of QAQC Program Applicable for 2015 Resource Estimate

100

 

xiv


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 11.5-2

Summary of Analysis of Standards Used in 2015 Drill Program

103

Table 13.1-1

Cyanide and Flotation Testing Programs on Shahuindo

109

Table 13.1-2

Metallurgical Test Work Results

110

Table 13.2-1

Summary of HLC Column Leach Tests

111

Table 13.2-2

Summary of KCA Column Leach Tests

113

Table 13.2-3

Summary of KCA Bottle Roll Leach Tests

114

Table 13.4-1

Rock Type Summary

117

Table 13.4-2

Rio Alto Column Leach Test Results on Surface Samples

118

Table 13.4-3

Rio Alto Column Leach Test Results on Drill Core Composites

119

Table 13.4-4

SGS Column Leach Test Results

120

Table 13.4-5

SGS and Rio Alto Column Leach Test Results by Size and Rock Type

122

Table 13.4-6

Summary of SGS 72-hour Bottle Roll Tests

123

Table 13.4-7

Copper, Iron, Arsenic and Sulfur Levels in the SGS Composites

124

Table 13.4-8

Compacted Permeability Test Results

125

Table 13.5-1

KCA Oxide Ore Parameters - No Permeability or Fines Migration Issues

128

Table 13.5-2

Column Test Results Used in Estimating Field Design Criteria

129

Table 13.5-3

KCA Oxide Ore Recommendation - Crushed to p80 (60mm - 85mm range)

131

Table 13.5-4

Test Results Used to Determine Field Parameters on Coarse Crushed Ore

132

Table 14.2-1

Grid Transformation Applied to Collar Data in Database

135

Table 14.5-1

Descriptive Statistics of Shahuindo Density Values by Rock Type

144

Table 14.5-2

Descriptive Statistics for Gold Oxide Domains

146

Table 14.5-3

Descriptive Statistics for Silver Oxide Domains

148

Table 14.5-4

Hard Domains Used for Minor Element Estimation

149

Table 14.5-5

Description Statistics for Minor Elements

150

Table 14.7-1

Block Model Parameters

152

Table 14.7-2

Block Model Attributes List

153

Table 14.8-1

Search Parameters Used for Gold and Silver Estimation

155

Table 14.9-1

Shahuindo Mineral Resources — Oxide

159

Table 14.9-2

Measured Oxide Resources - Grade Tonnage

159

Table 14.9-3

Indicated Oxide Resources - Grade Tonnage

160

Table 14.9-4

Inferred Oxide Resources - Grade Tonnage

160

Table 14.9-5

Shahuindo Mineral Resources — Sulfide

161

Table 14.9-6

Inferred Sulfide Resources - Grade Tonnage

162

Table 14.10-1

Composites vs Resource Model Grades

163

 

xv


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.10-2

Confidence Levels of Key Criteria

165

Table 15.1-1

Shahuindo Mineral Reserves

170

Table 15.2-1

Cut-Off Grade Assumptions

172

Table 15.3-1

Pit Optimization Parameters for Shahuindo Mineral Reserve

172

Table 15.6-1

Pit Size vs Value

175

Table 16.1-1

Anddes and Associates Geotechnical Parameter Recommendations

177

Table 16.1-2

Shahuindo Geotechnical Parameters

178

Table 16.2-1

Predicted Water Inflows during Mining

180

Table 16.3-1

Waste Dump Volumes

182

Table 16.4-1

Drill and Blast Technical Parameters

184

Table 16.5-1

Comparison of Pit Design to Whittle Shell

185

Table 16.7-1

Mine Production Schedule

190

Table 16.8-1

Primary Mining Equipment Required for Shahuindo

191

Table 16.8-2

Ancillary Equipment Fleet Size

192

Table 16.8-3

Maximum Loader Productivity Estimate

192

Table 17.1-1

Phase 1 Leach Pad Schedule

198

Table 17.3-1

Phase 2 Leach Pad Design Criteria

202

Table 17.4-1

Phase 1 and Phase 2 Process Parameters

203

Table 20.2-1

Sulfur Analysis

215

Table 21.1-1

Estimated Capital Expenditure Summary by Year (US$M)

228

Table 21.1-2

Major Component Capital Expenditures — Life of Mine

228

Table 21.2-1

Operating Cost Summary

229

Table 22.1-1

Life of Mine Production

230

Table 22.3-1

Project Capital

231

Table 22.3-2

Sustaining Capital

231

Table 22.5-1

Gold and Silver Prices

232

Table 22.6-1

Gold and Silver Refining Terms

232

Table 22.7-1

Life of Mine Operating Cost

233

Table 22.11-1

Economic Indicators (US$M)

234

Table 22.12-1

NPV Sensitivity Analysis on Metal Prices

235

Table 22.12-2

NPV Sensitivity Analysis on Operating Cost

235

Table 22.12-3

NPV Sensitivity Analysis on Total Capital

235

Table 22.12-4

Sensitivity Analysis on Metal Recovery

235

Table 22.13-1

LOM Base Case Summary - Assumptions

236

 

xvi


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 22.13-2

Shahuindo Life of Mine Financial Model

237

Table 24.2-1

San Lorenzo — Select Drill Results

254

Table 24.2-2

Choloque — Select Drill Results

255

Table 24.2-3

Southeast Extension — Select Drill Results

256

Table 24.2-4

El Sauce — Select Drill Results

256

Table 24.2-6

La Chilca Baja — Select Drill Results

257

Table 24.2-7

Azules — Sulliden Drill Results

259

Table 24.2-8

Algamarca — Sample Results from the Descubridora Vein

261

 

xvii


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

1.0                               EXECUTIVE SUMMARY

 

1.1                               Introduction

 

Tahoe Resources Inc. (Tahoe or Company), whose common shares are listed for trading on the Toronto Stock Exchange (TSX:THO), New York Stock Exchange (NYSE:TAHO) and Bolsa de Valores: Peru (BVL:THO), has prepared this Technical Report in accordance with Canadian National Instrument 43-101 (NI 43-101) for the Shahuindo mine, Cajabamba, Peru. This technical report summarizes the prefeasibility study of the technical and economic viability of the Shahuindo mine.

 

The following events triggered an updated NI 43-101 report for the Shahuindo mine:

 

·                  On 09 February 2015, Tahoe and Rio Alto Gold (Rio Alto) entered into a definitive agreement to combine their respective businesses and finalized the transaction on 01 April 2015. Through this merger, Tahoe Resources acquired 100% ownership of the mining assets of Rio Alto which included the Shahuindo project.

 

·                  The Mineral Resources and Mineral Reserves estimates have been updated as the result of data obtained from drilling and additional engineering studies conducted in 2014 and 2015. Mining studies incorporate updated cost estimates and financial analyses.

 

·                  Tahoe has revised the mining strategy for the Shahuindo mine.

 

·                  Tahoe has conducted further metallurgical testing on the ore at Shahuindo and has revised the metallurgical assumptions and flowsheet for the project.

 

This report has been completed having an effective date of 01 January 2016. The effective dates of the Mineral Resources estimate and Mineral Reserves estimate are 15 April 2015 and 01 November 2015, respectively. Unless otherwise noted, monetary values are expressed in United States dollars ($) and units are metric.

 

1.2                               Principal Findings

 

Tahoe, through its wholly owned subsidiary, Shahuindo SAC, owns and operates the Shahuindo mine in Peru. The Shahuindo deposit is an intermediate-sulfidation sediment-hosted epithermal gold-silver deposit which the Company has initiated open pit mining and heap leaching of oxide ore. Metal recovery is by carbon-in-column adsorption-desorption-refining (ADR) processes which produces a gold-rich doré for sale to international refineries.

 

Construction of the Shahuindo mine commenced in mid-2014, with commissioning of the mine and processing facilities in the fourth quarter of 2015. The Company anticipates achieving commercial production at Shahuindo in the second quarter of 2016.

 

1


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Production at Shahuindo is scheduled in two phases: Phase 1 processes coarse-grain run-of-mine (ROM, i.e., no crushing required) material at an initial rate of 10,000 tonnes of ore per day (tpd) in 2016; a second adsorption column circuit will be installed in mid-2016 to increase the plant processing capacity to accommodate increased mining rates. Phase 2 begins in 2018 and continues through the end of the current mine life with the plant capacity increased to 36,000 tpd to process mixed coarse- and fine-grain ore that requires crushing and agglomeration prior to leaching. The phased approach enables gold production as soon as possible with minimal capital expenditure, thus generating cash flow early in the project.

 

Throughout this report, references made to Phase 1 and Phase 2 production rates refer to process plant capacity rather than mining rates, though plant capacity and mining rates (ore placed on leach pads) do coincide later in the mine life. An ore stockpile will be utilized to store mine production in excess of plant capacity, with stockpiled ore incrementally added to the leach pads over the life of mine.

 

The prefeasibility study supports the declaration of Proven and Probable Mineral Reserves. The study provides economic parameters for the Shahuindo mine from 01 January 2016 forward.

 

Highlights of the study include:

 

·                  Measured and Indicated Mineral Resources of 143.1 million tonnes and 2.28 million oxide gold ounces at an average gold grade of 0.50 gram per tonne (g/t).

 

·                  Proven and Probable Mineral Reserves of 111.9 million tonnes at an average gold grade of 0.53 g/t, containing 1.91 million ounces of gold.

 

·                  Average annual gold production (i.e., gold in doré) of 78,000 ounces in the first two years of production (Phase 1) and 169,000 ounces in years three through ten (Phase 2). Total gold produced in doré over the LOM is estimated to be 1.504 million ounces.

 

·                  As of 01 January 2016, capital costs are estimated at $179.6 million for project (construction) capital and $140.7 million for sustaining capital over the LOM.

 

·                  After tax net present value at a 5% discount rate (NPV5) of $318.9 million and an internal rate of return (IRR) of 40.6% with a payback period of 4.1 years at the base case metal prices.

 

·                  Exploration conducted by previous owners and by Tahoe demonstrates considerable potential to add additional gold ounces to the production profile at Shahuindo and has identified multiple exploration prospects in the district.

 

Mineral Resources and Mineral Resources are reported using metal prices of $1,200/oz Au and $15/oz Ag. Mineral Resources are reported within a $1,400/oz Au pit shell at a gold-equivalent (AuEq) cut-off grade of 0.14 g/t. The financial analysis uses escalating metal prices over the LOM beginning with $1,100/oz Au in 2016 and increasing in $100/oz increments annually to $1,400/oz Au in 2019 where it

 

2


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

remains constant through the end of the mine life. Likewise, silver prices used are $14.75/oz in 2016, $17.25/oz in 2017, $20.00/oz in 2018, and $23.50/oz in 2019 and forward to the end of the mine life. Silver has a negligible contribution to the mine economics.

 

1.3          Property Description and Location

 

The Shahuindo mine is located in the district of Cachachi, province of Cajabamba, department and region of Cajamarca, Peru. It is situated approximately 59 kilometers southeast of the town of Cajamarca and 14 kilometers west of the town of Cajabamba. The project can be accessed from Cajabamba via a combination of asphalt, gravel and dirt roads. Access can be gained all year round.

 

The local climate consists of two major seasons; a cold and dry “dry season” between the months of May to September, and a humid “wet season” between the months of October to April. The average annual precipitation is 999.7mm a year, with an average temperature of 15.7ºC.

 

1.4          Mineral Tenure

 

The Shahuindo property comprises one mineral concession, Acumulacion Shahuindo, which includes 26 mineral titles with an approximate area of 7,339 hectares. The concession is 100% controlled by Tahoe’s wholly owned subsidiary, Shahuindo SAC. The mining rights and surface rights are registered under the name of Shahuindo SAC in the government title registry office. All claims are in good standing as of the effective date of this report.

 

Shahuindo SAC has acquired 381 surface rights within the Shahuindo project area to date, covering a total area of about 2,559 hectares. Some of these surface rights were used to relocate local land owners into new areas.

 

1.5          Permits

 

The Shahuindo mine operates under an initial Environmental Impact Statement (EIA, Estudio de Impacto Ambiental) approved in 2013. The EIA was prepared according to the Ministry of Energy and Mines (MEM) requirements and complies with Peruvian regulations.

 

As of the effective date of this report, most required permits have been obtained, with the remaining permits being in the final stages of approval. The following list describes the status of the required permits for operations as of 01 January 2016:

 

·      Certificate for the inexistence of Archaeological Remains — Approval granted.

 

·      Environmental Impact Assessment (EIA) - Approval granted. Expansion EIA in process.

 

·      Mine Closure Plan — Approval granted

 

3


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·      Beneficiation Concession — Approval granted.

 

·      Water usage permit — Approval granted.

 

·      Mining Plan — Final stage of evaluation with Ministry of Energy and Mines.

 

·      Operations Permits — In process; approvals expected in January 2016.

 

All permits and any new permits will be renewed or obtained as required. It is expected that all remaining permits required for full operations will be obtained in January 2016.

 

1.6          Environment

 

The operating plan will adhere to Tahoe’s mandate that the Shahuindo Project meet or exceed the standards of sustainability and environmental management based on North American practice and regulation. The Company has implemented a comprehensive environmental management plan to regularly and systematically monitor air quality, surface water and groundwater quality, stream sediment geochemistry, blast vibration, noise levels, waste rock geochemistry (ARD monitoring), waste disposal practices, reagent handling and storage, and reclamation and reforestation progress.

 

1.7          History

 

Modern exploration activities have been conducted on the Shahuindo property since 1945 by Minera Algamarca SA (1945-1989), Alta Tecnología e Inversión Minera y Metalúrgica S.A. (Atimmsa, 1990), Asarco LLC (Asarco, 1994-1996), Southern Peru Copper Corporation (Southern Peru, 1997-1998) and Sulliden Gold Corporation (Sulliden, 2002-2012). Rio Alto initiated infill drilling of the resource upon their acquisition of Sulliden in 2014 and Tahoe has continued infill and exploration drilling in the district.

 

1.8          Geology and Mineralization

 

The Shahuindo deposit is located on the eastern flank of the Andean Western Cordillera in northern Peru, within a regional fold and thrust belt of predominantly sedimentary rocks. The region is particularly well-endowed with mineral occurrences varying from low-to-high sulfidation systems and from porphyry through polymetallic to epithermal deposits.

 

Mineralization at Shahuindo is best described as an intermediate-sulfidation epithermal system, though high-sulfidation mineralization occurs at depth and in the core of hydrothermal breccias. Oxidation of mineralization extends to a depth of 150m below surface. In the weathered oxide facies, gold and silver are associated with the presence of jarosite and hematite. In the underlying fresh sulfide facies, gold is typically extremely fine grained with the related mineral species not yet identified.

 

The principal zone of mineralization in the Shahuindo district occurs in a belt between two large-amplitude regional-scale folds, the Algamarca anticline and the San Jose Anticline. The Algamarca

 

4


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

anticline is upright and symmetrical with amplitude of at least 400m, whereas the San Jose fold is an asymmetric, overturned, northeast-vergent fold with a shallowly dipping axial surface and amplitude of at least 300m. Important structural elements include fold limbs and fold axial surfaces, fold-related fractures, faults and related extension fractures, breccia dikes and irregular bodies, and igneous intrusive contacts.

 

Both structure and lithology control the location, shape, and orientation of the mineralization. The mineralization is hosted within the siliciclastic sandstone-dominant Farrat Formation and the underlying sedimentary Carhuaz formation. These sedimentary rocks have been intruded by at least three felsic stocks which tend to be located along faults and cores of anticlinal structures. In addition, the metallurgical recovery of gold is affected by lithology with the identification of five primary geometallurgical domains based on the relationship between lithology and grain size and gold recovery. Modelling the distribution and occurrence of lithologic units / geometallurgical domains is critical to mine planning.

 

1.9          Drilling

 

Mineral Resources were estimated using data from 1,039 diamond core and reverse circulation (RC) drill holes, totaling 164,015 meters, from drilling conducted by Atimmsa, Asarco, Southern Peru, Sulliden and Rio Alto. The cut-off date for drill data inclusion in the mineral resource model was 15 April 2015.

 

Prior to the acquisition by Tahoe in April 2015, Rio Alto drilled predominantly RC holes in the oxide portion of the deposit to bring the drill density to a nominal 25m x 25m spacing. Tahoe has continued drilling diamond core and RC for infill, step-out, geotechnical, hydrology, and condemnation purposes.

 

1.10        Sample Preparation and Analysis

 

Tahoe has limited information about sample preparation and analyses for the drill programs prior to the major drill programs by Sulliden beginning in 2003. The drilling prior to Sulliden’s work is considered to be a minimal risk to the estimate of Mineral Resources, as this dataset accounts for only 15% of the data used in the estimate and many of the holes drilled prior to Sulliden have been twinned or offset with new drill holes.

 

From 2003 to 2012, Sulliden’s sampling and sample dispatch for the Shahuindo project were carried out under the supervision of Sulliden staff. Samples were sent to ALS Minerals (ALS, formerly known as ALS Chemex) in Lima for sample preparation and analysis. Samples were prepared and analyzed using industry-standard practices, including the use of quality assurance and quality control (QA/QC) duplicates, blanks, and assay standards. The ALS laboratory in Lima is ISO 9001:2008 and ISO 17025:2005 certified.

 

5


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Samples from Rio Alto’s 2014-2015 drill programs were analyzed by CERTIMIN (Lima). Gold was assayed with a 50-gram fire assay using an atomic adsorption finish. Fire assays were repeated using with a gravimetric finish for samples whose initial fire assay results were greater than 10 g/t Au. Rio Alto employed a QA/QC program of field duplicates, blanks and assay standards. The CERTIMIN laboratory is ISO 9001 certified for geochemical, metallurgical and environmental sample analyses. Tahoe continues to use the CERTIMIN laboratory in Lima as its primary assay lab for its continued drilling at the Shahuindo project.

 

Drill core and RC sampling procedures, sample analyses, QAQC procedures and sample security employed at Shahuindo are of sufficient quality for use in the resource estimate.

 

1.11        Data Verification

 

The drill hole database has been the subject of three major audits between 2003 and 2012 by independent consulting firms and one audit by Tahoe in 2015. The results of these audits, including the 2015 Tahoe audit, found the database integrity and QAQC results sufficient to ensure the dataset used is reliable for resource estimation purposes. Some discrepancies with silver standards used by Rio Alto and Tahoe in 2015 were identified, though this is not considered material due to the minimal contribution of silver to the value of the project.

 

The result of the verification programs support the estimation of the Shahuindo Mineral Resources and the assignment of Measured, Indicated and Inferred resource classifications.

 

1.12        Mineral Processing and Metallurgical Testing

 

The mineral processing and metallurgical testing that included cyanidation and flotation testing programs have been conducted on composite samples from the Shahuindo project by various companies starting in 1996. These companies include Asarco, Compania Minera Algamarca, Sulliden, Rio Alto and Tahoe, with test work conducted at Dawson Metallurgical Laboratories, Kappes, Cassiday & Associates (KCA), Heap Leach Consultants (HLC), SGS and Tahoe’s La Arena laboratory.

 

Results from the cyanidation tests conducted by KCA from 2009 to 2012 and in 2014, and by Tahoe (Rio Alto) in 2014 and 2015 on core drill hole and surface composites were used in the development of the recovery and leach design parameters for use in the prefeasibility study. The results of the testing program indicate excellent gold recoveries at both run-of-mine (ROM) and coarse crush sizes with low to moderate reagent requirements, implying amenability to heap leaching. Silver recoveries were generally low.

 

Compacted permeability tests on -25mm crushed samples were conducted, both with and without cement. The results are variable with one-third of the tests conducted in 2015 failing. The results from

 

6


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

KCA’s compacted permeability tests on -32mm composites conducted in 2012 indicated that mixing of the more weathered samples with competent material would be required to maintain permeability at 6 kg of cement per tonne of ore. Two of the three KCA tests passed the compacted permeability tests at a simulated heap height of approximately 110 meters.

 

Table 1.12-1 includes the field gold and silver recoveries, reagent consumptions, and leach times on oxide material, based on the available test work results from both ROM and single-stage crushing tests.

 

Table 1.12-1        Metallurgical Test Results

 

Parameter

 

 

ROM

 

 

Crush

% Au Recovery

 

 

73%

 

 

80%

% Ag Recovery

 

 

7%

 

 

12%

NaCN Consumption

 

 

0.2 kg/t

 

 

0.3 kg/t

Cement

 

 

0

 

 

6 kg/t*

Lime

 

 

2 kg/t

 

 

1 kg/t

Leach Time

 

 

80 days

 

 

70 days

Size, p80

 

 

~ 150mm

 

 

60 to 85mm

 


*Cement addition based on screened minus 75mm material

 

Maintaining heap permeability and minimizing channeling at higher heap heights constitutes a risk to the project, as additional agglomeration and compacted permeability testing is required. Tahoe will conduct further test work on the agglomeration circuit before operations in 2018 (Phase 2). This will include further work on maximizing recovery and determining the maximum leach pad height.

 

1.13        Mineral Resource and Mineral Reserve Estimates

 

The Mineral Resource estimate has been classified as Measured, Indicated and Inferred based on the confidence of the input data, geological interpretation and grade estimation parameters. The Mineral Reserve estimate has been classified as Proven and Probable, applying applicable mining, metallurgical, economic, permitting, and other relevant factors to the Measured and Indicated Mineral Resources. The Mineral Resource and Mineral Reserve estimates have been prepared and reported in accordance with Canadian National Instrument 43-101 (NI 43-101), Standards of Disclosure for Mineral Projects, and classifications adopted by the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Council.

 

Tahoe is not aware of any specific metallurgical, infrastructural, environmental, legal, title, political, taxation, socio-economic or marketing issues that would impact the Mineral Reserve Estimate as presented.

 

7


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

1.13.1     Mineral Resources

 

The Mineral Resource estimate for the Shahuindo deposit contains Measured and Indicated Mineral Resources (oxide) of 143.1 million tonnes at average grades of 0.50 g/t Au and 6.7 g/t Ag, containing 2.28 million ounces of gold and 30.7 million ounces of silver. Inferred Mineral Resources (oxide) total 2.6 million tonnes at average grades of 0.42 g/t Au and 7.4 g/t Ag; containing 36,000 ounces of gold and 626,000 ounces of silver. Sulfide resources total 87.7 million tonnes at average grades of 0.71 g/t Au and 21.1 g/t Au; containing 2.0 million ounces of gold and 59.4 million ounces of silver. All sulfide resources are classified as Inferred Mineral Resources. The effective date of the Shahuindo Mineral Resource estimate is 15 April 2015.

 

Table 1.13-1 is a summary of the Shahuindo Mineral Resources, at cut-off grades for oxide material of 0.14 g/t AuEq and sulfide material of 0.50 g/t AuEq.

 

Table 1.13-1        Shahuindo Mineral Resources

 

Material

 

 

Resource

 

 

Tonnes

 

 

Au

 

 

Ag

 

 

Au Ounces

 

 

Ag Ounces

 

Type

 

 

Classification

 

 

(M)

 

 

(g/t)

 

 

(g/t)

 

 

(koz)

 

 

(koz)

 

Oxide

 

 

Measured

 

 

96.5

 

 

0.50

 

 

6.7

 

 

1,546

 

 

20,901

 

 

 

Indicated

 

 

46.6

 

 

0.49

 

 

6.5

 

 

736

 

 

9,778

 

 

 

Measured and Indicated

 

 

143.1

 

 

0.50

 

 

6.7

 

 

2,282

 

 

30,679

 

 

 

Inferred

 

 

2.6

 

 

0.42

 

 

7.4

 

 

36

 

 

626

 

Sulfide

 

 

Inferred

 

 

87.7

 

 

0.71

 

 

21.1

 

 

2,002

 

 

59,441

 

 

Numbers may not add due to rounding

 

Oxide resources are reported within a $1,400/oz Au optimized open pit shell. Gold-equivalent grades were calculated in the Shahuindo resource block model using the individual gold and silver grades for each block and metal prices of $1,200/oz Au and $15/oz Ag using the formula:

 

AuEq g/t = Au g/t + (Ag g/t x 15/1200)

 

The sulfide Mineral Resources at Shahuindo are classified entirely as Inferred due to limited metallurgical characterization and wider drill spacing than in the oxide portion of the deposit. There have been no economic or mining studies of the sulfide portion of the Shahuindo deposit completed to date; the Inferred sulfide resource is reported at a 0.5 AuEq g/t cut-off using the same metal prices as used for calculating the oxide gold-equivalent values.

 

The drill data used for the estimate of Mineral Resources includes data from all drilling completed through April 2015. The drill hole information includes collar location, downhole survey, assay, lithology and oxidation data.

 

8


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Lithological, oxidation and structural models were created to model the distribution of mineralization to the pertinent geologic domains. Gold mineralization domains were created using a 0.1 g/t Au cut-off; these domains were used as hard boundaries to constrain the grade estimate. Silver values have been estimated inside the gold domains. A suite of other elements were also modeled and estimated into the block model, including sulfur, copper, lead, zinc, arsenic, molybdenum, calcium, total iron, sodium and manganese. The economic contribution of these elements is not material to the project.

 

1.13.2     Mineral Reserve Estimate

 

The Shahuindo Proven and Probable Mineral Reserves total 111.9 million tonnes of oxide material at average grades of 0.53 g/t Au and 6.8 g/t silver; containing 1.91 million ounces of gold and 24.5 million ounces of silver at a cut-off grade of 0.18 g/t Au. Mineral Reserves are inclusive of Mineral Resources. There are no sulfide Mineral Reserves reported. The effective date of the Shahuindo Mineral Reserve is 01 November 2015.

 

The Shahuindo Mineral Reserve estimate is summarized in Table 1.13-2.

 

Table 1.13-2        Shahuindo Mineral Reserve

 

 

 

 

Tonnes

 

 

Au Grade

 

 

Ag Grade

 

 

Au Ounces

 

 

Ag Ounces

 

Reserve Classification

 

 

(M)

 

 

(g/t)

 

 

(g/t)

 

 

(000s)

 

 

(000s)

 

Proven

 

 

82.7

 

 

0.54

 

 

6.92

 

 

1,424

 

 

18,400

 

Probable

 

 

29.2

 

 

0.51

 

 

6.54

 

 

483

 

 

6,142

 

Proven & Probable

 

 

111.9

 

 

0.53

 

 

6.82

 

 

1,906

 

 

24,541

 

 

Numbers may not add due to rounding

 

Metal prices used for reporting Mineral Reserves are $1,200 per ounce gold and $15.00 per ounce silver. The Mineral Reserve estimate does not include process recovery factors or plant losses.

 

The cut-off grade for the Mineral Reserve was calculated from operating costs experienced at Tahoe’s La Arena mine, the estimated metallurgical performance sourced from test work and engineering first principles. Proven and Probable reserves include five percent dilution at zero grade and mining losses of two percent. Resources within the mine plan classified as Inferred were considered to have no economic value and have been classified as waste in the mining schedule.

 

1.14        Mining Method and Mine Production Schedule

 

The Shahuindo mine is an open pit heap leach operation. The mining method used is a conventional drill/blast, shovel and dump truck operation. The mining will be executed under an alliance style contract similar to the mining operation at the Company’s La Arena mine.

 

9


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The mining schedule at Shahuindo consists of two phases. Phase 1 entails mining higher grade starter pits providing ROM material to the Phase 1 leach pads in 2016 and 2017; the average mining rates in 2016 and 2017 are approximately 15,800 tonnes of ore per day and 15,300 tonnes of ore per day, respectively. Phase 2, beginning in 2018, includes the addition of a crushing and agglomeration facility, increased plant capacity and an additional leach pad. The mining rate in Phase 2 increases production to meet the Phase 2 plant capacity of 36,000 tonnes of ore per day, which will require an upgraded mining fleet.

 

The LOM production schedule as of 01 January 2016 forecasts the Shahuindo mine to produce and deliver to the processing facilities a total of 110.9 million tonnes of ore at an average gold grade of 0.53 g/t, and average silver grade of 6.86 g/t. The LOM plan is summarized in Table 1.14-1.

 

Table 1.14-1        Life of Mine Mining Schedule

 

 

 

 

Unit

 

 

2016

 

 

2017

 

 

2018

 

 

2019

 

 

2020

 

 

2021

 

Ore Tonnes

 

 

k tonnes

 

 

5,756

 

 

5,602

 

 

10,289

 

 

13,412

 

 

13,039

 

 

12,352

 

Au Grade

 

 

g/t

 

 

0.68

 

 

0.54

 

 

0.64

 

 

0.48

 

 

0.48

 

 

0.51

 

Ag Grade

 

 

g/t

 

 

5.95

 

 

5.73

 

 

7.24

 

 

6.45

 

 

7.05

 

 

6.47

 

Waste Tonnes

 

 

k tonnes

 

 

4,954

 

 

4,113

 

 

21,835

 

 

18,895

 

 

19,246

 

 

19,893

 

Strip Ratio

 

 

waste:ore

 

 

0.86

 

 

0.73

 

 

2.12

 

 

1.41

 

 

1.48

 

 

1.61

 

Total Tonnes

 

 

k tonnes

 

 

10,710

 

 

9,715

 

 

32,124

 

 

32,306

 

 

32,285

 

 

32,245

 

Au Mined

 

 

k oz

 

 

126

 

 

97

 

 

212

 

 

206

 

 

200

 

 

201

 

Ag Mined

 

 

k oz

 

 

905

 

 

1,090

 

 

2,524

 

 

2,741

 

 

2,954

 

 

2,568

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Unit

 

 

2022

 

 

2023

 

 

2024

 

 

2025

 

 

Total

 

 

 

 

Ore Tonnes

 

 

k tonnes

 

 

16,066

 

 

14,405

 

 

12,732

 

 

7,236

 

 

110,890

 

 

 

 

Au Grade

 

 

g/t

 

 

0.50

 

 

0.59

 

 

0.52

 

 

0.49

 

 

0.53

 

 

 

 

Ag Grade

 

 

g/t

 

 

7.79

 

 

7.16

 

 

6.36

 

 

7.30

 

 

6.86

 

 

 

 

Waste Tonnes

 

 

k tonnes

 

 

16,395

 

 

15,922

 

 

17,497

 

 

11,106

 

 

149,855

 

 

 

 

Strip Ratio

 

 

waste:ore

 

 

1.02

 

 

1.11

 

 

1.37

 

 

1.53

 

 

1.35

 

 

 

 

Total Tonnes

 

 

k tonnes

 

 

32,461

 

 

30,327

 

 

30,230

 

 

18,342

 

 

260,485

 

 

 

 

Au Mined

 

 

k oz

 

 

258

 

 

273

 

 

215

 

 

113

 

 

1,900

 

 

 

 

Ag Mined

 

 

k oz

 

 

3,599

 

 

3,143

 

 

2,663

 

 

2,246

 

 

24,470

 

 

 

 

 

10


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

1.15        Processing

 

Gold from the Shahuindo mine will be extracted from the ore via heap leach and then processed by carbon-in-column, adsorption-desorption-refining (ADR) operations. The civil and geotechnical design of the leach pads were engineered by Anddes Asociados SAC; the process plant was engineered by Heap Leaching Consulting SAC, both of Lima, Peru.

 

The start-up production plan for the processing of Shahuindo ore is 10,000 tpd (Phase 1) with processing capacity expanded early in the second half of 2016. Average processing rates in 2016 and 2017 are about 12,200 tonnes of ore per day and 16,500 tonnes of ore per day, respectively. The process plant facilities will be further expanded in Phase 2 to 36,000 tonnes per day. The Phase 2 expansion to be implemented in 2018 will include a crushing and agglomeration circuit that includes a single-stage crusher and screen, cement and lime addition to the fines, agglomeration in belt conveyors and stacking system to place ore onto the leach pad.

 

The processing parameters are shown in Table 1.15-1.

 

Table 1.15-1        Processing Design Parameters

 

Parameter

 

 

Phase 1

 

 

Phase 2

Leach Pad Area

 

 

41 Ha

 

 

153

Dry Tonnes of Ore/Day

 

 

10,000

 

 

36,000

Head Grade

 

 

0.64 g/t Au

 

 

0.52 g/t Au

Average Flow Rates

 

 

400 m3/H

 

 

1600-1800 m3/H

Leach Time

 

 

80-90 days

 

 

75-85 days

Lift Height

 

 

8 meters

 

 

8-16 meters

Material Size

 

 

100% minus 300mm

 

 

100% minus 75mm

NaCN Consumption

 

 

0.2 kg/tonne of ore

 

 

0.3 kg/tonne of ore

Lime Consumption

 

 

no addition

 

 

1.0 kg/tonne of ore

Cement Consumption

 

 

n/a

 

 

4-6 kg/tonne

Average Au Recovery

 

 

73%

 

 

80%

 

The Shahuindo mine is scheduled to produce a total of 1.504 million ounces of gold and 2.8 million ounces of silver in doré over a 10 year period. Table 1.15-2 summarizes the life of mine process plant throughput schedule and ounce production.

 

11


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 1.15-2        Life of Mine Process Plant Throughput

 

 

Unit

2016

2017

2018

2019

2020

2021

Heap Leach Process Tonnes

k tonnes

4,446

6,022

11,179

13,000

13,039

12,352

Process Au Head Grade

g/t

0.79

0.52

0.60

0.48

0.48

0.51

Process Ag Head Grade

g/t

6.59

5.63

6.84

6.56

7.05

6.47

Au ounces recovered

k oz

82.6

74.1

172.9

161.8

160.0

160.8

Ag ounces recovered

k oz

65.9

76.3

294.9

328.9

354.5

308.2

 

 

Unit

2022

2023

2024

2025

Total

Heap Leach Process Tonnes

k tonnes

13,140

13,140

13,140

11,431

110,890

Process Au Head Grade

g/t

0.55

0.62

0.52

0.41

0.53

Process Ag Head Grade

g/t

8.52

7.44

6.30

6.28

6.86

Au ounces recovered

k oz

186.5

209.5

174.5

120.8

1,503.7

Ag ounces recovered

k oz

431.9

377.2

319.6

276.9

2,834.2

 

1.16        Infrastructure

 

The Shahuindo mine is approximately 25 kilometers by road from the town of Cajabamba and 130 kilometers by road from the town of Cajamarca. Access from Cajamarca is via asphalt-paved highway and gravel and dirt roads.

 

During Phase 1 operations, power at the site will be provided by on-site diesel generation capable of sustaining 1.2 MW of power. In 2018, power will be provided via the National Commercial Grid. The long term power requirement for the Shahuindo mine is 7.4MW.

 

All process and domestic water for the operation will be supplied from an 18,000 cubic meter rainwater run-off collection pond, a water well located 300m west of the Shahuindo open pit, and from pit dewatering which will be pumped at the beginning of the second year of operation. Hydrogeological studies indicate sufficient water will be available to supply process and potable water requirements for the life of the mine.

 

At the effective date of this report, buildings required for the initial start-up are in place and are tailored for Phase 1 production. Some of the infrastructure from Phase 1 will be upgraded before Phase 2 production commences.

 

1.17        Mine Closure

 

The entire facility was designed with closure in mind to the greatest extent practicable. The facilities are designed and operated to minimize the footprints and areas of disturbance and utilize the most advanced planning and reclamation techniques available. The disturbance footprint of Shahuindo mine site is

 

12


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

approximately 1,348 Ha. Reclamation will commence as soon as practical during operations by placing salvaged topsoil on outer slopes and encouraging vegetation.

 

1.18        Capital and Operating Costs

 

1.18.1     Operating Costs

 

The operating costs for the Shahuindo mine were calculated for each year during the life of mine using the forecasted annual production tonnages. The mining, processing and site general and administration (G&A) costs were derived from first principals, or based on operating costs experienced at Tahoe’s La Arena mine which is comparable to the Shahuindo mine.

 

Table 1.18-1 includes the summary of the anticipated life-of-mine costs.

 

Table 1.18-1        Operating Cost Summary

 

Operating Cost

 

Value

Mining Cost ($/tonne mined)

 

$

1.91

 

Mining Cost ($/ore tonne mined)

 

$

4.50

 

Process Plant Operating Cost ($/tonne processed)

 

$

2.55

 

General Administration ($/tonne processed)

 

$

2.23

 

 


*includes $1.42/tonne ore for crushing and agglomeration beginning in 2018

 

1.18.2     Capital Costs

 

The capital expenditure requirement for the Shahuindo mine is $320.3 million dollars beginning on 01 January 2016. This includes construction capital of $179.6 million and $140.7 million in sustaining capital. Capital expenditures incurred prior to 01 January 2016 are considered as ‘sunk’ costs.

 

The project capital is summarized in Table 1.18-2. The total project capital carried in the financial model for new construction is expended over a three year period.

 

Table 1.18-2        Project Capital

 

Project Capital

 

$ (millions)

Mining

 

$

27.5

 

Process Plant

 

$

105.6

 

Other

 

$

46.6

 

Total

 

$

179.6

 

 

13


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

1.18.3     Financial Analysis

 

The Shahuindo mine economic analysis indicates that the project has an Internal Rate of Return (IRR) of 40.6% with a payback period of 4.1 years after taxes and an after-tax Net Present Value using a five percent discount rate (NPV5) of $318.9 M after taxes.

 

Sensitivity analyses were conducted using changes in metal prices, operating cost, initial capital, and recovery; the results of which are summarized in Table 1.18-3. Changes to metal prices have the greatest impact on the NPV and IRR of the project.

 

Table 1.18-3        Sensitivity Analysis — NPV and IRR after Taxes

 

Variable

 

Change

NPV @
0%

NPV @
5%

NPV @
10%

IRR%

Payback

Change in

Metal Prices

 

+20%

 

$

723,045

 

$

508,619

 

$

362,690

 

67.7

%

3.3

 

 

+10%

 

$

597,309

 

$

413,960

 

$

289,289

 

53.1

%

3.6

 

 

Base Case

 

$

471,200

 

$

318,863

 

$

215,413

 

40.6

%

4.1

 

 

-10%

 

$

342,701

 

$

221,333

 

$

139,143

 

29.0

%

4.8

 

 

-20%

 

$

202,022

 

$

113,741

 

$

54,457

 

17.1

%

6.1

 

Change in

Operating

Cost

 

+20%

 

$

348,725

 

$

225,158

 

$

141,508

 

29.0

%

4.9

 

 

+10%

 

$

411,022

 

$

273,026

 

$

179,417

 

34.8

%

4.4

 

 

Base Case

 

$

471,200

 

$

318,863

 

$

215,413

 

40.6

%

4.1

 

 

-10%

 

$

530,361

 

$

363,820

 

$

250,632

 

46.7

%

3.8

 

 

-20%

 

$

588,728

 

$

407,955

 

$

285,031

 

53.1

%

3.6

 

Change in

Total

Capital

 

+20%

 

$

409,200

 

$

263,661

 

$

165,625

 

29.1

%

4.8

 

 

+10%

 

$

440,142

 

$

291,213

 

$

190,477

 

34.2

%

4.5

 

 

Base Case

 

$

471,200

 

$

318,863

 

$

215,413

 

40.6

%

4.1

 

 

-10%

 

$

502,354

 

$

346,596

 

$

240,419

 

49.0

%

3.7

 

 

-20%

 

$

533,592

 

$

374,233

 

$

265,224

 

60.2

%

3.4

 

Change in

Metal

Recovery

 

2%

 

$

508,599

 

$

347,156

 

$

237,466

 

44.2

%

3.9

 

 

1%

 

$

489,905

 

$

333,014

 

$

226,443

 

42.4

%

4.0

 

 

Base Case

 

$

471,200

 

$

318,863

 

$

215,413

 

40.6

%

4.1

 

 

-1%

 

$

452,456

 

$

304,682

 

$

204,358

 

38.9

%

4.2

 

 

-2%

 

$

433,662

 

$

290,459

 

$

193,265

 

37.2

%

4.3

 

 

14


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

1.19        Exploration Status

 

Numerous oxide and sulfide exploration targets that have considerable potential to increase the resource and reserve base at Shahuindo have been identified through surface mapping, rock-chip and soil sampling surveys, geophysical surveys and drilling conducted by previous owners of the Shahuindo property and by drilling conducted by Tahoe subsequent to its merger with Rio Alto in April 2015.

 

Drilling around the periphery of the currently-designed pit limits in the second half of 2015 successfully identified mineralization outside of the northeast and southwest margins of the Phase 2 pit shell that will be incorporated into future mine plans. Likewise, condemnation drilling in the planned waste dump area identified shallow mineralization that represents an extension to the known resource; a portion of which will be mined and delivered to the leach pad or stockpile prior to construction of the waste dump foundation.

 

Other drilling in 2015 identified metal grades and mineralogy similar to Shahuindo at the San Lorenzo, Choloque and La Chilca prospects proximal to the Shahuindo pit. These targets represent near-term opportunities to increase the resource base as Shahuindo.

 

1.20        Conclusions and Recommendations

 

The results of this study demonstrate that:

 

1.              The Shahuindo mine is economically viable from 01 January 2016 through to the end of the estimated mine life, supporting the declaration of Proven and Probable Mineral Reserves.

 

2.              The Shahuindo mining strategy consists of two phases. The first phase will process ROM ore at an initial rate of 10,000 tonnes of ore per day, ramping up to an average of 12,200 tonnes of ore per day in 2016 and 16,500 tonnes of ore per day in 2017; the second phase will include a crushing and agglomeration circuit that will increase production to 36,000 tonnes per day. The phased approach enables gold production as soon as possible with minimal capital expenditure, generating cash flow early in the project.

 

3.              The results of laboratory testing program indicate excellent gold recoveries at both ROM and moderate crush sizes with low to moderate reagent requirements, implying amenability to heap leaching. Silver recoveries are generally low.

 

4.              The Shahuindo district holds excellent opportunities for further discovery and definition of additional oxide and sulfide mineralized bodies that have potential to increase the resource base at Shahuindo.

 

The authors of this report recommend the Company to:

 

1.              Initiate field and laboratory studies investigate the potential to reduce capital and operating costs related to the Phase 2 crushing and agglomeration scheme. Conduct pilot scale heap leach tests

 

15


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

on the current ROM leach pad to investigate field-scale performance on composites with varying degrees of coarse-to-fines ratios. The metallurgical facilities at the Company’s La Arena mine should be utilized to conduct further permeability and compaction tests.

 

2.              Investigate the ability of the siltstones and breccia with high fines content to percolate in the ROM leach pad.

 

3.     Conduct additional metallurgical testing on drill samples.

 

4.              Improve the geometallurgical model. Further refinement of the geologic model at Shahuindo will greatly aid in mine planning and scheduling, and increase confidence in the material types scheduled for delivery to the leach pad to optimize material blending schemes.

 

5.              Aggressively explore the Shahuindo district and accelerate district exploration with the goal of discovering additional resources amenable to the Shahuindo processing facility.

 

6.              Evaluate the mineralized zones on the periphery of the Shahuindo deposit to expand the resource and incorporate these extensions into a new pit design.

 

7.              Improve the QA/QC procedures by including a wider-range of certified assay standards, particularly assay standards at or near the operational gold cut-off grade. Create assay blanks from coarse RC drilling rejects. Utilize a second commercial laboratory or the La Arena laboratory for check assays of exploration samples.

 

8.     Update and refine the resource estimate as additional drill hole information becomes available.

 

9.     Evaluate the economic potential of the sulfide mineralization below the Shahuindo pit.

 

After reaching commercial production, the authors recommend the Company systematically evaluate mining, processing and other surface operations to optimize processes and procedures and reduce capital and operating costs. Examples include the following trade-off studies to evaluate:

 

a)             the potential to reduce or eliminate the requirement for the crushing and or agglomeration circuit, and the impact to metal recoveries;

 

b)    the economic benefit of implementing a secondary crushing circuit to increase recovery;

 

c)              the potential to increase the overall slope angle of the pit to increase the NPV of the project through further geotechnical and hydrogeological analyses; and

 

d)             the potential to reduce operating costs by evaluating the suitability by backfilling mined waste rock into the pit.

 

16


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

2.0          INTRODUCTION

 

2.1          Purpose and Basis of Report

 

Tahoe Resources Inc. (Tahoe or Company), whose common shares are listed for trading on the Toronto Stock Exchange (TSX:THO), New York Stock Exchange (NYSE:TAHO) and Bolsa de Valores: Peru (BVL:THO), has prepared an updated Technical Report (the Report) for the Company’s Shahuindo mine in Peru. This report presents the results of a prefeasibility study of the technical and economic viability of the Shahuindo mine.

 

The following events have triggered an updated NI 43-101 Technical Report for the Shahuindo mine:

 

·                  On 09 February 2015, Tahoe and Rio Alto Gold (Rio Alto) entered into a definitive agreement to combine their respective businesses and finalized the transaction on 01 April 2015. Through this merger, Tahoe Resources acquired 100% ownership of the mining assets of Rio Alto which included the Shahuindo project.

 

·                  The Mineral Resources and Mineral Reserves estimates have been updated as the result of data obtained from drilling and additional engineering studies conducted in 2014 and 2015. Mining studies incorporate updated cost estimates and financial analyses.

 

·      Tahoe has revised the mining strategy for the Shahuindo mine.

 

·                  Tahoe has conducted further metallurgical testing on the ore at Shahuindo and has revised the metallurgical assumptions and flowsheet for the project.

 

This report has been completed in accordance with the disclosure and reporting requirements set forth in the Toronto Stock Exchange Manual, National Instrument 43-101 Standards of Disclosure for Mineral Projects (NI 43-101), Companion Policy 43-101CP to NI 43-101, and Form 43-101F1 of NI 43-101.

 

2.2          Sources of Information

 

Information contained in this Report was obtained from prior Technical Reports and from work completed by independent consultants on behalf, and under the direction, of Rio Alto and Tahoe, and by work completed by Rio Alto and Tahoe personnel under the guidance of the authors. Information included herein derived from this work is cited in the text of this Report, with references listed in Section 27.0. The authors have made all reasonable effort to establish the completeness and authenticity of the information provided in this Report.

 

Prior Technical Reports filed on the Shahuindo project include:

 

·      Resources Estimation, Shahuindo Project, Peru (Saucier and Poulin, 2004)

 

·      Resources Estimation, Shahuindo Project, Peru (Saucier and Buchanan, 2005)

 

17


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                  Shahuindo Gold Project, Cajabamba Province, Peru, NI 43-101 Technical Report on Preliminary Assessment (Wright et al., 2010a)

 

·                  Shahuindo Gold Project, Cajabamba Province, Peru, NI 43-101 Technical Report on Preliminary Assessment (Wright et al., 2010b)

 

·      Technical Report on the Shahuindo Project, Cajabamba, Peru (Tietz and Kappes, 2011)

 

·      Updated Technical Report on the Shahuindo Project, Cajabamba, Peru (Tietz and Defilippi, 2012)

 

·      Technical Report on the Shahuindo Heap Leach Project (Defilippi, et. al., 2012)

 

2.3          Qualified Persons and Site Visits

 

Mr. Tim Williams, Tahoe’s Vice President Operations and Peru Country Manager, Mr. Charles V. Muerhoff, Tahoe’s Vice President Technical Services and Mr. Carl E. Defilippi of Kappes, Cassiday & Associates prepared this Technical Report. Each is a Qualified Person (QP) by NI 43-101 definitions.

 

Dates of site visits and specific sections of the Report that the Qualified Persons are responsible for are listed in Table 2.3-1.

 

Table 2.3-1           Qualified Persons - Site Visits and Report Responsibilities

 

QP Author

 

Company

 

Designation

 

Site Visit

 

Section Responsibility

 

Tim Willams

 

Tahoe Resources Inc.

 

FAusIMM

 

Multiple Site Visits 2014 & 2015

 

Sections 4, 15, 16, 18, 20 and corresponding items in Sections 1, 25, 26

 

Charles V. Muerhoff

 

Tahoe Resources Inc.

 

SME Registered Member

 

May 19-20, 2015 November 13-14, 2015

 

Sections 2, 3, 5 through 12, 14, 19, 21 through 24 and corresponding items in Sections 1, 25, 26

 

Carl E. Defilippi

 

Kappes, Cassiday & Associates

 

SME Registered Member

 

May 4-7, 2010 April 6-8, 2010  September 2-3, 2015

 

Sections 13, 17 and corresponding items in Sections 1, 25, 26

 

 

2.4          Effective Dates

 

The effective date of this Technical Report is 01 January 2016. The effective date of the Shahuindo Mineral Resource estimate is the 15 April 2015. The effective date of the Shahuindo Mineral Reserve Estimate is 01 November 2015.

 

18


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

2.5          Units of Measurements

 

Unless otherwise specified, all monetary dollars expressed in this Report are in United States dollars ($). Metal grades are expressed in grams per metric tonne (g/t) and metal content is expressed in troy ounces. All units of measure, unless otherwise specified, are metric.

 

2.6          Abbreviations and Acronyms

 

A list of abbreviations and acronyms commonly used in this report is provided in Table 2.6-1.

 

19


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 2.6-1           List of Abbreviations

 

Abbr.

 

Description

 

Abbr.

 

Description

 

$

 

United States of America dollars

 

m

 

meters

 

μ

 

microns

 

m2

 

square meters

 

ADR

 

adsorption-desorption-refining

 

m3

 

cubic meters

 

Ag

 

silver

 

MCE

 

maximum considered earthquake

 

ARD

 

acid rock drainage

 

MEM

 

Ministry of Energy and Mines

 

Au

 

gold

 

mm

 

millimeters

 

AuEq

 

gold-equivalent

 

MMR

 

Minimum Mining Royalty

 

bcm

 

bank cubic meters

 

Moz

 

million troy ounces

 

CAPEX

 

capital expenditure

 

MPa

 

million Pascal

 

CIM

 

Canadian Institute of Mining, Metallurgy and Petroleum

 

Mt

 

millions of dry metric tonnes

 

CIRA

 

Certificate for the Inexistence of Archaeological Remains

 

Mt/y

 

million tonnes per year

 

CN

 

cyanide

 

MW

 

megawatt

 

dmt

 

dry metric tonne

 

NAG

 

non acid generating

 

DSHA

 

deterministic seismic hazard assessment

 

NI 43-101

 

Canadian National Instrument 43-101

 

EIA

 

Estudio de Impacto Ambiental (environmental impact study)

 

NPV

 

net present value

 

GEU

 

Geo Environmental Unit

 

NSR

 

net smelter return

 

g/t

 

grams per metric tonne

 

oz

 

troy ounce

 

in

 

inches

 

PAG

 

potentially acid generating

 

ha

 

hectare

 

PGA

 

peak ground acceleration

 

HDPE

 

high-density polyethylene

 

PLS

 

pregnant leach solution

 

hp

 

horsepower

 

ppm

 

parts per million

 

IBC

 

International Building Code

 

PSAD

 

Peru Central Zone

 

IGV

 

impuesto general a las ventas

 

PSHA

 

probabilistic seismic hazard assessment

 

IP

 

induced polarization

 

QA/QC

 

quality assurance and quality control

 

IRR

 

internal rate of return

 

QP

 

Qualified Person

 

k

 

thousand

 

RC

 

reverse circulation

 

Koz

 

thousands of troy ounces

 

RMR

 

rock mass rating

 

kPA

 

kilopascal

 

ROM

 

run-of-mine

 

kt

 

thousand tonnes

 

SENACE

 

National Environmental Certification Service

 

ktpd

 

thousand tonnes per day

 

SERNANP

 

National Service of Natural Protected Areas of the State

 

kV

 

kilovolt

 

SMT

 

Special Mining Tax

 

kW

 

kilowatt

 

t

 

dry metric tonne

 

lb

 

pound (weight)

 

tpd

 

tonnes per day

 

L/s

 

liters per second

 

t/y

 

tonnes per year

 

kt

 

thousand tonnes

 

UCS

 

unconfined compressive strength

 

ktpd

 

thousand tonnes per day

 

UIT

 

tax unit

 

kV

 

kilovolt

 

V

 

volt

 

L/hr/m2

 

liters per hour per square meter

 

WGS

 

World Geodetic System

 

LOM

 

life of mine

 

 

 

 

 

 

20


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

3.0          RELIANCE ON OTHER EXPERTS

 

This report has been prepared by Tahoe based on a high level assessment conducted on the Shahuindo mine in Peru. The information, conclusions, opinions, and estimates contained herein are based on:

 

·      Information available to Tahoe at the time of preparation of this report;

 

·      Assumptions, conditions, and qualifications as set forth in this report; and

 

·      Data, reports, and other information supplied by third parties under the direction of Tahoe.

 

The QPs as authors of this Report state that they are Qualified Persons for the Report as identified in the “Certificate of Qualified Person” for each author included in Section 28.0. Results and opinions included in this Report that are dependent on information provided by persons outside the employ of Tahoe are assumed to be current, accurate and complete as of the effective date of this Report. The preceding notwithstanding, the QPs assume responsibility for the information and conclusions contained in each of the QPs respective sections of this Report.

 

Reports received from other experts have been reviewed for factual errors by Tahoe. Any changes made as a result of these reviews did not involve any alteration to the conclusions made. Hence, the statements and opinions expressed in these documents are given in good faith and in the belief that such statements and opinions are not false and misleading at the effective date of this Report.

 

None of the authors of this Report are experts in verifying the legal status or ownership of mining concessions and surface lands in Peru. As such, the authors have relied on outside independent Peruvian legal counsel to verify the validity of Shahuindo SAC’s mining concessions and surface land ownership. The following title opinions were prepared on behalf of the Company:

 

·                  Title Opinion on the Shahuindo Mining Concessions, prepared by Pickmann and Ruiz (2015) for Tahoe Resources Inc. (unpublished)

 

·                  Title Opinion on the Shahuindo Surface Lands, prepared by Pickmann and Ruiz (2015) for Tahoe Resources Inc. (unpublished)

 

References to technical reports and data generated by prior owners of the Shahuindo property and by consultants in the employ of Rio Alto or Tahoe used in the compilation of this Technical Report are included in Section 27.0.

 

21


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

4.0                               PROPERTY DESCRIPTION AND LOCATION

 

4.1                               Location

 

The Shahuindo Project is located in the district of Cachachi, province of Cajabamba, department and region of Cajamarca, Peru. It is situated approximately 59 kilometers southeast of the town of Cajamarca and 14 kilometers west of the town of Cajabamba. The project is located at latitude 7 degrees 25 minutes south, longitude 78 degrees 25 minutes west or Universal Transverse Mercator (UTM) coordinates 9,158,000-North and 807,000-East, Zone 17S. The location of the project site is illustrated in Figure 4.1-1.

 

 

Figure 4.1-1                           Shahuindo Project Location Map

 

4.2                               Mineral Tenure and Title

 

The Shahuindo project comprises one mineral right, Acumulacion Shahuindo, which includes 26 mineral titles1 100% controlled by Tahoe’s wholly owned subsidiary, Shahuindo SAC, and has an approximate area of 7,338.91 hectares. Table 4.2-1 summarizes Shahuindo SAC’s mineral claims that are included in Acumulacion Shahuindo. The mineral claims are illustrated in Figure 4.2-1.

 


1     In accordance with Supreme Decree 014-92-EM, the Accumulation is a procedure approved by INGEMMET (a State-owned company focused on the exploration, development and management of properties and mining companies in Peru) where mineral concessions can be accumulated into one group only when these mineral concessions are adjacent to one another and owned by the same owner. The Accumulation which in this case is called “Acumulacion Shahuindo” is the newly created concession which includes the 26 original mining concessions.

 

22


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 4.2-1                                Mineral Title Summary

 

Concession

 

 

Application
Area
(hectares)

 

 

Actual Size
(hectares)

 

 

Application
Method

 

 

Date of Grant

San Jose

 

 

2.83

 

 

2.83

 

 

Stake-based

 

 

July 2, 1917

Puma Shahuindo

 

 

2.33

 

 

2.33

 

 

Stake-based

 

 

July 5, 1917

Pilacones 8

 

 

601.59

 

 

58.66

 

 

Grid-based

 

 

January 29, 1998

Pilacones 7

 

 

300.8

 

 

3.45

 

 

Grid-based

 

 

November 18, 1996

Pilacones 6

 

 

1002.62

 

 

401.38

 

 

Grid-based

 

 

April 9, 1999

Pilacones 5

 

 

701.82

 

 

492.35

 

 

Grid-based

 

 

April 21, 2003

Pilacones 4

 

 

100.26

 

 

20.93

 

 

Grid-based

 

 

April 1, 1996

Pilacones 3

 

 

902.36

 

 

571.15

 

 

Grid-based

 

 

August 31, 1997

Pilacones 2

 

 

701.85

 

 

246.85

 

 

Grid-based

 

 

December 30, 1997

Perdida 3

 

 

601.96

 

 

548.65

 

 

Stake-based

 

 

November 30, 1994

Perdida 2

 

 

391.11

 

 

357.92

 

 

Stake-based

 

 

August 24, 1995

Perdida 1

 

 

601.72

 

 

570

 

 

Stake-based

 

 

November 30, 1994

Nltrogeno

 

 

2

 

 

2

 

 

Stake-based

 

 

August 7, 1922

Moyan 3

 

 

280.78

 

 

280.78

 

 

Stake-based

 

 

November 30, 1994

Moyan 2

 

 

201.36

 

 

201.36

 

 

Stake-based

 

 

November 30, 1994

Moyan 1

 

 

541.48

 

 

541.48

 

 

Stake-based

 

 

February 16, 1995

Malvas

 

 

250.68

 

 

250.68

 

 

Stake-based

 

 

September 26, 1959

Malvas 92

 

 

701.904

 

 

295.07

 

 

Stake-based

 

 

August 6, 1999

Descubridora

 

 

4.25

 

 

4.25

 

 

Stake-based

 

 

June 19, 1917

Antimonlo

 

 

2

 

 

2

 

 

Stake-based

 

 

June 2, 1921

Algamarca 4

 

 

993.17

 

 

980

 

 

Stake-based

 

 

March 8, 1991

Algamarca 2B

 

 

20.33

 

 

20.34

 

 

Stake-based

 

 

February 16, 1995

Algamarca 2

 

 

200.56

 

 

200.56

 

 

Stake-based

 

 

October 31, 1994

Algamarca 1

 

 

501.35

 

 

501.35

 

 

Stake-based

 

 

April 23, 1991

Acumulaclon

 

 

802.15

 

 

797.9

 

 

Stake-based

 

 

March 31, 1987

Algamarca Selenlo

 

 

4.01

 

 

4.01

 

 

Stake-based

 

 

August 22, 1981

 

23


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 4.2-1                           Mineral Claim Location Map

 

24


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The mining rights and surface rights are registered under the name of Shahuindo SAC in the government title registry office of La Superintendencia Nacional de los Registros Públicos (SUNARP). The mining claims have no expiry date. All concessions are subject to an annual payment of $3 per hectare to the Peruvian government. A Peruvian law firm, Gallo Barrios Pickmann, issued a legal opinion to Tahoe in 2015 verifying the Company’s title to the concessions within Acumulacion Shahuindo (Pickmann and Ruiz, 2015). All claims are in good standing as of the effective date of this Report.

 

4.3                               Surface Rights

 

Shahuindo SAC has acquired 381 surface rights within the Shahuindo Project area to date, covering a total area of approximately 2,559 hectares. Some of these surface rights were used to relocate local land owners into new areas. Shahuindo SAC also acquired additional surface rights outside the mining concessions for the same process of relocating land owners. Shahuindo SAC and Desarrollo Agricola Del Norte (DAN) entered into a service agreement for this process; whereas DAN acquired the land outside the mining concessions and will transfer the properties to Shahuindo SAC to be swapped with land inside the concessions. A legal title opinion by Gallo Barrios Pickmann confirms the land ownership by Shahuindo SAC and DAN (Pickmann and Ruiz, 2015). The Company controls sufficient surface lands to accommodate the infrastructure necessary to operate the Shahuindo mining project as envisioned in this study.

 

4.4                               Informal Mining Activity

 

There is a small group of informal miners within the project area who are exploiting narrow veins on the west side of the Algamarca anticline. Shahuindo SAC is promoting and participating in a round table discussion with the Algamarca informal miners to update the environmental, social and economic baseline and to work on a sustainable solution to stop all informal mining activity and replace it with other economic alternatives.

 

Since 2004, Shahuindo SAC has submitted formal reports to the Ministry of Energy and Mines (MEM) regarding the informal mining activities in the mining concessions. The informal mining activities in the Algamarca area are outside the project area approved in the Environmental Impact Statement for Shahuindo.

 

Until recently, a second group of informal miners were active in the northern portion of the Shahuindo project, known locally as the La Chilca area. In August 2015, Shahuindo SAC recovered the La Chilca area from the informal miners and the area is now in possession of Shahuindo SAC.

 

25


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

4.5                               Environmental Considerations

 

4.5.1                     Environmental Regulations

 

The General Mining Law of Peru is the primary body of law with regard to environmental regulation of exploration and mining activities. The General Mining Law is administered by the MEM. A detailed description of Peru’s environmental regulations is found on the MEM website at www.minem.gob.pe. Depending on the level of project development, MEM requires exploration and mining companies to prepare an Environmental Impact Statement (EIA) Category I, Environmental Impact Study Semi Detailed (EIAsd) Category II, Environmental Impact Study Detailed (EIAd) Category III (see Table 4.5-1), an Environmental Impact Assessment, a Program for Environmental Management and Adjustment, and a mine closure plan. Mining companies are also subject to annual environmental audits of operations by the Organismo de Evaluación y Fiscalización Ambiental (OEFA).

 

The environmental and legal framework for the specific case of the Shahuindo project is detailed in Section 20.0 of this technical report.

 

According to Peruvian regulations D.S. 020-2008-EM and R.M. 167-2008-MEM-DM, a DIA-Category I covers drilling from less than 20 drill platforms within a 10 hectare area. An EIAsd-Category II is applicable to mining and exploration programs with either more than 20 drill platforms, exploration areas greater than 10 hectares, or construction of more than 50 meters of underground development. An EIAd is necessary for mining operations. All classifications require the development of a community involvement processes.

 

A new Environmental Impact Study must be developed when additional, previously undisturbed areas are proposed to be added to an operation per Peruvian regulations DS 016-93-EM, D.S. 028-2008-EM and R.M. 304-2008-MEM-DM, review articles 15 and 16, and must include preparation of an executive summary and scheduling of public workshops and community participation.

 

The Environmental Impact Study must incorporate planned expenditure on environmental programs at a rate that is no less than one percent of the value of annual production of the planned operation. MEM is required to review and render a decision on the project within 120 days, including initial notification, and the initial stage of the public consultation process. Formal project approval may take from 8 to 12 months. Within this period, the applying company must organize public hearings and workshops to present project data and coordinate the dates and locations of such hearings with the MEM.

 

26


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 4.5-1                                Summary of Environmental Requirements for Mining Exploration Programs

 

Classification

 

 

Description

 

 

Application Requirements

Category I
Environmental Impact Statement (EIA)

 

 

Mineral exploration with less than 20 drill platforms within a 10 ha area.

 

 

Required information as shown in Article 5 of Environmental Regulations for Mining Exploration.

 

 

 

 

 

 

 

 

 

Category II
Environmental Impact Study Semi-Detailed (EIAsd)

 

 

Mineral exploration with more than 20 drill platforms, exploration areas greater than 10 ha and/or construction of more than 50m of underground development.

 

 

Prepare an Environmental Evaluation (EA) report as per the Environmental Regulations for Mining Exploration.

 

 

 

 

 

 

 

 

 

 

 

 

Category III
Environmental Impact Study Detailed (EIAd)

 

 

Projects whose characteristics, size and/or location have the potential to produce significant (quantitative or qualitative) negative environmental impacts.

 

 

Requires a thorough analysis to review impacts and propose corresponding environmental management strategy.

 

 

 

 

 

 

 

 

 

 

 

 

 

A company must also prepare and submit a closure plan (Plan de Cierre de Minas) for each component of its operation. The closure plan must outline what concurrent, closure, and post-closure measures will be taken to protect the environment from impacts of the mining operation. The closure plan includes a detailed cost estimate and schedule of expenditures.

 

The General Mining Law of Peru has in place a system of sanctions or financial penalties that can be levied against a mining company which is not in compliance with the environmental regulations.

 

4.6                               Permits

 

Exploration, construction and commissioning operations conducted to date have been performed under the relevant local and national permits. All permits and licenses to conduct operations at Shahuindo either have been received or are in the process of finalization. The Company does not anticipate delays to the production schedule presented in this Technical Report due to the timing of receipt of necessary permits and licenses. Key permits required for mine operations are summarized in Table 4.6-1; the status of each relevant permit as it relates specifically to the Shahuindo operations is discussed in Section 20.0.0 of this Report.

 

27


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 4.6-1    List of Permits and Status

 

Permit

 

 

Status

 

 

Date of 
Approval

 

 

Approved By

 

 

Government Department

 

 

Comments

Certificate for the Inexistence of Archaeological Remains (CIRA)

 

 

In Process

 

 

 

 

 

 

 

 

Ministry of Culture

 

 

Currently undertaking Archaeological Evaluation (PEA in the Spanish acronym) for this permit

 

 

Approved

 

 

11-Jul-13

 

 

CIRA No 173-2013

 

 

Ministry of Culture

 

 

Certificate for the Inexistence of Archaeological Remains

 

 

Approved

 

 

15-Sep-15

 

 

CIRA No 232-2015

 

 

Ministry of Culture

 

 

Certificate for the Inexistence of Archaeological Remains - Four Rescued Areas

 

 

Approved

 

 

29-May-15

 

 

R.D. No 125-2015-DDCCAJ/MC

 

 

Ministry of Culture

 

 

Archaeological Monitoring Plan (PMA)

Environmental Impact Assessment

 

 

Approved

 

 

10-Sep-15

 

 

R.D. 339-2013-MEM/AAM

 

 

Ministry of Energy and Mines

 

 

Environmental Impact Assessment

 

 

Approved

 

 

18-Dec-14

 

 

R.D. 613-2014-MEM-DGAAM

 

 

Ministry of Energy and Mines

 

 

First Technical Sustentatory report of Environmental Impact Assessment (ITS-l-EIA)

 

 

Approved

 

 

07-Jul-15

 

 

R.D. 265-2015-MEM-DGAAM

 

 

Ministry of Energy and Mines

 

 

Second Technical Sustentatory report of Environmental Impact Assessment (ITS-2-EIA)

 

 

In Process

 

 

 

 

 

 

 

 

Ministry of Energy and Mines

 

 

EIA modification (MEIA)- For Phase 2 Expansion

Mine Closure Plan

 

 

Approved

 

 

10-Mar-15

 

 

R.D No 132-2015-MEM-DGAAM

 

 

Ministry of Energy and Mines

 

 

 

Beneficiation Concession

 

 

Approved

 

 

14-Apr-15

 

 

Resolution No. 145-2015-MEM/DGM/V

 

 

Ministry of Energy and Mines

 

 

Construction of the components of beneficiation to the Shahuindo Project of 10,000 TMD

 

 

 

Approved

 

 

25-Nov-15

 

 

R.D No. 2468-2015-MEM/DGM

 

 

Ministry of Energy and Mines

 

 

License to Operate Processing Plant

Permanent Power Concession

 

 

Not required

 

 

 

 

 

 

 

 

 

 

 

Not required at start-up due to first two year of power supplied by generators. Will apply when required.

Water usage permits

 

 

Approved

 

 

16-Jul-15

 

 

Resolution No. R.D No 655.2015-ANA-AAA.M

 

 

National Water Authority

 

 

 

Water License

 

 

Approved

 

 

12-Nov-15

 

 

R.D No 1157-2015-ANA-AAA.M

 

 

National Water Authority

 

 

 

Easements and rights-of-way

 

 

Not required

 

 

 

 

 

 

 

 

 

 

 

Not required at start-up due to first two year of power supplied by generators. Will apply when required.

District and Provincial municipality licenses

 

 

In Process

 

 

Various

 

 

 

 

 

 

 

 

In process and obtained when required.

Mining Plan

 

 

In Process

 

 

27-Nov-15

 

 

Resolution No 0587-2015-MEM-DGM/V

 

 

Ministry of Energy and Mines

 

 

Authorization for Construction, awaiting Mining Plan.

Operations Permits

 

 

In Process

 

 

Various

 

 

 

 

 

 

 

 

In process and obtained when required.

 

28


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

4.6.1       Environmental Laws

 

Under Legislative Decree 1013, approved on 14 May 2008, the government created the Ministry of the Environment to coordinate all environmental matters at the executive level. Currently, the Ministry of the Environment is charged with the implementation of the National Environmental Policy and direction of the environmental control regime, among other responsibilities.

 

The Ministry of the Environment works in coordination with different appointments to the ministry such as the National Service of Natural Protected Areas of the State (SERNANP) and the National Environmental Certification Service (SENACE) for the purposes of implementing sustainable investment and responsibilities for review and approval of detailed Environmental Impact Studies (EIA-d).

 

4.6.1.1          Environmental Legal Framework Applied to Mining Activities

 

The Environmental Regulations for the Activities of Exploitation, Processing, Transport, Auxiliary Works and Development of Mining and Metallurgic Activities are the controlling regulatory acts that establish, among others, the environmental requirements necessary conduct mining activities within the Peruvian territory.

 

Under this legal framework, the General Bureau of Environmental Affairs (DGAAM) of the Ministry of Energy and Mines (MEM) is the responsible governmental agency to approve the environmental studies required to undertake mining activities in Peru, while the Environmental Inspections and Auditing Bureau (OEFA) of the Ministry of the Environment is currently the agency responsible for the inspection and auditing of mining projects and operations in order to confirm compliance with environmental obligations and related commitments.

 

4.6.1.2          Exploration Activities

 

Environmental aspects specifically related to exploration projects are governed by the Regulations on Environmental Protection for the Development of Mining Exploration Activities under Supreme Decree 020-2008-EM. Pursuant to these regulations, depending on the scale and impact of the exploration activities to be conducted, exploration projects are classified into the following two categories:

 

·                  Category I: Before conducting exploration activities under this category, title holders are required to submit a DIA and have it approved by the DGAAM.

 

·                  Category II: In order to conduct exploration activities under this category, title holders are required to have an EIAsd approved by the DGAAM.

 

The approval of the corresponding environmental certificate does not grant the titleholder the right to start conducting exploration activities, given that titleholders of mining concessions are also required to

 

29


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

obtain all governmental consents and permits legally required and access and usage rights granted by the landowner to use the surface lands.

 

4.6.2       Mine Development, Exploitation and Processing Activities

 

Pursuant to the Environmental Regulations for the activities of Exploitation, Processing, Transport, Auxiliary Works and Development of Mining and Metallurgic Activities, prior to conducting mining and processing activities, titleholders of mining concessions must have an EIA approved.

 

4.6.3       Mine Closure and Site Remediation

 

4.6.3.1    Exploration Activities

 

Regarding environmental remediation of areas affected by mining exploration activities, the Regulations on Environmental Protection for the Development of Mining Exploration Activities requires titleholders of mining exploration projects to conduct ‘progressive closure’, ‘final closure’ and ‘post closure’ programs as outlined in the corresponding environmental study. Any amendment of the closure measures or its terms requires the prior approval of the DGAAM.

 

4.6.3.2    Mining Development, Exploitation and Processing

 

Prior to the start-up of mining activities, including mine development, exploitation and processing, titleholders are required to have a Mine Closure Plan, duly approved by the DGAAM prior to carrying out activities.

 

Peruvian legal framework covering Mine Closure Plans includes a number of financial and legal requirements intended to ensure the completion of the closure obligations by the titleholders of mining projects. In case of non-compliance, these financial and legal requirements allow the mining authority to seize the financial guarantees from titleholders and complete the Mine Closure Plans as approved.

 

4.6.4       Existing Environmental Conditions

 

There are surface disturbances associated with informal mining activity within the project area, primarily in the Algamarca anticline and La Chilca areas. The Company is currently conducting environmental field studies as there is an expectation that some level of environmental contamination may be associated with these sites.

 

4.7          Royalties, Taxes and Fees

 

4.7.1       Maintenance Fees

 

Pursuant to article 39 of the General Mining Law, titleholders of mining concessions pay an annual Maintenance Fee (Derecho de Vigencia) of $3.00 per hectare. The maintenance fee is due by 30 June

 

30


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

and is effective for the following year. Failure to make payments for two consecutive years causes the termination (caducidad) of the mining concession. However, according to article 59 of the General Mining Law, the payment for one year may be delayed with penalty and the mining concessions remain in good standing. The outstanding payment for the past year can be paid on the following June 30 along with the future year. Maintenance fees for concessions held in Acumulacion Shahuindo are current.

 

4.7.2       Minimum Production Obligation

 

Legislative Decree 1010, dated 09 May 2008 and Legislative Decree 1054, dated 27 June 2008 amended several articles of the General Mining Law regarding the Minimum Production Obligation, establishing a new regime for compliance (New MPO Regime).

 

According to the New MPO Regime, titleholders of metallic mining concessions must reach a minimum level of annual production (Minimum Production) of at least one Tax Unit2 or “UIT” (S/. 3,850 per hectare) and three UITs within a period of ten years. The ten year period begins on January 1st of the year following granting of the concession.

 

In the case of mining concessions that were granted on or before 10 October 2008 until the ten year term for reaching Minimum Production established by the New MPO Regime elapses on 01 January 2019, these mining concessions will be subject to the former provisions of the General Mining Law. Failure to comply with the minimum production requirements of the New MPO Regime obligates the concession holder to pay a penalty and may result in the termination of the concessions.

 

4.7.3       Royalties, OSINERGMIN Contribution and OEFA Contribution

 

4.7.3.1          Royalties

 

In June 2004, Peru’s Congress authorized a royalty payment structure pertaining to mining operations. Congress further modified the royalty regime under Law No. 29788 which went into effect on 01 October 2011 (Modified Mining Royalty or MMR). The MMR is applied to quarterly operational profit (i.e., operating margin), calculated by dividing the quarterly operating profit by the income generated from the quarterly sales of the mining product. The amount to be paid in royalties is the greater of the quarterly operation profit rate, which ranges from one percent to 12%, or one percent of the revenues generated by quarterly sales. In the case of the small scale mining titleholders, the mining royalty is set to zero. The payment of the mining royalty is considered an expense when determining corporate income tax in Peru.

 


2  Pursuant to Supreme Decree 304-2013-EF, dated 11 December 2013, the Tax Unit was set at S/.3,850 (approximately $ 1,360)

 

31


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

4.7.3.2    OSINERGMIN Contribution

 

El Organismo Supervisor de la Inversión en Energía y Minería (OSINERGMIN) is Peru’s state energy and mines investment regulator which has the mission to regulate, supervise and oversee national compliance with legal and technical dispositions related to activities in the electricity, hydrocarbon and mining industry sectors, as well as compliance with legal and technical requirements concerning environmental conservation and protection in the development of these activities. OSINERGMIN is the government agency of record to inspect and audit compliance with safety, job-related health and mine development matters.

 

Supreme Decree 128-2013-EF, published on 19 December 2013 established the rate applicable for the OSINERGMIN contribution. This payment is made by all large and medium scale mining titleholders and is calculated on the value of the monthly operating costs, corresponding to the activities directly related to OSINERGMIN minus the Valued Added Tax and the Municipal Promotion Tax.

 

OSINERGMIN rates by year:

2014: 0.21%

 

2015: 0.19%

 

2016: 0.16%

 

4.7.3.3          OEFA Contribution

 

El Organismo de Evaluación y Fiscalización Ambiental (OEFA) is the government agency of record that inspects and audits mining projects operations in order to secure compliance with environmental obligations and related commitments.

 

The Supreme Decree 130-2013-EF, published on December 19, 2013, established the rate applicable for the OEFA Contribution. This payment is made by all large and medium scale mining titleholders and is calculated on the value of the monthly costs corresponding to all activities directly related to OEFA minus the Valued Added Tax and the Municipal Promotion Tax. The OEFA rate is currently set at 0.13% for 2016.

 

4.7.4       Ownership of Mining Rights

 

Pursuant to the General Mining Law, mining rights may be forfeited only due to a number of enumerated circumstances provided by law (i.e., non-payment of maintenance fees and/or noncompliance with the Minimum Production Obligation). The right of concession holders to sell mine production freely in world markets is established. Peru is party to agreements with the World Bank Multilateral Investment Guarantee Agency and with the Overseas Private Investment Corporation.

 

32


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

4.7.5       Taxation and Foreign Exchange Controls

 

A recent modification of the tax law approved by the government reduced corporate taxes beginning in year 2015. The law progressively decreases the tax from 30% (applied in 2014) to 26% (2019 onward). The new law reduces the rate of corporate income tax and increases the tax rate on dividends as summarized in the following schedule in Table 4.7-1.

 

Table 4.7-1                                Corporate Income Tax

 

Fiscal Years

 

Corporate Income Tax

 

Dividends

 

2015 — 2016

 

28

%

6.8

%

2017 — 2018

 

27

%

8.0

%

2019 — forward

 

26

%

9.3

%

 

There are currently no restrictions on the ability of a company operating in Peru to transfer dividends, interest, royalties or foreign currency in or out of Peru or to convert Peruvian currency into foreign currency.

 

Congress has approved a Temporary Net Assets Tax, which applies to companies subject to the General Income Tax Regime. Net assets are taxed at a rate of 0.4% on the value exceeding one million Peruvian soles (approximately $345,000). Taxpayers must file a tax return during the first 12 days of April and the amounts paid can be used as a credit against Income Tax. Mining companies which have not started production and those in their first year of operation are exempt from the tax.

 

The Company is also subject to a Special Mining Tax (SMT) which is applied to operating income based on a sliding scale with progressive marginal rates ranging from 2% to 8.4%. The SMT has been considered as an income tax for the purposes of this study.

 

The Tax Administration Superintendent is the entity empowered under the Peruvian Tax Code to collect federal government taxes. The Tax Administration Superintendent can enforce tax sanctions, which can result in fines, the confiscation of goods and vehicles, and the closing of a taxpayer’s offices.

 

4.7.6       Worker Participation

 

Under Peruvian law, every company that generates income and has more than twenty employees on its payroll is obligated to grant a share of its profits to its workers. For mining companies, the percentage of this profit-sharing benefit is eight percent of taxable income. The profit-sharing amount made available to each worker is limited to 18 times the worker’s monthly salary, based upon their salary at the close of the previous tax year.

 

33


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

4.7.7       Regulatory and Supervisory Bodies

 

The five primary agencies in Peru that regulate and supervise mining companies are:

 

1.     Ministry of Energy and Mines (MEM),

 

2.     National Institute of Concessions and Mining Cadastral (INGEMMET),

 

3.     Supervisory Entity for the Investment in Energy and Mining (OSINERGMIN),

 

4.     Labour Ministry (MINTRA) and

 

5.     Environmental Inspections and Auditing Bureau (OEFA) of the Ministry of the Environment.

 

The MEM promotes the integral and sustainable development of mining activities, as well as regulates all the activities in the Energy and Mines sector.

 

The INGEMMET is the Government Entity in charge of granting mining concessions, which entitles the concession holder the right to explore and exploit the area in which boundaries such concessions are located.

 

OSINERGMIN and MINTRA oversee regulatory compliance with safety, job-related health, contractors, and mine development matters, while OEFA oversees regulatory compliance with environmental regulation, investigating and sanctioning the breach of any environmental obligation.

 

4.8                               Risks that may affect Access, Title, or the Right or Ability to Perform Work

 

Natural resources exploration, development, production and processing involves a number of risks, many of which are beyond the Company’s control. Project and business risk factors and discussion on these are included in the Company’s quarterly Management Discussion and Analysis and the Annual Information Forms filed on SEDAR. Such risks include the following:

 

·      Changes in the market price for mineral products.

 

·                  Community groups or non-governmental organizations that may initiate or undertake actions that could delay or interrupt the Company’s activities at Shahuindo.

 

·                  Although the Company believes it has a good understanding of the Shahuindo deposit and is successfully operating the nearby La Arena mine, the Company has no operating history at Shahuindo.

 

·                  Future construction and operating costs may differ from those costs projected in the financial study for Shahuindo.

 

34


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                  While the Company considers the regulatory environment in Peru to be very stable, the Company’s activities are subject to environmental laws and regulations that may change over time.

 

·                  The Company requires numerous permits in order to conduct exploration, development and mining activities at Shahuindo. Delays in obtaining the final permits and licenses necessary for sustained operations or failure to comply with the terms of any such permits and licenses could have a material adverse effect on the Shahuindo project.

 

·                  Title to the Company’s mineral properties at Shahuindo may be subject to prior unregistered agreements, transfers or claims or defects.

 

·      Changes in taxation legislation or regulations in Peru.

 

The foregoing notwithstanding, the Company believes that there are no significant risks to the Shahuindo project in regards to surface and concession title, the ability to access the project, the receipt of the remaining permits and licenses, or the Company’s ability to perform the work as described in this technical report.

 

35


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

5.0                               ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY

 

5.1          Accessibility

 

The Shahuindo Project is located in northern Peru approximately 970 kilometers by road north-northwest of Lima. The project site can be accessed from Lima by traveling north on Highway 1 (Pan-American Highway) to Ciudad de Dios, then east on Highway 8 to Cajamarca. The site is approximately 130 kilometers from Cajamarca via asphalt-paved highway (100 kilometers on Highway 3N), and gravel and dirt roads. The route from Cajamarca to Shahuindo is shown in Figure 5.1-1.

 

Figure 5.1-1         Shahuindo Road Route from Cajamarca

 

36


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

There are several seaports available to the Company for equipment import — the Port of Callao in Lima, Port of Paita (northern Peru) and Port Salaverry at Trujillo. There are daily flights between Lima and Cajamarca on Peruvian national airlines.

 

5.2          Climate

 

Climate in the area is typical of the sierra region. It is cold and dry during the dry season and humid during the rainy season. Rainfall typically occurs between October and April (wet season), with occasional sporadic showers in the other months. The average annual rainfall is about 1000mm with an extreme wet year having a rainfall of 1,550mm and an extreme dry year receiving 449mm. The dry season months are May through September.

 

The average daily temperature is 15.7ºC, reaching 23.1ºC during the day and decreasing to 7.5ºC in the night. The average minimum temperature is 9.7ºC and the average maximum temperature is 22.3ºC.

 

The prevailing wind direction is east-northeast with speeds ranging from 0 to 3.1 m/s.

 

Exploration and mining can be conducted year round with minimal impacts from the weather, though plastic overliners (raincoats) will be used to limit infiltration of precipitation into the leach pads during the wet season.

 

5.3          Local Resources & Infrastructure

 

Manning requirements for the project are sourced according to the company’s employment policy, with priority given to the local area, then expanding to the surrounding communities, including Cajabamba, whenever possible. More experienced and technical personnel have been recruited from Cajamarca and from throughout Peru. The project currently employs 1,310 people, with 73% of employees from within Cajamarca province.

 

Power for the operations will initially be from diesel generators located on site. As the mine ramps up production, the site will be connected to the trans-national 220 kV transmission line which was recently completed and passes within 3 kilometers of the site. It is currently planned to connect to line power in the second half of 2017, via a substation partially built by Sulliden which will require upgrading. From 2018 while processing 36 ktpd, the project will consume up to a maximum of approximately 45 million kWh of power per year. Maximum total demand power for the project is approximately 7.4MW. When the substation is completed, it will have an installed capacity of 40 MW.

 

The Shahuindo heap leach project will require a water supply for mining; processing, camp and other support facilities. Water demand will be highest during the dry season. During an average dry season,

 

37


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Anddes predicted the maximum water requirement to be up to 12.7 liters per second (L/s) in the dry season for the initial phase of operations (Anddes, 2015j). From January 2018, when the project ramps up to 36 ktpd and the primary leach pad is commissioned (Pad 2B), the operating flow for leaching activities is estimated to be as high as 39.9 L/s (Anddes, 2015c). Most of this water will be recycled through the closed circuit leach pad - pregnant solution pond - adsorption circuit - barren solution pond - leach pad.

 

The make-up water required by the heap leach system during the dry season, particularly during abnormally dry years, will be met from three sources:

 

1.     A 12-inch diameter water well with capacity of 15 L/s,

 

2.     Fresh water from a year-round spring with flows of four to six L/s, and

 

3.     Water stored in reservoirs which accumulate rainfall during the wet season.

 

5.4          Physiography

 

The Shahuindo property is located on the west side of the Condebamba River valley. The topography varies from rolling hillsides to steep ravines. Elevation across the project area varies from 2,400m to 3,000m above sea level.

 

The project area is classified as neo-tropical Peruvian “Yungas” by the World Wildlife Fund and includes sub-zones such as:

 

·                  Very humid tropical mountain forest. May be present in isolated inaccessible areas, but original vegetation has currently not been identified. The sub-zone is characterized by secondary successive-stage colonist species that have replaced the original forest.

 

·                  Humid tropical mountain forest. Covers 60 percent of the project area. Original vegetation is remnant and confined to ravines and steep hillsides. The majority of the sub-zone has been cleared for cultivation of potatoes, oca, mashua, tarwi, barley, broad beans, and green beans, and for cattle grazing.

 

·                  Low, dry, tropical mountain forest. Covers 40 percent of the project area, the majority of which falls within the lower part of the Shahuindo gorges, in the area near the Condebamba River. The areas are typically cultivated using irrigation. Crops include corn, potatoes, broad beans, wheat, green beans, vegetables and fruits.

 

Valley inhabitants anecdotally report the presence of deer, foxes, rabbits, vizcachas (rodents), and skunks.

 

38


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

5.5          Seismology

 

Peru is an area with high seismic and tectonic activity with earthquakes being more intense near the coastal regions and decreasing gradually towards the mountains and jungle regions.

 

According to the seismic zoning map of Peru’s National Building Regulations, the Shahuindo mine is located in Zone 3 which corresponds to moderately high seismic activity. Anddes SAC has estimated a peak ground acceleration (PGA) of 0.251g for this particular zone, based on the probabilistic seismic hazard assessment (PSHA) developed by Anddes (2015g, 2015i) for Shahuindo mine, when considering a 50 year useful life with a return period of 475 years and 10% of overage. The classification of the ground at the foundation level is of Type B (rock) according to the standards of the International Building Code (IBC) (International Code Council, 2012). Furthermore, there are additional PGA values estimated by Anddes for return periods of 100, 200, 475, 975 and 2475 years, as summarized in Table 5.5-1, which are the recommended design parameters to be utilized for the seismic design of structures.

 

Table 5.5-1                                Summary of PGA Values for Different Return Periods

 

Geographical

 

 

 

 

 

 

 

 

 

 

 

 

Coordinates

 

 

Return Period (years)

 

Longitude

 

 

Latitude

 

 

100

 

 

200

 

 

475

 

 

975

 

 

2475

 

-78,187

 

 

-7,615

 

 

PGA 0.143

 

 

PGA 0.184

 

 

PGA 0.251

 

 

PGA 0.320

 

 

PGA 0.425

 

 

According to the deterministic seismic hazard assessment (DSHA) developed by Anddes (2015i) for the Shahuindo mine, Anddes estimates a PGA of 0.286g generated by the intraslab subduction activity between the Nazca and Continental plates. This value is higher than the probabilistic PGA for a 475 year return period; however, it is important to note that estimating a return period for a deterministic analysis is unknown. For a conservative assumption, a value of 0.286g can be used as PGA with a return period of 475 years or lower.

 

The Maximum Considered Earthquake (MCE) estimated from the PSHA for a return period of 2475 years is 0.425g, which is consistent with the Maximum Credible Earthquake (MCE) estimated from the DSHA which indicates a PGA of 0.429g. For critical analysis, the International Commission on Large Dams (ICOLD, 2010) and National Earthquake Hazard Reduction Program (FEMA, 2009) criteria recommend using the MCE estimated from the DSHA calculated for the 84th percentile; in this case, it results in a PGA of 0.578g. All values are calculated for a class B site (rock) according to IBC.

 

5.6          Population Centers

 

According to Peru’s National Institute of Statistics and Information (Census 2007), Shahuindo’s Direct Area of Influence (DAI) has 3,954 inhabitants, distributed in 14 towns. An analysis of the population

 

39


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

structure by age reveals a significant majority of people under 25 years old, which increases the proportion of persons of working age. The distribution by sex shows a slight prevalence of male population.

 

On average, 80% of households are dedicated to agricultural subsistence activities that are complemented with livestock and mining.

 

Low wages and lack of opportunity in the countryside are determinants of emigration towards main cities such as Cajamarca, Trujillo or Lima. Young people move temporarily in search of quality educational services. Conversely, immigration is low, though people from nearby towns do come to the area in search of temporary jobs.

 

5.7          Local Infrastructure and Services

 

All the support infrastructure is either built or in process of construction to support the oxide gold mining and extraction activities at Shahuindo. All working areas of the mine are accessible by well-maintained dual lane gravel roads.

 

The site will be connected to the Peru power grid in mid-2017, before production increases to 36 ktpd. The energy demand for the first two years of production does not warrant the use of line power and all facilities will be connected to the internal 22.9 kV power network supplied from a substation powered by generators located near the process plant.

 

The project is considering three leach pads (1A, 2A and 2B). The initial dump leach pad construction is currently ongoing, with Pad 1A complete and construction started on Pad 2A to receive ore from mining in 2017. Pad 2B construction has been initiated using mine waste to construct the stability platform and solution ponds.

 

An independent analytical and assay laboratory and metallurgical laboratory located at the La Arena mine will be used to process all mining and metallurgical samples.

 

Two industrial water purification plants have been installed to treat 105 m3/hour to a suitable quality for discharge to the environment, one at the plant site (25 m3/hr) and a second at the camp (80 m3/hr). Other associated facilities in the process of construction are a reagent warehouse, workshop and offices.

 

Other site infrastructure constructed to date includes an explosives magazine, a temporary workshop and security guard camp. A new mine camp is currently under construction with facilities to house 200 people and a kitchen/mess hall that can cater for 750 people. The camp will be expanded to 500 beds in

 

40


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

2017. Office buildings and training infrastructure are also currently under construction with an estimated completion date of January 2016.

 

The temporary offices currently in use (former Sulliden exploration camp) all have phone and data connection via microwave link to a Peruvian telephone network with a total available bandwidth of 12 Mb/sec. A 3G cellular phone service has been installed under contract with a major Peruvian service provider and 3G signal is available across the site. These systems will be transferred to the new offices in early 2016.

 

A water well has been installed for the camps, processing plant, workshop and other facilities. The 12-inch diameter well is 300m deep and located approximately 500m above an 18 m3 water storage pond at the foot of the Algamarca anticline. The well has a nominal continuous flow capacity of 15 L/s.

 

Sewage and waste water management facilities have been installed.

 

The location of waste dumps, tailings storage, leach pads, processing plant and other infrastructure are discussed further in Section 18.0.

 

41


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

6.0          HISTORY

 

Mining in the Shahuindo area has occurred intermittently over the past few centuries, with the first mining activities conducted by the Spanish after their conquest of the Inca Empire in the 1530s. It was not until 1945 that modern mining exploration was conducted in the area.

 

6.1          Ownership History

 

Legal rights to the mineral leases of Shahuindo were in dispute between 1996 and 2009. A number of Peruvian, Mexican and Canadian companies have been involved in numerous legal processes that were eventually settled in 2009 with 100% ownership being legally registered to Shahuindo SAC (previously Sulliden Shahuindo SAC).

 

Sulliden Shahuindo SAC entered into a Transfer of Mineral Rights and Properties Contract, named Contrato de Transferencia de Propiedades Mineras (the Definitive Agreement), with Compañia Minera Algamarca S.A. and Exploraciones Algamarca S.A covering 26 mineral claims and 41 surface rights, which was formalized by public deed dated 11 November 2002.

 

Subsequently, the vendors (Compañia Minera Algamarca SA and Exploraciones Algamarca SA), controlled by new stockholders and other companies of the same group, challenged the Definitive Agreement and launched a number of judicial proceedings against Sulliden Shahuindo SAC. Sulliden Shahuindo SAC also commenced legal proceedings to confirm their rights under the Definitive Agreement and a number of other judicial proceedings to protect its title to the Shahuindo property. In 2009, Sulliden Shahuindo SAC prevailed and maintained 100% of the mineral claims and surface rights.

 

In August 2014, Rio Alto Mining Ltd. acquired all of the outstanding shares of Sulliden Gold Ltd. and became the owner of Shahuindo mineral claims and surface rights under their Peruvian subsidiary, Shahuindo SAC.

 

In April 2015, Tahoe completed an acquisition of Rio Alto Mining Ltd., acquiring control of Shahuindo SAC and the Shahuindo mineral claims and surface rights. Shahuindo SAC remains as Tahoe’s wholly owned operating company for the Shahuindo project.

 

6.2          Exploration History

 

Exploration and mining activities have been conducted on the Shahuindo leases since 1945. These exploration activities are summarized in Table 6.2-1.

 

42


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 6.2-1           Summary of Prior Exploration Activities on the Shahuindo Property

 

Period

 

Operator

 

Activities

1945 – 1989

 

Minera Algamarca SA

 

Exploration leading to the discovery and operation of an underground Cu-Ag-(Au) mine consisting of 5 adits at Algamarca. Limited small-scale mining (Au) in the Shahuindo and San José communities. No public records of exploration activities.

Circa 1990

 

Atimmsa

 

Geologic mapping, 11 reverse circulation and 6 diamond drill holes. Assays and drill logs available for the reverse circulation program.

1994 – 1996

 

Asarco LLC

 

Detailed and regional mapping, soil and rock geochemical sampling, 31 reverse circulation and 58 diamond drill holes, initial metallurgical testing. Drill exploration data available.

1997 – 1998

 

Southern Peru Copper Corporation

 

Limited surface sampling, 18 diamond drill holes, 80 reverse circulation holes, initial economic evaluation of the property. Drill exploration data available.

2002 – 2012

 

Sulliden Gold Corporation

 

Large surface drilling campaign totaling 642 holes; both diamond core and RC. Majority of the deposit within the 2012 resource outline drilled to a nominal 50m x 50m spacing.

2014-2015

 

Rio Alto Gold

 

Extensive surface drilling program of 234 RC holes, the majority of which to decrease the nominal drill spacing in the Shahuindo deposit to approximately 25m x 25m and expand the resource. An additional 12 diamond core holes were drilled for geotechnical purposes.

 

Compañia Minera Algamarca S.A. and Exploraciones Algamarca S.A. (Algamarca) commenced exploitation of the Algamarca mine in the 1940s and continued mining and exploration work on the Shahuindo property until 1989. Algamarca’s exploration activities during the 1980s led to the discovery of mineralization and mining of the San José and Shahuindo mines. Most of the Cu-Ag-(Au) vein deposits exploited by Algamarca were on the southwestern limb of the Algamarca anticline (the Algamarca mine), but several small veins and breccia zones on the northeast limb of the Algamarca anticline were also explored and mined by Algamarca (the San José and Shahuindo small-scale gold mines).

 

From about 1990 to 1998, three companies explored the Shahuindo Project area — Alta Tecnología e Inversión Minera y Metalúrgica S.A. (Atimmsa), Asarco LLC (Asarco), and Southern Peru Copper Corporation (Southern Peru). Atimmsa, Asarco, and Southern Peru completed geological mapping; soil, outcrop, and rock chip sampling; and RC and core drilling. Work by Asarco and Southern Peru led to the identification of four major low-grade gold-silver zones at Shahuindo — San José, Porphyry, South Contact, and East Zone. Southern Peru stopped work on the property in 1998 when its parent company, Asarco, merged with Grupo Mexico (Saucier and Poulin, 2004) and the property reverted to Algamarca in 1999 (Wright et al., 2010b).

 

43


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Sulliden acquired the property and commenced exploration activity in 2002. Sulliden’s work was the most comprehensive on the project and is summarized in Table 6.2-2.

 

Table 6.2-2           Summary of Sulliden Exploration Activities

 

Year

 

Description of Activities

2002

 

Preliminary geophysical surveys (magnetometer and induced polarization), re-survey of previous drill collars

2003

 

27 diamond drill holes. Geologic mapping and trenching, soil survey, surface rock sampling, geophysical surveys (magnetometer and induced polarization), preliminary metallurgical testing, re-survey of previous drill collars

2004

 

56 diamond drill holes. Geological mapping, soil survey, trenching, surface rock sampling, adit sampling, magnetometer survey

2007

 

14 diamond drill holes on targets outside of the main mineralized area. Re-establishment of grid, magnetometer surveys, soil sampling

2009

 

12 diamond drill holes and 25 reverse circulation holes. Acquisition of digital 2m topography, location of previous hole collars, trenching, drill-hole re-sampling program, soil sampling (mobile metal ion survey), metallurgical test work, preliminary economic assessment

2010

 

79 diamond drill holes, 82 reverse circulation holes. Mapping, rock sampling, soil sampling, geophysical surveys (magnetometer, induced polarization, down-hole IP), metallurgical test work, geotechnical evaluation

2011

 

162 exploration diamond drill holes and 145 reverse circulation holes. Geotechnical drilling and evaluation .Mapping, rock sampling, soil sampling. Resource estimation.

2012

 

13 exploration diamond drill holes (not included in the 2012 resource estimate. Geotechnical drilling and evaluation. Mapping, rock sampling, soil sampling. Geophysical surveys (magnetometer, induced polarization, down-hole IP)

 

From their acquisition of Sulliden in August 2014 to their merger with Tahoe in April 2015, Rio Alto completed 234 reverse circulation (RC) drill holes and 12 diamond drill core holes totaling 24,522 meters in and around the Shahuindo deposit. The majority of these holes were drilled as infill holes to pre-existing drill holes, with some ‘step-out’ drilling to expand the resource. Rio Alto also drilled several holes for metallurgical, geotechnical and hydrological investigation.

 

6.3          Historical Mineral Resource and Mineral Reserve Estimates

 

6.3.1       Pre-NI 43-101 Mineral Resource Estimates

 

Two historic resource estimates that predate the implementation of NI 43-101 were prepared for the Shahuindo deposit. In 1996, Asarco completed an unclassified resource estimate within 0.3 g/t gold envelopes interpreted and estimated on cross section and using a specific gravity of 2.5 for the tonnage

 

44


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

estimate. Southern Peru completed a second resource estimate in 1998 using the same methodology and parameters as the Asarco estimate, with the addition of 98 drill holes completed by Southern Peru.

 

The 1996 and 1998 resource estimates are not NI 43-101 compliant as a Qualified Person has not done sufficient work to verify or classify these historical estimates. Tahoe does not consider these historical estimates relevant (other than historical relevance) to the current status of the project and has not attempted to evaluate the reliability of the estimates.

 

A summary of the pre-NI 43-101 historical resource estimates are shown in Table 6.3-1.

 

Table 6.3-1           Pre-NI 43-101 Mineral Resource Estimates

 

 

 

 

 

 

 

 

 

 

Au Grade

 

Year

 

 

Company

 

 

Tonnes

 

 

(g/t)

 

1996

 

 

Asarco

 

 

17,706,000

 

 

1.14

 

1998

 

 

Southern Peru

 

 

29,410,000

 

 

0.88

 

 

6.3.2       Prior NI 43-101 Mineral Resource Estimates

 

Five NI 43-101 resource estimates were previously completed on the Shahuindo deposit for Sulliden, as broadly summarized in Table 6.3-2.

 

Table 6.3-2           Prior NI 43-101 Mineral Resource Estimate Summary

 

 

 

 

 

 

 

 

 

 

Drill

 

 

 

 

 

Grade

 

Year

 

 

Company

 

 

Consultant

 

 

Holes

 

 

Method

 

 

Estimation

 

2004

 

 

Sulliden

 

 

Met-Chem

 

 

223

 

 

67 x 50m spaced sections

 

 

ID2

 

2005

 

 

Sulliden

 

 

Met-Chem

 

 

279

 

 

67 x 50m spaced sections

 

 

ID2

 

2009

 

 

Sulliden

 

 

AMEC

 

 

320

 

 

67 x 50m spaced sections

 

 

ID4

 

2011

 

 

Sulliden

 

 

Mine Development Associates

 

 

570

 

 

83 x 50m spaced sections; 8m plan interpretations

 

 

ID3

 

2012

 

 

Sulliden

 

 

Mine Development Associates

 

 

826

 

 

83 x 50m spaced sections; 8m plan interpretations

 

 

ID3

 

 

In 2004, Met-Chem Canada Inc. (Met-Chem) completed a resource estimate for the Shahuindo project based on Sulliden’s 2003 drilling program as well as data from Asarco and Southern Peru’s exploration programs. A total of 67 cross sections, spaced 50 meters apart, were used to interpret the deposit. A three-dimensional block model was constructed using block sizes of 10m north-south by 10m east-west by 5m elevation. The estimate used data from 223 drill holes spaced from 25m to 100m apart. Grade interpolation was done using inverse distance squared (ID2). Tonnage calculations were based on specific gravity values for each area included in the estimate: San Jose (2.21), Porphyry (1.86), East Zone

 

45


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

(2.38), and South Contact (2.40). The mineral resource estimate included in the 2004 Technical Report, Resources Estimation, Shahuindo Project, Peru (Saucier and Poulin, 2004) prepared by Met-Chem on behalf of Sulliden, is summarized in Table 6.3-3.

 

Table 6.3-3       2004 Mineral Resource Estimate

(Saucier and Poulin, 2004; cut-off grade 0.3 g/t Au)

 

 

 

 

 

 

 

Au Grade

 

 

Ag Grade

 

 

 

 

 

 

 

Classification

 

 

Tonnes

 

 

(g/t)

 

 

(g/t)

 

 

Au Ounces

 

 

Ag Ounces

 

Indicated

 

 

25,817,075

 

 

1.07

 

 

23.97

 

 

890,240

 

 

19,898,241

 

Inferred

 

 

8,569,150

 

 

0.92

 

 

22.54

 

 

253,836

 

 

6,210,567

 

 

Met-Chem updated their resource estimate in 2005 to include data from an additional 56 core holes drilled by Sulliden in 2004. The database for resource estimation included a total of 279 holes drilled by Asarco, Southern Peru, and Sulliden, spaced from 25m to 100m apart. Auriferous zones were delineated on 50m spaced cross sections using envelopes of 0.3 g/t Au. Block model parameters and grade interpolation method were the same as in Met-Chem’s 2004 estimate. Met-Chem used different search ellipsoids for each zone and sub-zone to reflect variations in data density and geometric configuration. The mineral resource estimate was included in the 2005 Technical Report, Resources Estimation, Shahuindo Project, Peru (Saucier and Buchanan, 2005) prepared by Met-Chem on behalf of Sulliden, and is summarized in Table 6.3-4.

 

Table 6.3-4       2005 Mineral Resource Estimate

(Saucier and Buchanan, 2005; cut-off grade 0.3 g/t Au)

 

 

 

 

 

 

 

Au Grade

 

 

Ag Grade

 

Classification

 

 

Tonnes

 

 

(g/t)

 

 

(g/t)

 

Indicated

 

 

38,009,500

 

 

0.95

 

 

22.99

 

Inferred

 

 

17,159,200

 

 

0.62

 

 

12.83

 

 

AMEC Americas Inc. (AMEC) updated Met-Chem’s mineral resource estimate in October and November 2009 as part of a Preliminary Assessment. This estimate was based on assays from 320 drill holes and used a block model with 10m by 10m by 5m blocks with the model dimensions oriented horizontally at azimuth 125°. The gold model was estimated using two passes of inverse anisotropic distance weighting to the fourth power (ID4), and a model for silver was estimated using the same composite search strategy and interpolation power as for the gold model. AMEC estimated resources within a pit shell using a cut-off grade of 0.23 g/t AuEq, with a marginal cut-off grade of 0.17 g/t AuEq, for oxide mineralization and a cut-off grade of 0.63 g/t AuEq, with a marginal cut-off grade of 0.57 g/t AuEq, for mixed and sulfide mineralization. Metal prices of $890 per ounce gold and $13.25 per ounce silver were used in the estimate with variable metallurgical recoveries ranging from 80% to 85% for gold and

 

46


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

15% to 70% for silver. The mineral resource estimate was included in the 2010 Technical Reports, Shahuindo Gold Project, Cajabamba Province, Peru, Technical Report on Preliminary Assessment (Wright et al., 2010a) and Shahuindo Gold Project, Cajabamba Province, Peru, Preliminary Assessment (Wright et al., 2010b), both prepared by AMEC on behalf of Sulliden; the results of which are summarized in Table 6.3-5.

 

Table 6.3-5       2009 Mineral Resource Estimate

(Wright et al., 2010a, 2010b)

 

 

 

 

Tonnes

 

 

Au Grade

 

 

Ag Grade

 

 

Au

 

 

Ag Ounces

 

Classification

 

 

(kt)

 

 

(g/t)

 

 

(g/t)

 

 

Ounces

 

 

(koz)

 

Indicated

 

 

51,800

 

 

0.63

 

 

17.9

 

 

1,050

 

 

29,800

 

Inferred

 

 

18,000

 

 

0.50

 

 

6.1

 

 

290

 

 

3,500

 

 

Mine Development Associates (MDA) completed an updated mineral resource estimate in 2011 which included only Indicated and Inferred Mineral Resources. There were no Measured Mineral Resources classified due to limited density and QA/QC data, uncertainty in localized metal grades due to moderate core recovery, and uncertainty with regards to localized metallurgical characteristics. Sulfide resources were restricted to Inferred classification due to limited metallurgical characterization and some spatial and geologic uncertainty in the model. The mineralized overburden was restricted to Inferred due to the uncertainties in grade continuity.

 

The stated resource was fully diluted to 8m by 8m by 4m blocks and tabulated on gold-equivalent grade cut-offs that MDA considered reasonable for deposits of this nature and for the expected mining conditions and methods. The AuEq grade was calculated using individual gold and silver grades of each block using a gold price of $1,200 per ounce and a silver price of $18.75 per ounce. For the oxide and mixed resource estimates, the AuEq grade calculation included a 5:1 difference in gold versus silver recovery in the proposed heap leach processing scenario. The formulas used to calculate the AuEq grade were:

 

Oxide and Mixed Material:

AuEq g/t = Au g/t + (Ag g/t x 0.003125)

 

 

Sulfide Material:

AuEq g/t = Au g/t + (Ag g/t x 0.015625)

 

 

The gold and silver resources reported by MDA in the 2011 Technical Report on the Shahuindo Gold Project, Cajabamba, Peru (Tietz and Kappes, 2011) are shown in Table 6.3-6. At the reported cut-off grades, approximately 58 percent of the total resource was classified as Indicated. Approximately 89 percent of the oxide and mixed resource considered for potential open pit heap leach mining was classified as Indicated.

 

47


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 6.3-6           2011 Mineral Resource Estimate

(Tietz and Kappes, 2011)

 

 

 

Cut-off

Tonnes

AuEq Grade

Au Grade

Ag Grade

Au Ounces

Ag Ounces

Classification

 

(g AuEq/t)

(000’s)

(g/t)

(g/t)

(g/t)

(000’s)

(000’s)

Indicated—Oxide

 

0.20

 

111,430

 

0.514

 

0.496

 

6.0

 

1,776

 

21,350

 

Indicated—Mixed

 

0.35

 

7,750

 

0.864

 

0.781

 

26.6

 

195

 

6,630

 

Total Indicated

 

Variable

 

119,180

 

0.537

 

0.515

 

7.3

 

1,971

 

27,980

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Inferred—Oxide

 

0.20

 

19,390

 

0.377

 

0.365

 

3.6

 

228

 

2,270

 

Inferred—Mixed

 

0.35

 

710

 

0.719

 

0.685

 

10.7

 

16

 

240

 

Inferred-Sulfide

 

0.50

 

42,730

 

1.278

 

0.868

 

26.3

 

1,192

 

36,070

 

Total Inferred

 

Variable

 

62,830

 

0.994

 

0.711

 

19.1

 

1,436

 

38,580

 

 

MDA updated their resource estimate in July 2012 based on additional drilling completed by Sulliden through May 2012. The 2012 Mineral Resource estimate by MDA followed the same modelling and estimation methodology as their 2011 estimate and assumed a gold price of $1300 per ounce and a silver price of $25 per ounce. For the oxide and mixed resource estimates, the AuEq grade calculation included a 5:1 difference in gold versus silver recovery in the proposed heap-leach processing scenario. Formulas used to calculate the AuEq grade were:

 

Oxide Material:

AuEq g/t = AuEq g/t + (Ag g/t x 0.003846)

 

 

Mixed Material:

AuEq g/t = AuEq g/t+ (Ag g/t x 0.006410)

 

 

Sulfide Material:

AuEq g/t = AuEq g/t+ (Ag g/t x 0.019231)

 

 

MDA did not constrain the resource within a potentially economic open pit shell due to the proximity of the deposit to the current topographic surface.

 

The gold and silver resources reported by MDA in the 2012 Technical Report on the Shahuindo Heap Leach Project, Cajabamba, Peru (Defilippi, et al., 2012) are shown in Table 6.3-7.

 

48


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 6.3-7           2012 Mineral Resource Estimate

(Defilippi, et. al., 2012)

 

 

 

Cut-off

Tonnes

AuEq Grade

Au Grade

Ag Grade

Au Ounces

Ag Ounces

Classification

 

(g/AuEq/t)

(000’s)

(g/t)

(g/t)

(g/t)

(000’s)

(000’s)

Measured-Oxide

 

0.20

 

40,500

 

0.619

 

0.588

 

8.1

 

766

 

10,530

 

Measured-Mixed

 

0.35

 

780

 

0.964

 

0.748

 

33.7

 

19

 

850

 

Total Measured

 

variable

 

41,280

 

0.626

 

0.591

 

8.6

 

785

 

11,380

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Indicated-Oxide

 

0.20

 

104,840

 

0.506

 

0.482

 

6.3

 

1,624

 

21,080

 

Indicated-Mixed

 

0.35

 

1,190

 

0.919

 

0.766

 

23.8

 

29

 

910

 

Total Indicated

 

variable

 

106,030

 

0.511

 

0.485

 

6.5

 

1,653

 

21,990

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Meas. + Ind.

 

variable

 

147,310

 

0.543

 

0.515

 

7.1

 

2,438

 

33,370

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Inferred-Oxide

 

0.20

 

9,570

 

0.419

 

0.402

 

4.3

 

124

 

1,330

 

Inferred-Mixed

 

0.35

 

20

 

0.762

 

0.684

 

12.2

 

 

10

 

Inferred-Sulfide

 

0.50

 

61,410

 

1.202

 

0.762

 

22.9

 

1,504

 

45,220

 

Total Inferred

 

variable

 

71,000

 

1.096

 

0.713

 

20.4

 

1,628

 

46,560

 

 

Tahoe has not attempted to validate the prior NI 43-101 Mineral Resource estimates and does not consider any of these estimates as the current Mineral Resources for the Shahuindo project.

 

6.3.3       Prior NI 43-101 Mineral Reserve Estimates

 

Mineral Reserve estimates for the Shahuindo project were reported in the 2012 Technical Report on the Shahuindo Heap Leach Project, Cajabamba, Peru prepared for Sulliden Gold Corporation, Ltd. by Kappes, Cassiday & Associates and Mine Development Associates (Defilippi et. al., 2012). The Technical Report had an effective date of September 26, 2012. No Minerals Reserves were published prior to the 2012 Mineral Reserve estimate.

 

MDA estimated the oxide and sulfide Mineral Reserves within a pit design based on a pit optimization of the Measured and Indicated mineral resources. The economic assumptions and other parameters used by MDA to undertake the pit optimization for the Shahuindo deposit are presented in Table 6.3-8 .

 

49


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 6.3-8           2012 Pit Optimization Parameters

(Defilippi, et. al ., 2012)

 

Pit Optimization Parameters 2012

 

Market Conditions

 

 

 

Gold price per ounce

 

$1,300

 

Silver price per ounce

 

$25

 

Payable proportion of gold and silver produced

 

99.50%

 

Minimum government royalty

 

NA

 

Mill Recovery

 

 

 

Gold recovery - Oxide

 

86%

 

Gold recovery - Mix

 

50

 

Silver recovery - Oxide

 

15%

 

Silver recovery - Mix

 

15%

 

Costs

 

 

 

Mining cost

 

1.99

 

Process Cost

 

4.45

 

Incremental Cost Ore

 

NA

 

TPD

 

10,000

 

TPY

 

3,650

 

G&A Cost

 

1.73

 

Gold Refining

 

5.50

 

Silver Refining

 

0.57

 

Mining Parameters

 

 

 

Slope Angle

 

27 - 41 degrees

 

 

The breakeven cut-off grades were calculated to be 0.23 g/t Au for oxide and 0.39 g/t Au for mixed material. The 2012 Mineral Reserve estimate is summarized in Table 6.3-9.

 

50


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 6.3-9           2012 Mineral Reserve Estimate

(Defilippi, et. al., 2012)

 

 

 

Proven

Probable

Proven and Probable

 

 

Oxide

Mixed

Total

Oxide

Mixed

Total

Oxide

Mixed

Total

Tonnes (000’s)

 

14,994

 

165

 

15,159

 

22,595

 

93

 

22,688

 

37,589

 

258

 

37,847

 

AuEq Grade (g/t)

 

0.91

 

0.72

 

0.91

 

0.81

 

0.89

 

0.81

 

0.85

 

0.78

 

0.85

 

Au Grade (g/t)

 

0.90

 

0.71

 

0.90

 

0.80

 

0.87

 

0.80

 

0.84

 

0.76

 

0.84

 

Ag Grade (g/t)

 

10.4

 

17.6

 

10.5

 

8.8

 

21.3

 

8.9

 

9.4

 

18.9

 

9.5

 

AuEq Ounces (000’s)

 

438

 

4

 

442

 

588

 

3

 

591

 

1,026

 

6

 

1,032

 

Au Ounces (000’s)

 

434

 

4

 

437

 

582

 

3

 

585

 

1,015

 

6

 

1,022

 

Ag Ounces (000’s)

 

5,008

 

93

 

5,102

 

6,396

 

64

 

6,459

 

11,404

 

157

 

11,561

 

 

6.4          Historical Production

 

The following information regarding historical production from the Shahuindo district is presented verbatim from Sulliden’s 2012 Technical Report on the Shahuindo Heap Leach Project (Defilippi et al, 2012).

 

The Algamarca mine, located on the southwest side of the Algamarca anticline, produced approximately 1.5 million tonnes grading 2.0% Cu, 680 g/t Ag, and “some gold” over a period of 45 years; the underground operations closed in 1989 (Saucier and Poulin, 2004; Wright et al., 2010a, 2010b). Compania Minera Algamarca SAC was the operator.

 

On the northeast limits of the Algamarca anticline, Algamarca mined 8,000 tonnes of gold-silver ore from three adits in the Cuerpo San José area in 1988 (Saucier and Poulin, 2004; Saucier and Buchanan, 2005; Wright et al., 2010a, citing Fletcher, 1997). Algamarca also exploited narrow gold-silver veins producing 12,000 tonnes at the Shahuindo mine from 1987 to 1989 (Saucier and Poulin, 2004; Saucier and Buchanan, 2005; Wright et al., 2010a, citing Fletcher, 1997). AMEC’s Technical Reports (Wright et al., 2010a, 2010b, citing Montoya et al., 1995) also reference production from underground stopes and a small open pit totaling 70,000 tonnes at an unknown grade from San José and Shahuindo in the 1980s or 1990s. Although this appears to be the same mining described in the Met-Chem reports (Saucier and Poulin, 2004; Saucier and Buchanan, 2005), Tahoe cannot account for the difference in tonnages.

 

Small scale underground mining is currently being undertaken by informal miners in the Algamarca anticline area, about 1,000 meters west of Tahoe’s planned open pit operations.

 

51


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

7.0          GEOLOGICAL SETTING AND MINERALIZATION

 

7.1          Regional Geology

 

The Shahuindo Deposit is located on the eastern flank of the Andean Western Cordillera in northern Peru, approximately 35 kilometers north-northwest of Tahoe’s La Arena mine. The area is underlain by sediments of the Mesozoic West Peruvian Basin which were folded and faulted during the Cenozoic deformation.

 

The regional stratigraphy is dominated by the folded Upper Jurassic Chicama Formation to the Lower to Middle Cretaceous Goyllarisquizga Group, which are mainly siliciclastic sediments, with younger Lower-to Upper-Cretaceous carbonate sediments occupying the cores of synclines. The regional stratigraphical column is summarized in Table 7.1-1; a plan map and example cross section of the regional geology are illustrated in Figure 7.1-1 and Figure 7.1-2, respectively.

 

Table 7.1-1           Shahuindo Regional Stratigraphic Column

 

Era

 

System

 

Series

 

Group

 

Formation

 

Gold
Mineralization

 

Cenozoic

 

Quaternary

 

Recent

 

 

 

Alluvial, Fluvial

 

 

 

 

 

Pleistocene

 

 

 

Glacial, Lacustrine

 

 

 

 

Neogene

 

 

 

Calipuy

 

 

 

AC

 

 

Paleogene

 

 

Mesozoic

 

Cretaceous

 

Upper

 

 

 

Yumagual

 

 

 

 

 

Lower

 

 

 

Pariatambo

 

 

 

 

 

 

 

Chulec

 

 

 

 

 

 

 

Inca

 

 

 

 

 

 

Goyllarisquizga

 

Farrat

 

SHA

 

 

 

 

 

Carhuaz

 

SHA

 

 

 

 

 

Santa

 

 

 

 

 

 

 

Chimu

 

AC, ET, LA, LV, SR

 

 

 

 

 

Oyón

 

 

 

 

Jurassic

 

Upper

 

 

 

Chicama

 

 

 

 

after Reyes R. L, 1980 and Navarro et. al., 2010

 

gold occurrences: AC: Lagunas Norte, ET: EI Toro, LA: La Arena, LV: La Virgen, SHA: Shahuindo, SR: Santa Rosa

 

From oldest to youngest, the regional stratigraphy is described as follows:

 

Paleozoic (and Precambrian): Basement rocks to the east of Shahuindo along the River Marañon and the Eastern Cordillera. They are not exposed at Shahuindo or in the immediately surrounding area.

 

52


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Mesozoic: The oldest outcropping rocks in the region belong to the Upper Jurassic Chicama Formation and consist of soft, laminated marine black shales with thin sandstone intercalations.

 

The Chimu Formation constitutes the principal host rock for gold mineralization at Lagunas Norte, El Toro, La Arena, La Virgin and Santa Rosa deposits and the Algamarca vein system. The upper member of the Goyllarisquisga Group consists of the Santa, Carhuaz and Farrat Formations. These formations consist of generally finer-grained siliciclastic units with minor interbedded carbonates in the lower portion and thick beds of sandstone in the upper portion of the formation. The Carhuaz and Farrat formations are the hosts for gold and silver mineralization at Shahuindo.

 

Overlying the Goyllarisquisga Group sediments are Lower Cretaceous shallow marine carbonates of the Inca, Chulec and Pariatambo formations and the Upper Cretaceous Yumagual Formation.

 

The Mesozoic sediments were folded and faulted towards the end of the Cretaceous by the early stages of the developing Andean Orogeny.

 

Cenozoic: The Calipuy Group cordilleran arc volcanics unconformably overly the folded and faulted Mesozoic strata south-west of Shahuindo. These sub-aerial volcanics are associated with Upper Miocene sub-volcanic intrusive bodies of andesitic to dacitic composition. The Calipuy volcanics are mainly tuffs interbedded with andesitic lavas with agglomerate horizons at the base at the base formation.

 

Cenozoic intrusive rocks including andesite, dacite and quartz—feldspar porphyries that intruded as isolated stocks into the Mesozoic sedimentary sequence. The age of these intrusions vary from c.a. 16 to 26 Ma. (Bussey and Nelson 2011). One of these intrusions is interpreted to be the source of the gold and silver mineralization at Shahuindo.

 

The main structural features of the region are associated with the Jurassic-Cretaceous sedimentary sequence and consist of a series of folds, reverse faults and over-thrusts trending generally NW-SE (Figure 7.1-2). Individual folds range up to 80 kilometers in length and 5 kilometers in width, and display various degrees of deformation depending on the relative competency of the various stratigraphic levels. The highly competent sections of the Chimu Formation, for example, form structurally complex cores to the main anticlines, which have resisted erosion better than the enclosing strata.

 

The region is particularly well-endowed with mines and mineral occurrences varying from low-to-high sulfidation systems and from porphyry through polymetallic to epithermal deposits. Currently operating mines in the area include Quiruvilca polymetallic Cu-Zn-Pb-Ag mine and the La Arena, Lagunas Norte, La Virgen and Santa Rosa high-sulfidation epithermal gold mines, with many other gold-silver prospects in the region.

 

53


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.1-1         Shahuindo Regional Geology

 

54


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.1-2         Shahuindo Regional Cross Section

 

Mesozoic sediments affected by folds and reverse faults. Miocene intrusives emplaced in the fold axes.

 

55


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

7.2          Project Geology

 

The Shahuindo Project is located within a regional fold and thrust belt of predominantly Mesozoic sedimentary rocks. Sedimentary rocks in the project area have been intruded by at least three felsic stocks which tend to be located along faults and cores of anticlinal structures as shown previously in Figure 7.1-2.

 

Sedimentary rocks across the Shahuindo Project area consist of a lower, shallow marine-to-deltaic siliciclastic sequence and an upper sequence of finer grained siliciclastic units with minor interbedded carbonates in the lower portion and thick beds of sandstone the upper portion, all of Lower Cretaceous age.

 

The oldest rocks exposed at the bottom of the valleys and in the cores of anticlines are thinly bedded and laminated mudstones, minor siltstones and fine grained sandstones with occasional coal seams of the basal Lower Cretaceous Chicama Formation.

 

Overlying the Chicama Formation is the Goyllarisquizga Group which, from oldest to youngest, is comprised of the Chimu Formation, Santa Formation, Carhuaz Formation, and Farrat Formation.

 

Overlying the Chimu Formation is the Santa Formation which consists of mudstone with intercalations of limestone. It is exposed on the flanks of the Algamarca anticline. Overlying the Santa Formation is the Carhuaz Formation, consisting of interbedded sandstone, siltstone, and mudstone, with many sandstones displaying cross bedding and amalgamated wedge-shaped sandstone beds. The Farrat Formation consists of cliff-forming siliciclastic strata dominated by sandstone. The Farrat Formation is the dominant host of gold and silver mineralization in the northern part of the Shahuindo deposit. The Carhuaz and Farrat formations are the principal hosts for gold and silver mineralization in the central and southern portions of the deposit, as illustrated in Figure 7.2-2.

 

56


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.2-1         Shahuindo Local Geology

 

57


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.2-2         Local Stratigraphic Column for the Carhuaz/Farrat Formations

 

58


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Multiple intrusions of dacitic and andesitic feldspar stocks have intruded the Cretaceous sedimentary sequence at Shahuindo (Figure 7.2-3 and Figure 7.2-4). Intrusions recognized by previous mapping in the Shahuindo area include rocks described as andesite, dacite porphyry, and intrusion breccia. There is an opportunity to improve the geologic understanding of the district by carefully mapping the distribution of these intrusive phases and separating lithology from alteration.

 

The five non-breccia intrusive phases were recognized as diorite porphyry (known as “andesite” in the district), dacite porphyry, fine-grained dacite porphyry, quartz diorite porphyry, and foliated quartz diorite porphyry. The distribution of the five intrusion types is based on field observations. The three intrusive breccia phases are heterolithic breccia with biotite diorite matrix, heterolithic breccia with fine-grained dacite matrix, and heterolithic megabreccia with foliated quartz-biotite dacite matrix.

 

Diorite porphyry (andesite) was observed in the southeast part of the main Shahuindo corridor and is inferred to be present on the northeast side of the Algamarca anticline and east of the current resource outline. The mapped pattern of the intrusion indicates emplacement mostly as sills in the Goyllarisquizga Group units. It is characterized by large (8mm diameter) biotite phenocrysts, a lack of quartz, and no evidence of hydrothermal alteration where seen in the field, although it is deeply weathered. An isotopic age determination is reported to have been made (thought to be zircon U-Pb) on this intrusion and yielded an age of ~26 Ma. (Bussey and Nelson 2011).

 

The dacite porphyry is characterized by one cm bipyramidal quartz phenocrysts, with biotite and plagioclase phenocrysts in an aphanitic groundmass. It is the most widespread intrusion in the Shahuindo district and is argillically altered wherever observed. The mapped distribution indicates that much of the dacite porphyry was emplaced as sills concordant to bedding in the Goyllarisquizga Group. Nonetheless, the principal intrusion along the main Shahuindo corridor is a composite dike-like body with relatively steep discordant contacts, as is the dacite porphyry intrusion on the southwest limb of the Algamarca anticline (see Figure 7.2-6). The large dacite porphyry body in the north part of the main corridor splays to the southeast into a series of dikes that narrow and disappear beneath cover in the central area of the Shahuindo deposit. An isotopic age determination (zircon U-Pb) on this intrusion yielded an age of ~16 Ma (Bussey and Nelson 2011).

 

Three intrusive breccia phases are recognized on the property and include; (1) heterolithic biotite diorite breccia, (2) heterolithic fine-grained dacite breccia, and (3) heterolithic megabreccia (Figure 7.2-7).

 

Heterolithic fine-grained dacite breccia was recognized during mapping in the main Shahuindo corridor. It occurs as narrow dike-like bodies, no more than three meters in width, with rounded to subangular clasts up to 10 cm in diameter of sandstone, siltstone, dacite porphyry, and rare shale, in a matrix of

 

59


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

fine-grained lithic clasts and clay with 1-3mm quartz, biotite, and plagioclase crystals. Most of the locations are in the north-western area of the resource, with two sites in the central area of the resource. This breccia also was noted in drill core from the central zone where heterolithic fine-grained dacite breccia contains fragments of sedimentary rock mineralized with pyrite, sphalerite, quartz, and white clay, indicating that the breccia is associated with the mineralization.

 

60


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.2-3                           Multiphase Intrusion Crosscutting Sedimentary Rocks (Section E1100)

 

61


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.2-4                           Multiphase Intrusion Crosscutting the Sedimentary Rocks (Section X-X’)

 

62


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.2-5         Sedimentological Features for Determining Stratigraphic Sequencing

 

 

A - Tangential (at base) cross bedding

 

 

 

B - Load casts or channels on base of sandstone bed

 

 

 

C-D - Channel in overturned fold limb

 

 

 

E - Load casts

 

 

63


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.2-6                           Intrusive Relationships

 

Andesite (red pattern) intruding core of a fold and cut by altered dacite dike (yellow outline) in the northern Shahuindo area

 

64


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.2-7                           Monolithic-Clast Breccia

 

 

A - Sub-angular quartzite-clast breccia, matrix supported

 

 

 

B - Sedimentary-clast breccia cutting dacite

 

 

 

C - Pebble dike (sill) with rounded quartzite clasts

 

 

 

D - Sub-rounded sandstone-clast breccia

 

 

7.3                               Mineralization

 

Mineralization at Shahuindo has been identified over an area approximately 3.7 kilometers southeast to northwest and 0.5 kilometer southwest to northeast. Oxidation of mineralization extends to a depth of 150m below surface. Sulfide mineralization has been identified by surface drilling to 700m depth.

 

Mineralization at Shahuindo can best be described as an intermediate-sulfidation epithermal system, though high-sulfidation mineralization occurs at depth and in the core of hydrothermal breccias. The high-sulfidation mineralization was pervasively overprinted by intermediate-sulfidation mineralization (pyrite, galena, sphalerite, Ag sulfosalts), which occurs at shallow levels and in ‘feeder structures’. Mineralization occurs on fracture surfaces, in breccia matrix, and as disseminations within the sediment packages.

 

65


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The host rocks at Shahuindo are the Carhuaz and Farat sedimentary formations which are folded and locally fault offset, and cut by porphyritic dikes and stocks. Sandstone tends to be a better host to higher grades of gold and silver compared to siltstone. Brecciated structures with polylithic fragments consist of wall rock clasts, locally clasts of residual quartz (the vuggy texture indicating rock dissolution), as well as juvenile clasts of dike rock, the latter evidence of a syn-hydrothermal timing of dike emplacement.

 

In the oxide facies, which is interpreted to be the result of weathering processes, gold and silver are associated with the presence of jarosite and hematite. In the sulfide facies, gold is typically extremely fine grained; the mineral species has not been identified. Fine-grained pyrite forms a close association with gold mineralization and occurs as disseminations, veinlets, and semi-massive replacement bodies.

 

Tetrahedrite, sphalerite, galena, arsenopyrite, stibnite, and covellite have also been reported as minute blebs adhering to zoned pyrite. Although native silver has been identified at San José and in the historic Shahuindo mine, silver is usually found in sulfosalts at Shahuindo.

 

7.4                               Structural Geology

 

The Shahuindo district occurs within the Eocene fold-thrust belt of northern Peru (Montoya et. al., 1995). Although most structural elements of the fold-thrust belt formed during the Incaic II orogeny at ~43 Ma, geochronological data and field relationships suggest that mineralization commenced around16 Ma (Miocene). The Shahuindo district occurs along a localized belt of intrusive rocks that is mostly parallel to the dominant structural fabric of the fold-thrust belt. Pre-mineralization magmatism at ~26 Ma produced quartz diorite porphyry intrusions (mapped as andesite) and mineralization appears to have formed in association with dacitic to rhyolitic magmatism and associated brecciation, probably related to high-energy diatreme activity.

 

Although fold-thrust belt structures developed approximately 27 million years prior to mineralization, fold-thrust belt structural elements controlled much of the mineralization. NW-trending Miocene dikes, diatremes, and mineralized breccias parallel the regional strike of fold-thrust structures and were probably emplaced along reactivated fold-thrust belt structural elements and/or basement structures.

 

Field evidence indicates that both structure and lithology exert important controls on the location, shape, and orientation of mineralized rock. Important structural elements include fold limbs and fold axial surfaces, fold-related fractures, faults and related extension fractures, breccia dikes and irregular bodies, and igneous intrusive contacts. These structural elements are described below and their geometry and spatial relation to mineralized zones have been used to construct the structural model for the Shahuindo district.

 

66


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The principal zone of mineralization in the Shahuindo district occurs in a belt between two large-amplitude regional-scale folds, the Algamarca anticline and the San Jose Anticline (Figure 7.4-1). The Algamarca anticline has amplitude of at least 400m and is upright and symmetrical. The San Jose fold has an amplitude of at least 300m and is an asymmetric, overturned, northeast-vergent fold with a low-angle dip (15°-20°) axial surface (i.e., resembling a recumbent style fold).

 

The Chimú-cored Algamarca anticline is interpreted as either an allochthonous fault-bend fold in the hanging wall of a duplex roof thrust, or as an anticlinal stack of folded strata and folded thrust faults above the postulated sub-horizontal roof thrust below the base of the Algamarca anticline exposure. Analysis of old mine workings in the Algamarca mine suggest that the southern limb of the Algamarca anticline continues to at least the 2,690m elevation. However, geometric features of the Algamarca anticline (symmetrical, upright, box shape) indicate that it is probably a detachment fold, not a fault-bend fold.

 

The strain in fold-thrusts belts is typically partitioned or compartmentalized along strike by transverse accommodation faults (also known as tear faults). The existence of tear faults in the Shahuindo district was noted by Hodder (2010b) and Hodder et al. (2010a); such faults include the Choloque, La Cruz, and Los Alisos faults. Although these faults likely exist (the evidence is mostly from topographic lineament mapping), they display a combination of kinematics and strong displacement gradients. Although not well-exposed at surface, the faults are thought to be steeply dipping. The La Cruz Fault, although it terminates the Algamarca anticline where it accommodated much vertical displacement, cannot be traced north of the main Shahuindo corridor and terminates before reaching the Pampa de Arena anticline. The Los Alisos Fault, inferred to be present based on a topographic lineament and alignment of intrusive bodies, shows no displacement of units and does not correlate with transverse veins in the Algamarca district. However, the Los Alisos Fault appears to terminate the main Shahuindo mineralized corridor to the northwest.

 

67


Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.4-1                           Combined Structure and Mineralization Map - Shahuindo Project

 

68


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

7.5                               Hydrothermal Alteration

 

Visual evidence of mineralization in oxidized and weathered rocks at surface includes the presence of voids and crystal molds after pyrite and other sulfides, iron oxide in boxwork textures after sulfides, limonitic or gossanous coatings, fine-grained euhedral quartz druse as veinlets and vugs in brecciated zones, crystalline white clay or sericite, and alunite, jarosite, or scorodite in veins and veinlets.

 

Studies of hydrothermal clay-like alteration minerals have also been conducted on the project. A petrographic description followed by Terraspec® survey was completed by Rio Alto geologists on 50% of the core and chips samples from the project. This study defined deep occurrences of dickite, pyrophyllite, and alunite, particularly along fractures and dikes that may define feeder zones and shallow outflow of an initially reactive fluid. There is a broad zone of sericite (illite?) at shallower depth that may be associated with a white mica-stable mineralizing fluid (Hedenquist, et. al., 2015).

 

Trending from southeast to northwest through the deposit, there is an alteration vector of the following assemblages in the sediment package: silica-pyrophyllite, silica-paragonite, and illite-muscovite-paragonite. These assemblages are indicative of a general trend of lesser temperature and higher pH from southeast to northwest. A trend of lesser temperature and higher pH from the core of mineralization outward exists in the southeast part of the deposit.

 

Jarosite forms in acidic environments usually due to oxidation of pyrite-rich rocks in the near surface environment (Figure 7.5-1). Mesozoic sediments are affected by folds and reverse faults with Miocene intrusives emplaced in the fold axes.

 

At Shahuindo, jarosite occurs in veins and as breccia matrix. Because jarosite is precipitated from iron-rich acidic surface water, it often forms some distance away from the weathering pyrite-rich rock from which it is derived. Nonetheless, its presence in outcrop is a good indicator that pyrite-rich rocks are or were nearby.

 

Scorodite (iron-arsenic oxide) often forms with jarosite during weathering of rocks that contained arsenic-bearing sulfides in addition to significant pyrite, and is an important mineral to map in the field. Scorodite was noted at two sites in the eastern area of the resource. Its presence is an indication that arsenic-bearing sulfides were oxidized along with pyrite.

 

Figure 7.5-2 and Figure 7.5-3 are cross sections depicting the distribution of hydrothermal alteration intensities in the Shahuindo deposit.

 

69


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.5-1                           Jarosite in Outcrop.

 

A - Brown jarosite veins in sandstone (eastern Shahuindo)

 

B - Jarosite and grey-green scorodite (arrows) in breccia matrix exposed in road cut (central Shahuindo)

 

70


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.5-2                           Hydrothermal Alteration Section – Shahuindo Project (Section E1100)

 

71


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 7.5-3                           Hydrothermal Alteration Section – Shahuindo Project (Section XX’)

 

72


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

7.6                               Geometallurgy

 

Metallurgical recovery of gold from the Shahuindo deposit is affected by lithology (discussed in detail in Section 13 — Mineral Processing and Metallurgical Testing). Five primary geometallurgical domains (with additional subdomains) have been determined based on the relationship between lithology and grain size and gold recovery. The domains used for geometallurgical classification are:

 

·                  Sandstone

 

·                          low fines content (<5% fines)

·                          high fines content (5%-20% fines)

 

·                  Siltstone

 

·                  Breccia

 

·                          clast-supported (<20% fines)

·                          matrix-supported (>20% fines)

 

·                  Mixed sandstone and siltstone

 

·                  Colluvium

 

There is a high degree of lateral and vertical lithologic variability at Shahuindo, particularly in the northern half of the deposit. Modelling the distribution and occurrence of lithologic units / geometallurgical domains is critical to mine planning. Additional detailed study and modelling of lithology, geochemistry and alteration from drill core and open pit mapping is needed to refine the distribution of lithologic units and create a more comprehensive geometallurgical domain model for planning purposes.

 

73


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

8.0                               DEPOSIT TYPES

 

8.1                               Deposit Types

 

The Shahuindo deposit formed in a predominantly intermediate-sulfidation epithermal system (Figure 8.1-1) of probable Miocene age. Distinguishing characteristics of an intermediate-sulfidation environment include mineral assemblages indicating a sulfidation state between those of high and low sulfidation types, relatively high total sulfide content of five to 10 percent in the sulfide environment, presence of silver sulfosalts, and association with andesitic to dacitic volcanics. Magmatic associated fluids are implied. There is no evidence of adularia at Shahuindo, thus ruling out a low-sulfidation environment. There are some observances of enargite at depth, suggesting a mixed intermediate- to high-sulfidation system.

 

Epithermal deposits form as high-temperature mineralizing fluids rise along structural pathways and deposit quartz and precious and base-metal minerals in open spaces in response to boiling, which is usually coincident to a release of pressure within the hydrothermal system. This quartz and metal deposition, followed by resealing of the system, is repeated over the life of the hydrothermal system resulting in crosscutting and overprinted breccia and vein textures. Typically, the larger and higher grade deposits are associated with long-lived hydrothermal systems marked by complex overlapping veins.

 

These deposits are strongly structurally controlled. Mineralizing fluids are directed along structural pathways with high grade ‘ore shoots’ typically concentrated in open dilatant zones. These dilatant zones commonly form where inflections occur vertically and laterally along the deposit. Metal deposition and zoning in epithermal deposits are related to the level of boiling. Typically, precious metals deposit at or near the boiling level while base metals precipitate below. Boiling may occur at different levels as the hydrothermal system evolves producing an overprint of various episodes.

 

74


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 8.1-1                           Spatial Relationship of Intermediate Sulfidation Deposits

(after Corbett, 2002)

 

75


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

9.0                               EXPLORATION

 

9.1                               Exploration Strategy

 

The exploration strategy at Shahuindo utilizes relatively standard exploration techniques that include detailed surface geologic mapping, surface geochemical sampling, and drill testing. The most effective exploration tool at Shahuindo has been core and RC drilling, the results of which are discussed in Section 10 — Drilling. Samples have also been collected from underground workings in the northern portion of the project area which has seen exploitation by informal miners.

 

Several targets proximal to the Shahuindo deposit have been identified in the district from geophysical surveys, prior informal mining operations, surface mapping and geochemical sampling, and drilling. Information regarding specific exploration targets is presented in Section 24.2 — Exploration Potential.

 

The focus on the 2014-2015 work plan was to infill drill the existing resource/reserve; hence only a small amount of exploration work has been carried out on other exploration targets outside the planned pit limits during this period.

 

9.2                               Geophysical Surveys

 

Val Dór Geofisica Peru conducted magnetic and induced polarization (IP) geophysical surveys between 2002 and 2012 on behalf of the prior owners of Shahuindo. There have been no additional geophysical surveys completed on the concession since the acquisition of the deposit by Rio Alto in 2014.

 

The magnetic surveys covered most of the concession and comprise about 550 line-kilometers of data. Gaps in the image are due to areas that could not be accessed. The surveys clearly suggest a major intrusive body, as indicated by a prominent magnetic high, extends from the center of the Shahuindo deposit to the project boundary in the northwestern area of the concession package. Another magnetic anomaly that may reflect an additional porphyry body is apparent to the northwest of Shahuindo (Azules exploration target). Results of the magnetic surveys are illustrated in Figure 9.2-1.

 

Over 160 line-kilometers of various pole-dipole IP surveys were conducted over prospective areas on the Shahuindo concession The IP surveys highlighted anomalies which have subsequently been successfully drill tested since 2002 on the deposit. There are large tracts of ground that have not been traversed with IP surveys and present some longer term exploration opportunities (Figure 9.2-2).

 

76


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 9.2-1                           Shahuindo – Magnetic Survey Results

 

77


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 9.2-2                           Shahuindo – IP Survey Results

 

78


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

9.3                               Geochemistry

 

Mineralization outcrops or subcrops in numerous locations on the concession. A large database of soil, channel sample, and rock sampling results has been accumulated since 2002. Geochemistry is generally a reliable tool to assist in the identification and evaluation of precious and base metal mineralization potential and for the generation of drill targets. A compilation of rock chip gold geochemistry results are displayed in Figure 9.3-1.

 

 

Figure 9.3-1                           Shahuindo — Rock Geochemistry

 

79


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The Shahuindo surface sample database contains a total of 12,070 rock samples and 11,680 soil samples. Surface samples consist of trench, grab and rock chip samples. Trench samples were generally excavated to bedrock, or to a maximum depth of 1.8 meters. Trenches were sampled either horizontally or vertically, depending on trench geology. Horizontal channel samples were typically located at the base of the trench wall. Where bedding was horizontal, vertical channel samples were taken from the top to the base of the wall. Sample lengths are variable depending on geology.

 

Most of the accessible underground adits located on the concession were sampled prior to 2012. Where possible, samples were taken from the adit portal and along the accessible portion of the tunnel. Most samples were vertical and non-continuous. Approximately 140 small adits were sampled.

 

Detailed soil sampling completed by Sulliden between 2003 and 2012 revealed a series of continuous, parallel gold anomalies in the central and northern areas of the concession. Base metal anomalies were found to the northwest and to the southeast of the concession.

 

Geologic mapping and rock chip sampling programs are ongoing, with an emphasis of delineating mineralized sandstone to assist in drill targeting for ROM material or material to be used for blending with siltstone on the leach pad.

 

No analytical data from surface rock samples or soil samples were used in the mineral resource estimate.

 

80


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

10.0                        DRILLING

 

10.1                        Introduction

 

A total of 1,039 holes drilled by Atimmsa, Asarco, Southern Peru, Sulliden and Tahoe have been used to model and estimate the resource at Shahuindo. Reverse circulation (RC) (604 holes) and diamond drilling (435 holes) have both been carried out on the property. The cut-off date for drill data inclusion in the resource model is 15 April 2015. Table 10.1-1 is a summary of the drilling included in the resource model.

 

Table 10.1-1                         Shahuindo Drilling Summary

 

 

 

Diamond Core

Reverse Circulation

Total Drill

Total

Company

Year

Number

Meters

Number

Meters

Holes

Meters

Attimsa

 

1992

 

 

 

11

 

744

 

11

 

744

 

Asarco

 

1994-1996

 

55

 

8,105

 

31

 

3,681

 

86

 

11,786

 

Southern Peru

 

1997-1998

 

16

 

1,818

 

80

 

9,755

 

96

 

11,573

 

Sulliden

 

2003-2012

 

352

 

72,913

 

248

 

42,477

 

600

 

115,389

 

Rio Alto

 

2014-2015

 

12

 

1,258

 

234

 

23,264

 

246

 

24,522

 

Total

 

1992-2015

 

435

 

84,094

 

604

 

79,921

 

1,039

 

164,015

 

 

The majority of the RC drilling completed by Rio Alto in 2014 and 2015 was within the current resource. The database also includes twelve diamond core holes that were drilled for geotechnical purposes and subsequently sampled for analyses. The majority of the drilling in the oxide domain within the resource is on a nominal 25m x 25m spacing due to the extensive RC infill programs conducted in 2014 and 2015. A drill hole location map showing all holes used for the resource estimate is shown in Figure 10.1-1.

 

Drill holes in the resource area have been collared at azimuths around 35 degrees or 215 degrees to intersect the main structural trend of the deposit at a high angle. In some areas of the resource, and in other exploration targets away from the main mineralized zone, holes are drilled at a variety of azimuths to attempt to intersect local structural features at high angles or due to topographic restrictions on drill site locations.

 

The Company notes that there are minor differences in the number of drill holes and meters drilled from programs conducted prior to and including 2012 when comparing the database acquired from Rio Alto in 2015 to the drill totals reported in Sulliden’s 2012 technical report. These differences are not material to the project.

 

81


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 10.1-1                    Shahuindo Drill Hole Location Map

 

82


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Upon its acquisition of Rio Alto in April 2015, Tahoe has continued drilling diamond core and RC for infill, step-out, geotechnical, hydrology, and condemnation purposes.

 

10.2                        Drilling Methods and Equipment

 

The following descriptions of drilling equipment and procedures for exploration programs prior to Rio Alto’s 2014 drill program are summarized from Defilippi, et. al. (2012).

 

Tahoe has no information regarding Atimmsa’s drill contractor or the type of equipment used in the 1992 drill campaign in which they drilled 11 RC holes (744 meters). Review of the data on cross section and comparing it to Sulliden’s and Tahoe’s proximal drill data suggests the Atimmsa data to be sufficiently reliable for inclusion in the resource model database.

 

Asarco retained Geotec S.A. (Geotec) for their diamond drill programs in 1994 through 1996. Geotec used a Longyear wireline diamond drill, drilling HQ (63.5 millimeter core diameter) and NQ (47.6 millimeter) core. Core recovery was reported to be consistently better than 90% (Fletcher, 1997, cited by Saucier and Poulin, 2004). Asarco’s RC drill holes were generally drilled dry with good sample recovery (Saucier and Poulin, 2004); Tahoe has no information on Asarco’s RC drill contractor or the type of drill rig used.

 

Southern Peru used Andes Drilling and Podiur as their RC and diamond drill contractors, respectively, in 1997 and 1998. Southern Peru drilled HQ core in 1997, reducing to NQ in 1998. Tahoe has no information on the type of drill rigs used.

 

Forage Orbit S.A. drilled for Sulliden in 2003 and 2004, using a skid-mounted drill rig. In 2007, Sulliden’s drill contractor was MDH Bradley SAC (MDH Bradley), who employed a skid-mounted rig. From 2009 to the end of 2011, MDH Bradley and AK Drilling International (AK Drilling) were the drill contractors for the Shahuindo Project. MDH Bradley conducted all the diamond drilling, using a variety of skid and track-mounted electric-hydraulic diamond drill rigs (mostly LF70 rigs). AK Drilling used a Foremost Prospector 750 Buggy with auxiliary booster and compressor to complete the RC drill program.

 

Sulliden’s core holes were generally drilled using HQ tools. However due to ground conditions, some 2003 and 2004 holes were drilled using NQ tools. In 2010 and 2011, limited PQ drilling (85.5 millimeters) was done for metallurgical and twinning purposes.

 

Sulliden used a variety of RC hammers that ranged from 4½ inches to 5½ inches in diameter. Dry samples were preferred over wet samples, and generally a frontal hammer was used to retrieve dry samples. Conventional hammers were used for wet samples; a tricone was sometimes necessary when ground condition were very poor.

 

83


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Operators prior to Sulliden placed core into corrugated plastic core trays with depth markers to denote each drill run. Sulliden’s HQ and NQ core was placed into wooden boxes with wooden blocks to denote each drill run. Between 2007 and 2012, a liner was fitted into the wooden boxes to help retain all the material produced by drilling. PQ core was placed into plastic boxes with plastic separators. Boxes contain either three meters of HQ core, four meters of NQ core, or two meters of PQ core. Core boxes were securely sealed and delivered once a day, by truck, to core-logging facilities at the exploration camp in San José.

 

Asarco and Southern Peru bagged RC cuttings in the field, and a reference chip tray was collected, at two meter intervals. Sulliden’s RC cuttings were sampled on 1.5 meter intervals. Thirty percent of the cuttings of each individual sample were bagged and sent to the laboratory for analyses. The remaining 70 percent of the sample cuttings were bagged and kept as rejects. Two reference chip trays, one with a complete sample and the other with a sieved sample (one millimeter mesh), were collected at the same 1.5 meter interval.

 

Rio Alto’s 2014-2015 drill program was executed by Explomin del Peru (RC and diamond core). Diamond core was generally HQ and to a lesser degree NQ size, depending upon ground conditions. Average core recovery was 95%. Reverse circulation drilling utilized 5¼-inch (133mm) diameter face sample hammers and achieved an average recovery of 90%. Rio Alto followed the same RC and core sampling and handling procedures as Sulliden.

 

10.3                        Collar Surveys

 

Drill collar northing and easting coordinates are located in relation to the UTM WGS84 coordinate grid. In 2002 and 2003, Val d’Or Geofisica del Peru (VDG) established the exploration coordinate grid with a differential GPS with stations located on the cross-lines at 50 meter intervals. In addition to establishing the exploration grid, VDG also relocated and resurveyed drill-collar locations from historic campaigns. Upon completion of Sulliden’s 2003 through August 2010 drilling, drill hole collars were surveyed by VDG using differential GPS. In 2009, Horizon South America S.A.C (Horizon) was contracted by Sulliden to perform an aerial survey of the Shahuindo property and create a two meter contour map. Beginning in September 2010 and through 2015, drill hole collars were located using a total station utilizing the aerial survey points established by Horizon as control points.

 

The collar elevations of all pre-2009 drill holes were back-interpolated (i.e., “pressed”) to the two meter contour topographic map created by Horizon in 2009.

 

84


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

10.4                        Downhole Surveys

 

Downhole survey data are available for 589 core and RC holes, corresponding to approximately 56 percent of the number of drill holes in the database used for the resource estimate.

 

Survey data are not available for the 193 drill holes completed by Attimsa, Asarco, and Southern Peru between 1992 and 1998 and for 53 of the 600 drill holes completed by Sulliden from 2003 to 2012. The unsurveyed drill holes are relatively shallow (average depth of about 125 meters), and therefore any downhole deviation is considered minor and not likely to cause any appreciable uncertainty in the position of data points along the drill hole trace.

 

Prior to 2009, Sulliden’s downhole surveys consisted mostly of acid tests with minor use of Tropari and Sperry Sun single-shot tools. From 2009 to 2012, downhole surveying was primarily done using Flex-it multi-shot survey tools, with lesser use of Reflex Easy-Shot and Maxibore II tools. Downhole survey readings were taken at approximately 65 meter drill depth intervals, with the first reading within 20 meters of the collar. Sulliden’s core holes generally have two to three downhole survey readings per hole with the bottom readings usually within 50 meters of the final drill depth. The depth intervals between survey readings are variable, depending on the total depth of the core hole; the maximum interval between survey readings is 100 meters. Nearly all of the Sulliden RC holes have two survey readings at regular 15 meters and 75 meters drill depths. The RC holes have an average drill depth of 180 meters with a maximum depth of 309 meters so, for most RC holes, the bottom 100 to 200 meters were unsurveyed.

 

AMEC reported (Wright et al., 2010b) that a deflection study was carried out based on Flexit, Reflex, and Maxibore II data from 28 core and 10 RC drill holes drilled in the 2003, 2007, and 2009 campaigns. The average deflection of the diamond drill holes was 1.8 meters of deflection per 100 meters downhole, and the average deflection of the RC holes was 4.8 meters deflection per 100 meters downhole. A more comprehensive deflection study completed by MDA (Defilippi, et.al., 2012) on all 2009 through May 2011 drill holes indicated an average deflection for every 100 meters down hole of 2.9 meters and 9.4 meters for the core and RC holes, respectively. As the RC deflection analysis is based on two readings per hole spaced at a regular 60 meter downhole interval, the 9.4 meter deflection is an extrapolated value that may not be indicative of the true deflection at greater drill depths.

 

Rio Alto did not perform downhole surveys during their 2014-2015 drill campaign. The average depth of Rio Alto’s drill holes was about 100 meters, so downhole deviation that occurred is considered to be minor and not likely to cause uncertainty in the position of drill hole. Tahoe initiated downhole surveys of all drill holes upon the acquisition of Rio Alto in April 2015.

 

85


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

10.5                        Drill Logging

 

To standardize the various geologic logging nomenclature from Atimmsa, Asarco, and Southern Peru drill data, Sulliden relogged the majority of the core and RC chips from holes drilled by the previous operators and checked the pre-existing database against the original assay certificates.

 

Between 2003 and 2010, Sulliden logged sample intervals, alteration, mineralization, and rock type data in digital spreadsheet forms. Drill logs recorded lithology, fracture orientation, oxidation, sulfide mineralization types and intensities, and alteration type and intensity. Sample recovery percentages and Rock Quality Designation (RQD) were also recorded. In 2010, Sulliden introduced the use of logging software (GEOTIC) to record geologic and geotechnical data. Logging by Rio Alto geologists in 2014 and 2015 used a similar nomenclature to the Sulliden system, using the GMAPPER recording system. Tahoe has continued with the logging procedures and nomenclature established by Sulliden and refined by Rio Alto.

 

Rio Alto undertook a major relogging program of existing drill core on 100m centers in 2015 using APT geological consultants, a local Peruvian geological consultancy. The purpose was to normalize the lithology data in the database for use in building a more robust geology model in preparation for an updated resource model and estimate using grouped siltstone-, sandstone-, mixed sandstone/siltstone-, breccia-, intrusive-, and colluvium-dominant rock packages that correspond to the geometallurgical domains. All other drill holes in the database that were not relogged were recoded into the above lithologic categories.

 

All drill core beginning with the 2003 Sulliden drill campaign through 2015 has been photographed.

 

10.6                        Drill Database

 

The database used by Tahoe for the current resource estimation was finalized on 15 April 2015 and includes all drill data up through RC hole SHA-R15-234 and core hole SHA-D15-002. The project database has a total of 103,378 gold assays, 102,140 silver assays and 84,466 total sulfur analyses. The database also includes a 31-element suite of trace element analyses for most holes drilled from 2007 to the present.

 

Tahoe considers the database to be of sufficient quality for use in resource estimation (see Section 12 — Data Verification).

 

10.7                        Core Recovery

 

In the 2012 NI 43-101 technical report prepared on behalf of Sulliden, MDA reported the results of their examination of the relationship between core recoveries to gold grade, particularly evaluating the

 

86


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

possible grade loss due to loss of fines in the drilling process. MDA concluded “the data suggests that, if present, this grade loss is limited to a small sample population and would not have a significant impact on the resource estimate” (Defilippi, et. al., 2012).

 

Tahoe has not performed any further study on the relationship between core loss and gold grade since the vast majority of drilling completed for the resource model and estimate since Rio Alto’s acquisition of Sulliden has been RC (234 holes) rather than core (12 holes).

 

10.8                        Comparison of Core and Reverse Circulation Drilling

 

In 2010, AMEC examined the relationship of gold values between RC and diamond drilling by comparing paired-sample plots for RC and diamond drill sample pairs that were within 5 meters and 10 meters apart. AMEC reported that there was no statistically significant sampling bias between RC drilling and diamond drilling (Wright et. al., 2010b).

 

MDA completed an analysis of the RC and core gold assay data using the 2012 drill database and came to a similar conclusion as the AMEC study (Defilippi, et. al., 2012). Both the comparative statistics (Table 10.8-1) and the quantile-quantile distribution plot (Figure 10.8-1) of drill data from within the mineral resource boundary indicated little to no global difference between the core and RC data. While the average gold values for each drill type are very similar, there was slightly more variation within the core versus the RC data, as indicated by the higher standard deviation and coefficient of variation values.

 

Table 10.8-1                         Core and RC Gold Analyses

(Defilippi, et. al., 2012)

 

Drill Type

 

Number
Samples

Mean

Median

Min

Max

Std Dev

CV

Core

 

28,521

 

0.492

 

0.225

 

0

 

59.9

 

1.241

 

2.535

 

RC

 

19,790

 

0.46

 

0.235

 

0

 

44.3

 

1.04

 

2.261

 

 

87


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 10.8-1                    Comparative Plot of Core and RC Gold Assays

(Defilippi, et. al., 2012)

 

To further investigate potential differences between RC and core drill data, Tahoe modelled estimates based on RC data only and RC + diamond core data in the area south of the Choloque fault. The RC drilling in this area is generally 25m x 25m spaced and the diamond core is generally 50m x 50m spaced. The same geologic model and estimation parameters were used for both estimates with the results constrained within a $1,400/oz Au pit shell. The results shown in Figure 10.8-2 demonstrate there is no appreciable difference between the gold estimates based on the RC only and the RC+DDH datasets.

 

88


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 10.8-2                    Comparison of RC to RC+DDH Model Estimates

(resource area south of Choloque fault)

 

10.9                        Tahoe 2015 Drill Program

 

From 15 April 2015 (the cut-off date for inclusion of drill data in the resource estimate) through 31 December 2015, Tahoe continued infill drilling within the current resource and pit shell, step-out drilling to expand the resource, geotechnical, metallurgical and condemnation drilling in support of operations, and exploration drilling at the proximal San Lorenzo, La Chilca, and Choloque targets. Post-resource drilling completed by Tahoe in 2015 includes 180 core and RC holes totaling 32,717 meters, as summarized in Table 10.9-1 and shown in Figure 10.9-1.

 

89


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 10.9-1                         Post-Resource Drilling

 

 

Core Drilling

RC Drilling

Totals

Purpose /
Area

No. Drill
Holes

Meters
Drilled

No. Drill
Holes

Meters
Drilled

No. Drill
Holes

Meters
Drilled

Infill

 

6

 

3,090.8

 

19

 

2,716.0

 

25

 

5,806.8

 

Step-out

 

10

 

2,856.4

 

40

 

9,186.0

 

50

 

12,042.4

 

Geotechnical

 

16

 

946.5

 

0

 

0.0

 

16

 

946.5

 

Metallurgical

 

8

 

1,262.8

 

0

 

0.0

 

8

 

1,262.8

 

Condemnation

 

19

 

3,630.8

 

28

 

2,814.0

 

47

 

6,444.8

 

San Lorenzo

 

2

 

422.1

 

24

 

4,076.0

 

26

 

4,498.1

 

Choloque

 

1

 

300.0

 

4

 

1066.0

 

5

 

1,366.0

 

La Chilca

 

3

 

350.0

 

0

 

0.0

 

3

 

250.0

 

Totals

 

65

 

12,859.4

 

115

 

19,858.0

 

180

 

32,717.4

 

 

 

Figure 10.9-1                    Post-Resource Drilling

 

90


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

10.9.1              Infill Drilling

 

Six core holes and 19 RC holes totaling 5,807 meters were collared inside of the current resource boundary and pit shell to aid in geologic interpretation and confirm grade estimates in areas of wider drill spacing. The six core holes were extended to target sulfide mineralization underlying the oxide resource.

 

10.9.2              Step-Out Drilling

 

Ten core holes and 40 RC holes totaling 12,042 meters were drilled around the periphery of the pit boundary to test for the continuation of mineralization beyond the currently defined pit extents. The drilling successfully identified mineralization outside of the northeast and southwest margins of the pit shell that will be incorporated into mine plan. Significant intercepts from the step-out drilling are tabulated in the Appendix — Post-Resource Drill Intercepts.

 

10.9.3              Exploration

 

Thirty-four drill holes (six core and 28 RC) totaling 6,114 meters were completed on the San Lorenzo, Choloque and La Chilca targets proximal to the Shahuindo resource. The San Lorenzo and La Chilca zones are associated with northeast-trending structures that cross the northwest-trending San Jose anticline, which is the dominant control of mineralization at Shahuindo. The northeasterly structural controls appear similar to the structural trends associated with gold-bearing veins in the nearby Algamarca district and likely represent a secondary structural control at Shahuindo. Three core holes were drilled at La Chilca to test oxidation levels and the continuity of mineralization along this northwest-trending structure northwest of the current Shahuindo resource. The results of this drilling are discussed in Section 24.2 - Exploration Potential; significant drill hole intercepts are tabulated in the Appendix.

 

10.9.4              Other Drilling

 

Geotechnical Drilling — Geotechnical drilling, consisting of 16 core holes totaling 947 meters, was completed in and around the proposed pit shell to validate and augment the results from prior geotechnical characterization studies.

 

Metallurgical Drilling — Eight core holes totaling 1,263 meters were drilled to obtain samples for additional metallurgical test work conducted by Tahoe (discussed further in Section 13.0 - Mineral Processing and Metallurgical Testing). The drill holes were designed to collect representative samples of the primary lithologic host rocks at Shahuindo.

 

Condemnation Drilling — Condemnation drilling (i.e., sterilization drilling) was focused primarily at the proposed waste dump, leach pad and crushing/agglomeration infrastructure sites and included 19 core

 

91


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

holes and 32 RC holes totaling 7,549 meters. The condemnation drilling in the waste dump area identified shallow ore grade mineralization in colluvium and bedrock sediments outside of the current resource boundary. This material is not included in the current mineral resource estimate, but a portion will be mined and delivered to the leach pad prior to construction of the waste dump foundation. Significant intercepts returned from the condemnation drilling are discussed further in Section 24.2 - Exploration Potential and tabulated in the Appendix (Post-Resource Drill Intercepts).

 

92


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

11.0                        SAMPLE PREPARATION, ANALYSES AND SECURITY

 

The information presented in this section regarding pre-2010 sampling, analyses, and security has been largely based on the 2010 Shahuindo PEA authored by AMEC (Wright et al., 2010b), with additional information from the 2012 Shahuindo technical report authored by Kappes, Cassiday & Associates and Mine Development Associates (Defilippi, et. al., 2012), and updated with Rio Alto and Tahoe drilling information.

 

11.1                        Drill Sampling

 

11.1.1              Diamond Drill Core Sampling

 

Asarco, Southern Peru, Sulliden, Rio Alto, and Tahoe have conducted diamond drilling operations at Shahuindo.

 

Asarco drilled 55 diamond core holes at Shahuindo in 1994 and 1995. Core samples were split lengthwise using a standard manual Longyear-type splitter. Tahoe has no further information on Asarco’s sampling procedures. Southern Peru drilled 16 core holes in 1997 and 1998. Tahoe has no details about their sampling procedures. The lack of information regarding diamond drill core sampling procedures by Asarco and Southern Peru is not considered material, as it accounts for only 12 percent of the total meters drilled by diamond drilling methods and the analytical values obtained from this drilling have been corroborated by subsequent drilling done by Sulliden and Rio Alto.

 

Between 2003 and 2012, Sulliden drilled 352 diamond core holes and generally sampled the drill core over the entire length of the drill hole. Competent core was split lengthwise with a diamond-blade rotary saw; disaggregated core was sampled using a spatula to take half of the sample. Sample lengths were typically 1.5 meters but were reduced to break samples at lithologic contacts or changes in oxidation state. Where core was completely disaggregated, sample lengths were changed to coincide with drill runs to minimize mixing between samples of differing core recoveries.

 

Post-2012 up to 15 April 2015, Rio Alto drilled 12 core holes and used the same procedures as Sulliden. However, sample lengths are typically two meters where not reduced to break samples at lithologic contacts or changes in oxidation state. Tahoe is continuing with these core sampling procedures.

 

11.1.2              Reverse Circulation Chip Sampling

 

Attimsa, Asarco, Southern Peru, Sulliden, Rio Alto, and Tahoe have conducted RC drilling operations at Shahuindo.

 

93


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Attimsa drilled 11 RC holes in 1992. Tahoe has no information on the sampling procedures used by Attimsa. The data from these RC holes is being used in the resource estimate, but contributes only 0.5% of the total data used for the estimate.

 

Asarco drilled 31 RC holes during their exploration campaign at Shahuindo. Fletcher (1997) reports that during the Asarco RC drill campaigns, drilling was mostly dry with good sample recovery. RC samples were collected and bagged on-site with samples split through a standard Jones-type riffle splitter multiple times to reduce the sample to three to four kilograms for shipment to the assay laboratory.

 

In 1997 and 1998, Southern Peru drilled 80 RC holes at Shahuindo, with standardized sample lengths of two meters. Tahoe has no other details regarding Southern Peru’s sampling procedures. The Southern Peru data accounts for 7.1% of the total data used in the resource estimate.

 

Sulliden completed 248 RC holes in 2009, 2010, and 2011, with standardized sample intervals of 1.5 meters. Different drilling and sampling procedures were used for dry versus wet ground as described below. Over 80% of the meterage completed was drilled dry. The following drilling and sampling descriptions are taken verbatim from the 2012 Shahuindo technical report (Defilippi, et. al., 2012):

 

Drilling in dry ground. In most cases, a 5¼-inch frontal recuperation hammer drill was used with pressurized air. In exceptional cases, a conventional 5¼-inch hammer was used based on ground conditions. Samples were reduced using a riffle splitter. The reject (70%) was retained for check-assay sampling. Samples were collected in polyethylene bags and were identified with the corresponding sample number. Each sample was sealed after inserting the laboratory tag number.

 

Drilling in wet ground. When intersecting ground water, argillaceous material in contact with water, or heavily fractured ground, pressurized air with minimal water was used with a conventional 5¼-inch SD5 hammer. Alternatively, a tricone bit was used where the recovery of cuttings was poor. A gyratory splitter was used to reduce sample size to a 30/70 split. Samples were collected with filter bags in truncated buckets in order to avoid spills or contamination.

 

A double-bagging system was incorporated for samples to be forwarded to the lab. A cloth bag with low filtration capacity was used inside a micro-porous cloth bag with high filtration capacity. If the bags were filled to capacity, both were tied-off separately, tagged, left for filtering, and dried prior to transportation to the primary assay laboratory. The rejects were received in a cloth bag and left for filtering and drying prior to being bagged in a polyethylene bag, tagged, and stored. Where reject samples were too large for a single bag, more than one sample was often obtained. The resulting additional bags filled with the corresponding samples and water from the same drilled interval were filtered and dried before being combined in one polyethylene bag, which was then identified and stored.

 

94


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Post-2012, Rio Alto and Tahoe have used the same procedures as Sulliden; however sample lengths have been increased to 2 meters due to sampling practicalities and better sample length accuracy when physically taking the sample.

 

11.1.3              Sample Storage

 

Sulliden created two secure core-storage facilities in the city of Cajamarca. Work to centralize the storage of all existing core at the facilities in Cajamarca was completed in 2009. Since 2009, all exploration core generated on the project has been being sent to Cajamarca for storage.

 

Archived drill core is stored in wooden and corrugated plastic boxes under cover at the core-storage facilities. Core boxes are in racks and stacked by hole number.

 

RC and laboratory coarse rejects and pulps are stored at the project site in a secure metal building. Coarse rejects are stored in labelled plastic bags and organized by hole and campaign. Pulps are stored in envelopes in cardboard boxes.

 

Stored coarse rejects and pulps are in varying condition. Some materials from previous operators were reorganized and transferred to new plastic bags by Sulliden to prolong their useful life and make locating individual samples more convenient. An inventory of project materials including certificates, core, coarse rejects, and pulps was compiled in 2009; Rio Alto, and now Tahoe, has maintained the drill sample inventory records.

 

11.2                        Sample Preparation and Analysis

 

Tahoe has limited information about sample preparation and analyses for the drill programs prior to the drill programs completed by Sulliden.

 

11.2.1              Atimmsa

 

Atimmsa used SGS del Peru S.A.C. (SGS) as the primary laboratory for their 1992 drilling. Tahoe has no further details and does not consider the lack of information to be material to the resource estimate due to the low percentage of data from this data set (0.4%) when compared to the overall drill database. Tahoe does not have information regarding SGS’s laboratory certification at the time of Atimmsa’s drilling program.

 

11.2.2              Asarco

 

During Asarco’s drill programs, all drill-hole samples were analyzed for gold and silver by one-assay-ton fire assay. Asarco used SGS to analyze their 1994 samples. For their 1995 drilling, Asarco used Skyline Laboratories, Inc., SGS, CIMM Peru S.A., and Actlabs, Inc. For Asarco’s 1996 drilling, SGS was the

 

95


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

primary lab. SGS, Skyline and Actlabs are currently ISO/IEC 17025 certified, but Tahoe has not determined laboratory certifications at the time of Asarco’s work.

 

11.2.3              Southern Peru

 

Tahoe has no details regarding sample preparation or analysis for Southern Peru’s drilling. Tahoe considers the risk to be minimal to the estimate as this data set accounts for only 7.1% of the data used in the estimate. Assay certificates from the 1997 and 1998 campaigns show that samples were analyzed by CIMM in Lima for gold and silver plus copper, lead, zinc, molybdenum, arsenic, bismuth, antimony, and mercury (Wright et al., 2010b). Southern Peru also re-assayed five drill holes from Asarco’s 1994 drilling at CIMM in Lima.

 

11.2.4              Sulliden

 

Between 2003 and 2012, Sulliden’s sampling and sample dispatch for the Shahuindo Project were carried out under the supervision of Sulliden staff. Samples are sent to ALS Minerals (ALS, formerly known as ALS Chemex) in Lima for sample preparation and analysis. Certificates were issued by ALS digitally and on paper. The ALS laboratory in Lima is ISO 9001:2008 and ISO 17025:2005 certified.

 

Samples were received at ALS, entered into the laboratory information management system, and weighed. Samples were dried and crushed to 70 percent passing plus two millimeters. Crushed samples were split with a riffle splitter to obtain 250-gram sub-samples, with the sub-samples pulverized using a ring mill to 85 percent passing 75 micrometers.

 

Between 2003 and 2012, gold was assayed with a 50-gram fire assay (FA) with atomic absorption (AA) finish. For samples with greater than 10 g/t Au in the initial FA-AA assay, the fire assay was repeated using a gravimetric finish.

 

In 2003 and 2004, silver was assayed from a 5-gram split, which was digested by aqua regia and read by AA (ALS method AA47); ALS method AA46 was used for samples with assay values exceeding 100 g/t Ag (Saucier and Poulin, 2004; Saucier and Buchanan, 2005). Between 2007 and 2012, a separate split was taken and digested in aqua regia for analysis with inductively coupled plasma atomic emission spectroscopy (ICP-AES) to determine 31 major and trace elements including silver, copper, arsenic, bismuth, and antimony (Wright et al., 2010b). For samples having greater than 100 Ag g/t, a silver assay was carried out from another 5-gram split, which was digested in aqua regia and read by AA. For samples having greater than 1,000 Ag g/t, silver was assayed by a 50-gram fire assay and a gravimetric finish. Mercury was analyzed with the cold vapor/AA method.

 

96


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

For the 2003 drilling, a total of 2,435 samples were assayed for gold, and pulps for each gold sample above 0.3 g/t Au in mineralized zones were re-assayed for silver (Saucier and Poulin, 2004). Starting with the 2004 drilling, silver was assayed for all mineralized intersections (Saucier and Buchanan, 2005).

 

11.2.5              Rio Alto

 

Reverse circulation and core samples from Rio Alto’s 2014-2015 drill program were analyzed by CERTIMIN laboratory in Lima. Gold was assayed using a 50-gram fire assay with an atomic absorption finish (CERTIMIN method IC-EF-01). When the result was greater than 10 g/t Au in the initial fire assay, the fire assay was repeated using a gravimetric finish (CERTIMIN method IC-EF-10). The procedure for silver analysis used by CERTIMIN is the same as the ALS method used by Sulliden, but did not include FA/Gravimetric analysis for samples having results greater than 1,000 g/t Ag. The CERTIMIN laboratory is ISO 9001 certified for geochemical, metallurgical and environmental sample analyses.

 

Tahoe continues to use the CERTIMIN laboratory in Lima as its primary assay lab for its continued drilling at the Shahuindo project.

 

11.3                        Bulk Density Determinations

 

The Shahuindo Project database contains 1,411 specific gravity measurements. The measurements were taken during various drill campaigns on drill core from throughout the deposit. Samples for measurement have been collected from all significant rock types along the extent of the deposit.

 

In 2004 and 2005, a total of 89 drill core samples were collected and sent to ALS in Lima for specific gravity determination (Saucier and Poulin, 2004; Saucier and Buchanan, 2005). The analyses were completed on drill core from 49 core holes from the 1998, 2003, and 2004 drill campaigns. Tahoe has no information on the methods used to determine specific gravity by ALS. The current database includes 87 of these determinations due to incomplete information on two samples.

 

In 2010, an additional 353 core samples were sent to Kappes, Cassiday & Associates (KCA) in Reno, Nevada for specific gravity measurements. Samples sent to KCA for measurements were from 12 core holes from Sulliden’s 2009 and 2010 drill campaigns.

 

In 2011 and 2012, Sulliden submitted 971 core samples from all core drilling campaigns executed on the project for density determination. Laboratories selected were KCA and ACME Labs in 2011 (580 samples) and ACME and SGS in 2012 (391 samples). The ACME and SGS laboratories are both located in Lima, Peru. Drill core specific gravity measurements conducted by KCA, ACME, and SGS used the coated immersion/water displacement method.

 

Tahoe has not conducted further bulk density determinations.

 

97


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

11.4                        Sample Security

 

From 2003 through 2009, all drill samples collected on the Shahuindo Project were under direct supervision of Sulliden’s staff up to the moment they were shipped by bus from Cajamarca to the ALS sample preparation facility. Between 2010 and 2012, samples were shipped directly from the camp to the laboratory facilities. Rio Alto and Tahoe have since changed the primary laboratory to Certimin in Lima. Samples were driven by Rio Alto employees directly to the Certimin laboratory in Lima.

 

Chain of custody procedures consist of filling out sample submittal forms that are physically handed to the laboratory with sample shipments to make certain that all samples are received by the laboratory.

 

11.5                        Quality Assurance/Quality Control

 

11.5.1              Asarco

 

According to Saucier and Poulin (2004), Asarco included standards prepared internally by them with every batch of drill samples for most of their drilling, and the standards had highly reproducible gold and silver values. Tahoe has no details on those standards. According to Fletcher (1997, cited by Saucier and Poulin, 2004), “[The laboratory] generally has very good precision…in their assays, but their results are typically 5-7% low for gold, and 11-15% low for silver relative to the standards. This discrepancy is probably due to matrix effects in the standards which have carbonate content, versus the routine drill samples which have none.”

 

A total of 1,835 duplicate samples were prepared and sent to a separate laboratory as a check assay. According to Fletcher (1997, cited by Saucier and Poulin, 2004), in general, the check assays validated the original assay values.

 

Tahoe has no reason to doubt Fletcher’s (1997) analysis and conclusions about Asarco’s assay data, but cannot confirm the work as Tahoe has no record of the results for Asarco’s standards or check assays.

 

11.5.2              Other Drilling Programs Prior to Sulliden

 

Tahoe has no information on quality control or quality assurance (QA/QC) that may have been used by Atimmsa or Southern Peru. This is considered to be of minimal risk to Tahoe given the small amount of samples involved when compared to the total database.

 

11.5.3              Sulliden

 

For Sulliden’s 2003 drilling, no blanks, duplicates, or standards were used to check the original assay results. However, 200 pulps taken randomly within the mineralized intervals were sent to SGS for re-assay for gold. These pulps were assayed for gold by fire assay with AA finish, with gravimetric finish for

 

98


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

gold grades over 5 g/t. Silver was assayed by multi-acid digestion with an AA finish. Saucier and Poulin (2004) reported that there was a “good correlation” between the original and check assays.

 

No blanks, site duplicates, or standards were used to check the results of Sulliden’s original assays from their 2004 drill program (Saucier and Buchanan, 2005). However, 355 pulps were randomly selected from within mineralized intervals by Sulliden’s geologists and sent to Actlabs in Lima for check assaying for gold and silver. Saucier and Buchanan (2005) reported that “a fairly good correlation could be found between the original values and the reanalysis.”

 

AMEC reported that except for the reject check program in 2003 and 2004, Sulliden did not apply QA/QC procedures until their 2009 drill program (Wright et al., 2010b). In 2009, Sulliden instituted analysis of commercially prepared standard reference materials, fine blanks, field duplicates for RC drilling, core duplicates for diamond drilling, and coarse-crush reject and pulp duplicates. The following information for Sulliden’s 2009-2010 drilling programs is summarized from the 2010 AMEC report (Wright et al., 2010b), to which the reader is referred for additional detail.

 

For the first stage of their 2009-2010 core and RC drill programs, Sulliden analyzed 110 RC field duplicates, 38 core duplicates, 99 coarse-crush reject duplicates, and 99 check assays performed at SGS in Lima, in addition to fine blanks and four commercial standards included with sample batches. AMEC concluded that based on analysis of the results of standards and check assays, the accuracy of the gold assays was “excellent,” whereas based on analysis of the check assays, the accuracy of silver assays was not as good as the accuracy of the gold assays (Wright et al., 2010b).

 

Based on analysis of RC and core field duplicates, AMEC concluded that the sampling precision for gold was acceptable for the resource estimate used for feasibility-level analysis (Wright et al., 2010b). Silver grades were not analyzed for the core and RC field duplicates. Analysis of the gold results of coarse-crush duplicates indicated that sub-sampling precision was better than generally accepted limits. Silver grades of coarse reject duplicates were not assayed.

 

Analytical precision is generally established by the analysis of pulp duplicates, two splits of the same pulp analyzed during the same time period, with the same analysis method at the same laboratory. No pulp duplicates were analyzed as part of the 2009 Sulliden drill program.

 

Analysis of 80 blank samples found only two minor issues above “a practical detection limit” of 0.02 Au g/t, and a plot of grade of blanks versus previous sample grade showed no correlation (Wright et al., 2010b).

 

Sulliden completed a comprehensive QA/QC testing program in 2011 and 2012, which included the analysis of commercially prepared standard reference materials, fine blanks, field duplicates for RC drilling, core duplicates for diamond drilling, and coarse-crush reject and pulp duplicates. The laboratory

 

99


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

analyses for the standards, fine blanks, RC field duplicates and core duplicates were completed at ALS while the analysis of the pulp duplicates were completed at SGS. The MDA review of standards suggested that “overall the analyses of standards suggest that Sulliden’s gold analyses may be, in aggregate, very slightly conservative” (Defilippi, et. al., 2012). There were 1,843 analyses of blank material, with only two counting as failures at a nominal 0.01 g/t failure line.

 

11.5.4              Rio Alto

 

Rio Alto completed a large RC and diamond core infill drill program in late 2014 and early 2015. The primary laboratory was changed from ALS to CERTIMIN on the basis of high quality QA/QC and good turnaround experienced at the La Arena operations.

 

Blanks, standards and field duplicates were inserted into the sample stream to check the QA/QC process both in the field and at the CERTIMIN laboratory in Lima. Blanks showed no evidence of contamination. Field duplicates show good repeatability, although the rate of insertion is low and needs to be increased. Review of the standards results shows CERTIMIN is assaying low in the lower grade ranges for silver and, to a lesser extent, gold There appears to be a consistent low bias at the CERTIMIN laboratory, mainly affecting silver assays.

 

Tahoe believes the rate of insertion of control samples is acceptable for blanks and standards, although low for RC field duplicates (Table 11.5-1). Tahoe has since increased the insertion rate for RC field duplicates.

 

Table 11.5-1        Summary of QAQC Program Applicable for 2015 Resource Estimate

 

Type

DDH
Samples

RC
Samples

Duplicates

Duplicates
(%)

Blanks

Blanks
(%)

Standards

Standards
(%)

Geotechnical

 

586

 

 

 

27

 

4.6

%

32

 

5.5

%

31

 

5.3

%

RC

 

 

 

11,631

 

166

 

1.4

%

600

 

5.2

%

587

 

5.0

%

DDH

 

373

 

 

 

17

 

4.6

%

18

 

4.8

%

20

 

5.4

%

Total

 

959

 

11,631

 

210

 

1.7

%

650

 

5.2

%

638

 

5.1

%

 

11.5.5              Blanks

 

Certified fine blanks were purchased from SGS and inserted into the sample stream. The average grade of the blanks is 0.006 g/t Au and 0.3 ppm Ag. Blanks are usually inserted every 50m downhole in RC holes and at or near the end of runs of mineralization in the diamond core. No failures are observed when using nominal 0.012 g/t Au and 0.6 ppm Ag upper acceptable limits of tolerance; well below a limit that would affect the resource estimate for either element. There is no evidence of any extra contamination after higher grades are encountered in the sample prior to the blank, although high grade

 

100


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

samples are somewhat rare in this new dataset. An example of the blank control plots is shown in Figure 11.5-1.

 

The use of fine blanks makes it easy for the laboratory to identify the control sample. At this stage in the project life for Shahuindo, it is recommended that coarse blanks be collected from coarse RC reject material if it is demonstrated that homogenous samples can be prepared. The insertion of coarse RC reject material as blanks would make it much more difficult for the laboratory to identify the blank control samples.

 

 

Figure 11.5-1                    Blank Analyses 2015 Drill Program

 

11.5.6              Field Duplicates

 

Field duplicate samples from RC data only have been analyzed as there is not a statistically valid number of diamond core samples for analysis (27 core samples). Although the insertion rate of RC field duplicates is low, they generally display good to very good repeatability in most grade ranges for both gold and silver (Figure 11.5-2 and Figure 11.5-3). The outliers are rare and not extreme, particularly given the observed nugget variance in the variography. The repeatability of sampling at lower gold grades close to the anticipated cut-off grade is acceptable (Figure 11.5-4).

 

101


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 11.5-2                    Field Duplicates 2015 RC Drill Program - All Au Grade Ranges

 

 

Figure 11.5-3                    Field Duplicates 2015 RC Drill Program - All Ag Grade Ranges

 

102


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 11.5-4                    Field Duplicates 2015 RC Drill Program - Au Grade Range 0.1g/t to 0.3g/t

 

11.5.7              Standards

 

Four commercially prepared standards from SGS (Lima) were reviewed. The standards are ST05, ST06, ST54 and ST50. The three lower grade standards within this group have gold results that are biased slightly low. All silver results are biased low (Table 11.5-2), with the lower grade silver standards showing the most bias. These results suggest a calibration error at the CERTIMIN Lima laboratory. The bias is systematic and follow up work is required.

 

Table 11.5-2        Summary of Analysis of Standards Used in 2015 Drill Program

 

STANDARD

 

No. of
Control
Samples

Certified
Mean Au
(g/t)

Control
Sample
Mean Au
(g/t)

Bias for
Au (%)

Certified
Mean Ag
(g/t)

Control
Sample
Mean Ag
(g/t)

Bias
for Ag
(%)

ST05

 

75

 

0.485

 

0.456

 

-6

%

14.8

 

12.63

 

-15

%

ST06

 

47

 

0.530

 

0.513

 

-3

%

8.4

 

6.44

 

-23

%

ST54

 

242

 

0.794

 

0.763

 

-4

%

17.7

 

16.49

 

-7

%

ST50

 

235

 

0.871

 

0.869

 

0

%

23.4

 

22.51

 

-4

%

 

Sample control sample charts are provided to display the systematic bias of the results for the standards (Figure 11.5-5 to Figure 11.5-8).

 

103


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 11.5-5                    Chart of Au Analyses of Standard 05

 

 

Figure 11.5-6                    Chart of Au Analyses of Standard 54

 

104


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 11.5-7                    Chart of Ag Analyses of Standard 06

 

 

Figure 11.5-8                    Chart of Ag Analyses of Standard 54

 

Tahoe believes the QA/QC process at Shahuindo would benefit from having one standard closer to the anticipated cut-off grade (0.18 g/t Au) and one higher grade gold standard to ensure that laboratory calibration for higher grade samples is appropriate.

 

105


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

11.6                        Summary Statement

 

Tahoe is of the opinion that the sampling methods, security, and analytical procedures used at Shahuindo are adequate for mineral resource estimation. While information is lacking for the Atimmsa and Southern Peru data, it represents only 7.6% of the dataset and is not considered to have a material effect on the resource estimate. The author is not aware of any sampling or assaying factors that may materially impact the Mineral Resource estimate discussed in Section 14.0.

 

A continuing program of specific gravity measurements is recommended due to the importance of bulk-density in the determination of resource tonnage.

 

The 2014-2015 QA/QC program demonstrates no evidence of laboratory contamination from the analysis of the blank samples. The field duplicates display good repeatability, particularly around the expected gold cut-off grade to be used while mining. Standards are biased slightly low (gold) to very low (silver). This is unlikely to have any material effect on the resource estimate, although this issue needs to be understood and resolved.

 

106


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

12.0                        DATA VERIFICATION

 

The Shahuindo drill hole database has been subjected to four audits prior to resource estimates in 2004, 2009, 2012 and 2015. The following is a summary of the key features of those audits conducted prior to the resource estimate reported herein.

 

12.1                        Met-Chem 2003/2004 Audit

 

·                  Site visits were conducted in 2003 and 2004

 

·                  The drill database was compared to the hardcopy assay certificates and geologic logs with no major errors were noted.

 

·                  A total of 102 check samples were collected and sent to secondary laboratories for analysis, with occasional local high variation encountered on individual samples; however, global averages of gold and silver from the check samples were in line with the primary samples.

 

·                  The overall conclusion was that the database was sufficient for global resource estimates (Saucier and Poulin 2004; Saucier and Buchanan, 2005).

 

12.2                        AMEC 2009 Database Audit and Verification

 

·                  AMEC collected 14 check samples; the results of which occasionally showed local high variability, though there was global agreement to grades reported by Sulliden for both gold and silver.

 

·                  AMEC completed a comprehensive database audit which included review of the project geology, drill hole logs, interpretations and drill collar locations, and 286 re-analyses of pulp rejects, duplicate pulps, coarse crushed rejects, and field duplicates from reverse circulation cuttings from the 1994-2007 drill programs. AMEC concluded the results of the work were sufficient to support mineral resource estimation (Wright et al., 2010a, 2010b).

 

12.3                        MDA 2012 Database Audit

 

·                  The focus of the MDA audit was on the drill hole collar, downhole survey and assay data. Spot checks of geological and geotechnical data were also completed. The Shahuindo database was considered to be of high quality sufficient to support the resource estimate and classification (Defilippi, et. al., 2012).

 

·                  MDA verified approximately 15 percent of the pre-2010 drill data to serve as a confirmation of the AMEC 2009 audit. If any discrepancies were identified, MDA checked additional holes from the same drill campaign.

 

107


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                  A comprehensive review of 2,599 inserted standards clearly displayed a constant small negative bias of the primary laboratory (ALS) from both standards and pulp duplicates, when compared to the check laboratory (SGS).

 

·                  There were 1,843 analyses of blank material, with only two counting as failures at a nominal 0.01 g/t failure line.

 

·                  A high level of repeatability was observed in all forms of field duplicates.

 

12.4                        Tahoe 2015 Database Audit

 

Tahoe conducted an audit of the 2014-2015 Rio Alto assay database (data through 15 April 2015) by comparing the analytical results reported in the hard copy certificates received from the laboratory (CERTIMIN) to the digital database used for the resource estimate. Tahoe compared 100% of the gold and silver assays in the database against the laboratory certificates with no errors detected.

 

12.5                        Statement on Data Verification

 

The QA/QC programs conducted on the Shahuindo samples and the multiple database audits are sufficient to ensure that the data used in the resource estimate is valid. While there are some discrepancies regarding the silver standards used by Rio Alto in 2014 and 2015, this is not considered material as silver has a negligible contribution to the economics of the project.

 

108


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

13.0                        MINERAL PROCESSING AND METALLURGICAL TESTING

 

13.1                        Metallurgical Testing Summary

 

Cyanidation and flotation testing programs have been conducted on composite samples from Shahuindo by various companies starting around 1996, as summarized in Table 13.1-1.

 

Table 13.1-1                         Cyanide and Flotation Testing Programs on Shahuindo

 

Year

 

Laboratory / Company

1996

 

Dawson Metallurgical Laboratories / Asarco (called Boti Project)

2003-2004

 

Heap Leach Consultants / Compañia Minera Algamarca

2009-2012

 

KCA / Sulliden

2014

 

KCA / Rio Alto

2014-2015

 

SGS / Tahoe (Rio Alto)

2014-2015

 

Tahoe (in-house tests at Rio Alto’s La Arena facilities)

 

Cyanidation tests were conducted by KCA from 2009 to 2012, by Rio Alto in 2014 and 2015, and by Tahoe in 2015 on drill core and surface sample composites. The results of the testing program indicated excellent gold recoveries at both run-of-mine (ROM) and coarse crush sizes with low to moderate reagent requirements, implying amenability to heap leaching. Silver recoveries are generally low.

 

Compacted permeability tests on minus 25mm crushed samples were conducted, both with and without cement. The results are variable with about one-third of the tests conducted in 2015 failing. The results from KCA’s compacted permeability tests on -32mm composites conducted in 2012 indicated that mixing of the more weathered samples with competent material would be required to maintain permeability at 6 kg of cement per tonne of ore. Two of the three KCA tests passed the compacted permeability tests at a simulated heap height of approximately 110 meters. There are no compacted permeability tests available at coarser crush sizes. Therefore, no definite conclusions can be made at this time on the permeability characteristics in a ROM or coarse crushed multiple-lift heap leach operation.

 

The projected field gold and silver recoveries, reagent consumptions, and leach times on oxide material based on the available test work results from both ROM and single-stage crushing tests are summarized in Table 13.1-2.

 

109


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 13.1-2                         Metallurgical Test Work Results

 

Parameter

 

ROM

 

Crush

% Au Recovery

 

73%

 

80%

% Ag Recovery

 

7%

 

12%

NaCN Consumption

 

0.2 kg/t

 

0.3 kg/t

Cement

 

0

 

6 kg/t*

Lime

 

2 kg/t

 

1 kg/t

Leach Time

 

80 days

 

70 days

Size, p80

 

~ 150mm

 

60 to 85mm

 


*Cement addition based on screened minus 75mm material

 

Figure 13.1-1 shows the locations of the drill holes and surface samples that were used for the metallurgical test work conducted by KCA and Tahoe (Rio Alto). As shown, the samples spatially represent the ore body.

 

 

Figure 13.1-1                    Location of Metallurgical Drill Holes

 

110


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

13.2                        Pre-2014 Metallurgical Test Summary

 

Tests were conducted early in the project life by Dawson Metallurgical Laboratories (Dawson), KCA and Heap Leach Consultants (HLC). Material tested by Dawson for Asarco included fifteen oxide and four sulfide composites made from RC drill cuttings. Cyanide bottle roll tests on the oxide composites and flotation tests on the sulfide samples were conducted.

 

The test program initiated by Asarco is of limited use as the work was preliminary in nature and heap leach column tests were not conducted. As such, this program is not mentioned further in this discussion.

 

13.2.1              Heap Leach Consultants Test Program

 

Heap Leach Consultants conducted column leach tests and bottle roll tests for Compañia Minera Algamarca on oxide surface bulk samples mainly taken from the northwestern half of the ore body. The column leach tests were conducted on samples at sizes ranging from ‘as-received’ (ROM) to minus 25mm.

 

Gold recoveries in the larger HLC column tests ranged from 17% to 91%. The average test recoveries and reagent consumptions by crush size are summarized in Table 13.2-1. Eight of HLC’s column tests failed due to permeability issues. There were also a series of small column tests conducted on composites crushed to minus 25mm and minus 75mm. All the minus 25mm tests except one failed due to permeability issues. The one minus 25mm small column test and the minus 75mm tests were agglomerated with 5 kg cement per tonne ore. Results from the failed tests are not included in the summary.

 

Table 13.2-1                         Summary of HLC Column Leach Tests

 

Crush
Size
mm

 

Calc’d
Head
Au g/t

Calc’d
Head
Ag g/t

Extraction
Au %

Extraction
Ag %

NaCN
Consumption
kg/t

Lime
kg/t

Cement
kg/t

ROM

 

1.14

 

5.8

 

27

 

5

 

0.2

 

2.4

 

0

 

-150

 

1.18

 

6.1

 

40

 

7

 

0.3

 

0.94

 

3

 

-100

 

0.99

 

6.2

 

81

 

14

 

0.34

 

0.31

 

4.4

 

-75*

 

N.A.

 

N.A.

 

50

 

6

 

N.A.

 

0

 

5

 

-25*

 

1.41

 

5.6

 

67

 

14

 

0.63

 

2.35

 

5

 

 


*Small column tests

 

Sodium cyanide consumptions in the column tests ranged from 0.2 to 0.8 kg/t. In the tests that were agglomerated, 3 to 5 kg cement per tonne of ore was added.

 

111


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Gold recoveries in the bottle roll tests conducted by HLC at minus 0.15mm (100 Tyler mesh) ranged from 75% to 93% while silver recoveries ranged from 13% to 39%. More detailed results from the column and bottle roll leach test program by HLC can be found in the 2012 Feasibility Study and Technical Report (Defilippi, et. al., 2012) and in HLC’s final report, Informe de Cianuracion en Botellas y Columnas a Escala Piloto (Heap Leach Consultants, 2005).

 

The HLC results were not used in the latest evaluation due to the unknown effect on recoveries due to permeability issues. Even though many of their tests went to completion, the specific solution application rate in several of the tests had to be decreased significantly to maintain flow, in some cases lowered to less than 2 l/hr/m2. These low application rates were mentioned in HLC’s final report. Channeling may or may not have been occurring in many of the tests. Therefore, it is unknown if the lower recoveries in many of the tests were due to ‘non-wetting’ of the material being tested.

 

KCA in their 2009 to 2012 test program conducted tests on bulk surface composites that were taken from similar locations as four of the samples that HLC tested. These results were used in this latest evaluation.

 

13.2.2              2009 to 2012 Kappes, Cassiday & Associates Test Program

 

KCA’s cyanidation tests were conducted on composites made from HQ and PQ drill core intervals taken in 2009 and 2010 and on bulk surface samples taken in 2011. The composites were made from core intervals ranging from surface to a depth of about 160 meters. The surface bulk samples were mainly used for coarse material column leach tests to simulate leaching of samples at ROM sizes.

 

Coarse material leach tests were conducted on the bulk surface samples at a p80 size of up to 240mm. The tests were conducted on as-received composites and on screened fractions of the composites: +100mm, -100+50mm and -50mm. The +100 and -100+50mm tests were conducted under flooding conditions. The gold and silver recoveries on the as-received composites averaged 77% and 25%, respectively. The test results on the screened composites varied greatly, partially due to permeability issues in several of the tests since the material tested was not agglomerated with cement.

 

There were a total of 21 column leach tests that were conducted on composites crushed from P80 sizes of 15mm up to 36mm. A total of 82 bottle roll leach tests were conducted on pulverized and coarse crushed composites.

 

Gold recoveries in the crushed ore column leach tests ranged from 79% to 94%. Average gold recovery at an average P80 crush size of 22mm was 89%. Gold recovery appears to be more related to sulfide sulfur content than crush size in the size ranges tested. The tests on crushed composites with an approximate sulfide sulfur content of 0.5% averaged 83% gold recovery. Silver recoveries in the crushed material column tests were generally low and ranged from 7% to 21% and averaged 17%.

 

112


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

A series of column leach tests utilizing various levels of agglomeration polymer at two solution application rates on splits of a single composite sample crushed to 21mm were conducted by KCA. Gold recovery ranged from 89% to 91% and averaged 90.6% with no obvious differences in final recoveries due to polymer addition or application rate.

 

Sodium cyanide consumptions in the crushed material column tests ranged from 0.38 to 1.17 kg/t and averaged 0.82 kg/t. All composites tested except the ROM samples and one at a crush size of minus 36mm were agglomerated with an average of 6 kg Portland Type II cement per tonne. The tests on the coarse material used hydrated lime as a source of alkalinity.

 

The average results of the ROM and crushed ore column leach tests and on the screened fractions are summarized in Table 13.2-2.

 

Table 13.2-2                         Summary of KCA Column Leach Tests

 

Sample Description

 

Avg
Crush/Screen
Size mm

Avg Calc’d
Head
Au g/t

Avg
Extraction
Au %

Avg NaCN
Consumption
kg/t

Avg
% Sulfide

ROM

 

129

 

0.41

 

77

 

0.28

 

0.06

 

Crushed Ore — All

 

22

 

1.04

 

89

 

0.88

 

0.11

 

Crushed Ore (<0.1% Sulfide)

 

22

 

1.15

 

90

 

0.81

 

0.05

 

Crushed Ore (>0.1% Sulfide)

 

21

 

1.49

 

83

 

0.86

 

0.49

 

+100mm Screened Fraction

 

+100

 

0.49

 

54

 

0.44

 

0.08

 

-100+50mm Screened Fraction

 

-50

 

0.52

 

71

 

0.38

 

0.08

 

-50mm Screened Fraction

 

-50

 

0.53

 

85

 

0.42

 

0.08

 

 

The KCA bottle roll test program included tests on pulverized and crushed composite samples. Gold recoveries in the pulverized bottle roll tests ranged from 73% to 95% while silver recoveries ranged from 19% to 77%. Coarse bottle roll tests were conducted on composite samples crushed at nominal sizes of minus 90, 37.5, 25 and 19mm. Gold recoveries ranged from 3% to 91% while silver recoveries ranged from 3% to 66%. Results from the bottle roll test program are summarized in Table 13.2-3.

 

113


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 13.2-3                         Summary of KCA Bottle Roll Leach Tests

 

Test Description

 

Avg P80
Crush Size
mm

Avg Calc’d
Head
Au g/t

Avg
Extraction
Au %

Avg
Extraction
Ag %

Avg NaCN
Consumption
kg/t

Avg
% Sulfide*

Pulverized

 

0.075

 

0.99

 

87

 

42

 

0.44

 

0.13

 

nominal -90mm

 

41.5

 

0.44

 

59

 

5

 

0.36

 

0.01

 

nominal -37.5mm

 

24.7

 

1.42

 

76

 

12

 

0.43

 

0.04

 

nominal - 25mm

 

19

 

1.05

 

69

 

21

 

0.53

 

0.51

 

nominal -19mm

 

13

 

1.48

 

79

 

14

 

0.34

 

0.04

 

All Coarse Tests, >0.1% S*

 

19.2

 

1.75

 

55

 

16

 

0.79

 

1.02

 

Minus 25mm, >0.1% S*

 

18.9

 

1.46

 

52

 

19

 

0.86

 

1.2

 

Minus 25mm, <0.1% S*

 

17.8

 

0.71

 

75

 

22

 

0.28

 

0.02

 

 


*Sulfide Sulfur

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The variability of gold recovery with sulfide content, crush size and sample depth was reviewed in the bottle roll test program. The test results generally indicate a decreasing gold recovery with increasing sulfide content and with increasing crush size. The results also suggest that there is a minor correlation between gold recovery and the depth of the sample with gold recovery decreasing with depth.

 

Details on KCA’s test results can be found in the 2012 Technical Report (Defilippi, et. al., 2012) and in the following unpublished laboratory reports:

 

·                  January 2011 KCA Report — Drill Core Composite Samples, Column Leach Test Program, Report of Metallurgical Test Work

 

Eight spatial and grade representative core drill holes, composited to three samples by rock code (codes 20, 30 and 40) - head analyses, bottle roll cyanide leach, cyanide shake, agglomeration testing, and column leach test work.

 

·                  March 2011 KCA Report — Report of Metallurgical Test Work, Bottle Roll Tests - 2009 Core 1 18 bags of broken core intervals combined to create 24 composites - twenty-four bottle roll tests, one on each composite.

 

·                  March 2011 KCA Report — Report of Metallurgical Test Work, Bottle Roll Tests — 2010, SHM- 10-116 — SHM-10-118

 

Nine composites from 2 core hole samples: SHM-10-116 and SHM-10-1 18; 5 composites developed from SHM-10-1 16; and 4 composites from SHM-10-118 - twenty-five bottle roll tests on composites crushed to 100% minus 90, 37.5 and 19mm.

 

114


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                 May 2011 KCA Report — 116 & 118 Column Tests, Report of Metallurgical Test Work

 

Core intervals from holes SHM-10-116 and SHM-10-118 - selected intervals utilized in the generation of three 80 kilogram composites crushed to 100% minus 37.5mm, one for each rock code tested (20, 30, 40) - size fraction analyses, bottle roll leach testing, agglomeration testing and column leach testing - multi-element ICP analysis and whole rock analysis performed on the samples.

 

·                  June 2011 KCA Report - All Rock Code Composites, Report of Metallurgical Test Work

 

Seven composites developed from the following SHM-10 series of drill holes:

 

·                  Composite 1: 121, 124, 127; Composite 2: 131, 133, 137

 

·                  Composite 3: 1 18, 121, 124, 131, 133; Composite 4: 116, 121, 124, 127

 

·                  Composite 5: 116, 118, 121; Composite 6: 116, 127, 131, 133

 

·                  Composite 7: 116, 124, 127, 131, 133

 

Seven 80 kilograms composite samples crushed to 100% minus 37.5mm and one 280 kilogram composite (split of composite 1) crushed to 100% minus 75mm (P80 of 36mm) - size fraction analyses, bottle roll leach testing, agglomeration testing and column leach testing - detoxification testing on barren solution from one of the smaller column tests - ICP and whole rock analyses on each composite.

 

·                  June 2011 KCA Report — Polymer Testing, Report of Metallurgical Test Work

 

Core intervals from holes SHM-10-131 and SHM-10-133 - one 200 kilogram composite crushed to approximately 20mm - size fraction analyses with assays by size fraction, bottle roll leach testing, agglomeration testing, column leach testing and detoxification test work - seven column leach tests on portions of the composite; each test utilized varying amounts of SNF and Nalco polymer as well as varying flow rates.

 

·                  December 2011 KCA Report — HLC 6, 7, 8, 9 Composites, Report of Metallurgical Test Work

 

Nine surface bulk samples received (samples taken from same approximate locations as the HLC 6, 7, 8 & 9 composites) - five of these bulk samples combined into three composites: an “A” composite, a “B” composite and a Global Master Composite - size fraction analyses bottle roll leach testing, agglomeration testing and column/flood leach testing.

 

·                  January 2012 KCA Report — P1 and P2 Zones, Report of Metallurgical Test Work

 

Ten barrels from each of the P1 and P2 Zones - material from each zone screened at 100 and 50mm - flood testing on +100mm and -100 +50 mm samples - size fraction analyses, bottle roll leach testing, agglomeration testing and column leach testing on -50mm material - two run of mine (ROM) composites, one from each zone, for column leach testing.

 

115


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                 May 2012 KCA Report — Bulk ROM Material, Report of Metallurgical Test Work

 

Eighty drums of bulk ROM material composited into eight bulk ROM samples - size fraction analyses, bottle roll tests - no column testing due to termination of ROM testing program

 

·                  May 2012 KCA Report — Report of Metallurgical Test Work

 

Acid-base accounting and humidity cell test work on waste drill core intervals and leached ore.

 

13.3                        2014 Kappes, Cassiday & Associates Test Program

 

Two column leach tests were conducted on composites from drill hole core samples remaining from the 2009 to 2012 KCA test program. KCA prepared a single composite based on instructions from Rio Alto. This composite was then screened and separated into different size fractions. Splits from each of the size fractions were then recombined into two composites: coarse and fine composites with “coarse” defined as the fractions greater than 25mm. The coarse composite was generated with a ratio of coarse to fine material of 1:1 while the fine composite was generated with a ratio of 1:2.

 

Column leach tests were conducted on each composite. Gold and silver recoveries in the two tests were the same at 89% and 10%, respectively, after 58 days of leaching. Sodium cyanide consumptions were virtually identical in the two tests at 0.67 and 0.68 kg per tonne. Both composites required a little over 3 kg of lime per tonne for alkalinity control.

 

Calculated head grades were also very similar, 1.10 g/t Au and 7.1 g/t Ag and 1.05 g/t Au and 6.4 Ag g/t. The tailings screen analyses of the coarse composite resulted in a p80 of 50.9mm while fine composite showed a p80 of 39.7mm.

 

13.4                        2014 and 2015 Test Programs

 

Numerous cyanidation and permeability tests were conducted under the direction of Rio Alto in 2014 and Tahoe Resources in 2015. The tests were conducted at Rio Alto’s La Arena testing facilities and by SGS Minerals Services, Anddes and PUCP (Catholic University, Lima).

 

13.4.1              Rio Alto, Tahoe Resources and SGS Column Leach Tests

 

Personnel at Rio Alto’s La Area laboratory conducted 38 column leach tests on composites generated from bulk surface samples and drill core intervals. Samples for testing were composited based on rock type and by drill hole. A total of eight core holes were drilled specifically for metallurgical test work.

 

The rock types developed by Tahoe Resources are summarized in Table 13.4-1.

 

116


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

Table 13.4-1        Rock Type Summary

 

Unit

 

Description

Q

 

Quaternary sandstone & siltstone clasts in clay matrix (>20% fines)

BX

 

Breccia with high fines content (>20% fines, clasts & matrix)

BXC

 

Breccia with low fines content (<20% fines, clasts & matrix)

SD

 

Sandstone (<5% fines)

SDH

 

Fine-grained sandstone (5%-20% fines)

ST

 

Siltstone (100% fines)

FPD

 

Dacite intrusive

SULF

 

Sulfide

 

The results from Rio Alto’s series of column leach tests are presented in Table 13.4-2 and Table 13.4-3. SGS conducted a total of five column leach tests; the results of which are summarized in Table 13.4-4. Two tests were conducted on individual composites of siltstone and sandstone and three tests on blends of sandstone and siltstone at ratios of 4:1, 2:1 and 1:1.

 

As shown in Table 13.4-2 through Table 13.4-4, gold recoveries on oxide material are generally very good, averaging approximately 82% including all crush sizes and rock types (except sulfides). Gold recoveries ranged from 68% to 89%.

 

The test with 68% gold recovery was on a fine-grained sandstone surface composite. The results of the column leach tests show a trend with lower recoveries in the tests containing this sandstone composite. Cyanide soluble tests on ground samples of this same composite also show lower gold recoveries as compared to other rock types. The reasoning for the lower recovery is not clear as tests on other sandstone composites resulted in significantly higher recoveries. It is possible that the composite contained a small quantity of sulfides, which have shown to decrease gold recovery.

 

In the SGS series of tests, the recovery of gold decreased slightly with increasing siltstone content. This trend was also present in the SGS bottle roll tests as discussed in Section 13.4.3. Silver recoveries in all the tests were generally low, averaging 17%.

 

Reagent consumptions were low to moderate in these series of column leach tests. Sodium cyanide consumptions varied from 0.12 to 1.43 kg NaCN per tonne ore and averaged 0.78 kg/t, including all results except those on the sulfide test. Lime additions ranged from 0.7 to 2.7 kg lime per tonne ore in tests where no cement was added. Average lime requirement in these tests was 1.8 kg/t. Cement at 4 to 6 kg/t was added to several of the -25mm tests. In these tests, the average cement addition rate was 4.5 kg/t and the average lime added was 1.5 kg/t.

 

117


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

Table 13.4-2 Rio Alto Column Leach Test Results on Surface Samples

 

Column

No.

 

 

 

Crush Size,

p100, mm

 

 

 

 

 

Leach Time

days

 

Head g/t

 

% Recovery

 

NaCN

kg/t

 

Lime

kg/t

 

Cement

kg/t

 

 

Sample Description

 

 

Rock Type

 

ppm CN-*

 

 

Au

 

Ag

 

Au

 

Ag

 

 

 

 

15

 

Drum, Surface PM1

 

76

 

Sandstone

 

150

 

60

 

5.570

 

808.0

 

79.7

 

3.3

 

0.48

 

2.2

 

0

 

16

 

Drum, Surface PM1

 

76

 

Sandstone

 

150

 

60

 

5.570

 

808.0

 

79.7

 

3.3

 

0.60

 

2.3

 

0

 

17

 

Drum, Surface PM2

 

76

 

Sandstone

 

150

 

23

 

0.170

 

7.1

 

83.3

 

3.7

 

0.12

 

1.1

 

0

 

18

 

Drum, Surface PM2

 

76

 

Sandstone

 

150

 

23

 

0.170

 

7.1

 

84.0

 

3.5

 

0.17

 

1.1

 

0

 

8

 

Drum, Surface Blend of PM1 & PM2

 

76

 

Sandstone

 

500

 

60

 

2.550

 

360.8

 

83.2

 

5.2

 

1.25

 

1.5

 

0

 

1

 

Truck 1, First Sample

 

ROM

 

Sandstone

 

150

 

60

 

0.325

 

4.7

 

75.5

 

4.5

 

0.20

 

2.3

 

0

 

3

 

Truck 1, First Sample

 

100

 

Sandstone

 

150

 

60

 

0.311

 

4.9

 

76.1

 

4.6

 

0.28

 

2.2

 

0

 

14

 

Truck 1, First Sample

 

12.5

 

Sandstone

 

150

 

30

 

0.346

 

7.2

 

75.1

 

8.0

 

0.14

 

2.4

 

0

 

15

 

Truck 1, First Sample

 

12.5

 

Sandstone

 

300

 

30

 

0.346

 

7.2

 

78.0

 

9.5

 

0.43

 

2.4

 

0

 

16

 

Truck 1, First Sample

 

12.5

 

Sandstone

 

500

 

30

 

0.346

 

7.2

 

81.7

 

9.7

 

0.74

 

2.4

 

0

 

1

 

Truck 2: 1:2=Sample 514420 : Sample 514416

 

ROM

 

Sandstone, Siltstone

 

100

 

80

 

1.765

 

8.8

 

76.2

 

2.9

 

0.26

 

1.8

 

0

 

2

 

Truck 2: Sample 514420

 

ROM

 

Sandstone - Medium Grain

 

100

 

80

 

0.474

 

2.1

 

77.8

 

13.1

 

0.22

 

1.8

 

0

 

3

 

Truck 2: Sample 514425

 

150

 

Siltstone & Sandstone - Fine Grain

 

100

 

81

 

0.967

 

3.5

 

84.0

 

10.7

 

0.32

 

1.9

 

0

 

4

 

Truck 2: 1:2=Sample 514420 : Sample 514417

 

150

 

Sandstone - Intertwinned

 

100

 

81

 

0.861

 

2.0

 

70.3

 

13.4

 

0.34

 

2.0

 

0

 

9

 

Truck 2: Sample 514416

 

76

 

Siltstone - Fine Grain

 

100

 

77

 

3.444

 

10.7

 

73.9

 

6.7

 

0.45

 

2.7

 

0

 

11

 

Truck 2: Sample 514425

 

76

 

Siltstone & Sandstone -Fine Grain

 

100

 

77

 

1.379

 

4.0

 

78.1

 

14.3

 

0.37

 

2.5

 

0

 

12

 

Truck 2: Sample 514417

 

76

 

Sandstone - Fine Grain

 

100

 

83

 

1.062

 

3.3

 

68.1

 

14.1

 

0.54

 

2.6

 

0

 

13

 

Truck 2: Sample 514420

 

76

 

Sandstone - Medium Grain

 

100

 

83

 

0.472

 

2.5

 

80.8

 

17.3

 

0.51

 

2.2

 

0

 

 


*Average concentration of cyanide (as CN-) in test leach solutions

 

118


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

Table 13.4-3        Rio Alto Column Leach Test Results on Drill Core Composites

 

Column

No.

 

 

 

Crush Size

p100 mm

 

 

 

 

 

Leach Time

days

 

Head g/t

 

% Recovery

 

NaCN

kg/t

 

Lime

kg/t

 

Cement

kg/t

 

 

Sample Description

 

 

Rock Type

 

ppm CN-*

 

 

Au

 

Ag

 

Au

 

Ag

 

 

 

 

32

 

ST1 (Met hole 001M, drill core intervals to 132m)

 

25

 

Siltstone

 

500

 

60

 

0.348

 

1.7

 

84.2

 

23.64

 

0.95

 

1.3

 

5.0

 

21

 

ST2 (Met hole 001M, intervals 161m to 176m)

 

25

 

Siltstone

 

500

 

60

 

0.323

 

2.0

 

87.1

 

34.16

 

1.13

 

1.5

 

5.0

 

33

 

SD+SDH (all SD+SDH intervals in met hole 001M)

 

25

 

Compact & Fine Grained Sandstone

 

500

 

60

 

0.410

 

3.3

 

88.7

 

25.36

 

0.91

 

0.9

 

0.0

 

34

 

BX + BXC (all BX+BXC intervals in met hole 001M)

 

25

 

Breccia, High & Low Fines Content

 

500

 

60

 

0.511

 

2.5

 

87.4

 

21.13

 

0.98

 

1.0

 

4.0

 

35

 

ST (Met hole 002M, core intervals to 132m)

 

25

 

Siltstone

 

500

 

60

 

0.643

 

1.8

 

89.0

 

21.48

 

1.20

 

1.3

 

5.0

 

36

 

SD (all SD intervals in met hold 002M)

 

25

 

Compact Sandstone

 

500

 

60

 

0.623

 

7.5

 

85.0

 

19.73

 

1.08

 

0.7

 

0.0

 

22

 

BX + BXC (all BX+BXC intervals in met hole 002M)

 

25

 

Breccia, High & Low Fines Content

 

500

 

60

 

0.924

 

3.6

 

85.6

 

11.68

 

1.32

 

1.9

 

4.0

 

37

 

ST (Met hole 003M, core intervals to 132m)

 

25

 

Siltstone

 

500

 

60

 

0.533

 

6.5

 

87.7

 

14.18

 

1.43

 

1.0

 

5.0

 

38

 

ST (Met hole 004M, core intervals to 132m)

 

25

 

Siltstone

 

500

 

60

 

0.887

 

6.7

 

89.5

 

21.05

 

1.25

 

2.1

 

5.0

 

23

 

BX + BXC (Met hole 004M)

 

25

 

Breccia, High & Low Fines Content

 

500

 

60

 

1.084

 

4.4

 

73.2

 

27.99

 

0.66

 

1.6

 

4.0

 

39

 

ST (Met hole 005M, core intervals to 80m)

 

25

 

Siltstone

 

500

 

60

 

0.224

 

1.4

 

85.5

 

26.65

 

1.06

 

0.9

 

5.0

 

40

 

ST (Met hole 005M, intervals from 82m to 150m)

 

25

 

Siltstone

 

500

 

60

 

0.273

 

1.6

 

89.4

 

33.77

 

1.15

 

2.0

 

5.0

 

41

 

SD + SDH (all SD+SDH intervals in met hole 005M)

 

25

 

Compact & Fine Grained Sandstone

 

500

 

60

 

0.267

 

4.5

 

86.6

 

32.32

 

0.97

 

1.2

 

0.0

 

42

 

ST (all ST intervals in met hole 006M)

 

25

 

Siltstone

 

500

 

60

 

0.331

 

5.9

 

85.0

 

22.39

 

0.95

 

1.1

 

5.0

 

43

 

SD + SDH (all SD+SDH intervals in met hole 006M)

 

25

 

Compact & Fine Grained Sandstone

 

500

 

60

 

0.365

 

6.3

 

83.8

 

30.67

 

0.89

 

0.9

 

0.0

 

44

 

ST (all ST intervals in met hole 007M)

 

25

 

Siltstone

 

500

 

60

 

0.484

 

1.1

 

88.4

 

19.62

 

1.15

 

1.4

 

5.0

 

45

 

SD + SDH (all SD+SDH intervals in met hole 007M)

 

25

 

Compact & Fine Grained Sandstone

 

500

 

60

 

0.465

 

8.7

 

80.7

 

16.08

 

1.01

 

0.8

 

0.0

 

46

 

ST (Met hole 008M, intervals from 0m to 80m)

 

25

 

Siltstone

 

500

 

60

 

0.428

 

6.9

 

82.2

 

23.6

 

1.16

 

1.8

 

5.0

 

47

 

SD + SDH (all SD+SDH intervals in met hole 008M)

 

25

 

Compact & Fine Grained Sandstone

 

500

 

60

 

0.360

 

4.3

 

82.5

 

17.23

 

1.14

 

1.6

 

0.0

 

48

 

SULFIDES (008M, intervals from 114m to 160m)

 

25

 

Sulfides

 

500

 

60

 

0.695

 

23.9

 

19.7

 

2.527

 

1.72

 

2.9

 

5.0

 

 


*Average concentration of cyanide (as CN-) in test leach solutions

 

119


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

Table 13.4-4                         SGS Column Leach Test Results

 

Column

No.

 

 

 

Crush Size

p100 mm

 

 

 

 

 

Leach Time

days

 

Head g/t

 

% Recovery

 

NaCN

kg/t

 

Lime

kg/t

 

Cement

kg/t

 

 

Sample Description

 

 

Rock Type

 

ppm CN-*

 

 

Au

 

Ag

 

Au

 

Ag

 

 

 

 

SGS 1

 

Core intervals composited from 003M

 

25

 

Silstone

 

500

 

48

 

0.48

 

9.7

 

80.7

 

14.7

 

1.24

 

3.92

 

6

 

SGS 2

 

Core intervals composited from 005M

 

25

 

Sandstone

 

500

 

48

 

0.28

 

4.7

 

84.7

 

34.9

 

0.77

 

2.26

 

0

 

SGS 3

 

4:1 ratio of SD:ST, 001M to 008M

 

25

 

Sandstone-Siltstone Blend

 

500

 

48

 

0.3

 

5.7

 

83.3

 

29.7

 

0.81

 

1.08

 

0

 

SGS 4

 

2:1 ratio of SD:ST, 001M to 008M

 

25

 

Sandstone-Siltstone Blend

 

500

 

48

 

0.41

 

6.9

 

83.1

 

25.0

 

1.06

 

0.49

 

4

 

SGS 5

 

1:1 ratio of SD:ST, 001M to 008M

 

25

 

Sandstone-Siltstone Blend

 

500

 

48

 

0.46

 

8.3

 

83.2

 

21.8

 

1.11

 

0.22

 

5

 

 


*Average concentration of cyanide (as CN-) in test leach solutions

 

120


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

13.4.2     Discussion on the Results of the Rio Alto and SGS Column Leach Tests

 

The results from the column leach tests by SGS and Rio Alto were sorted and averaged based on crush size. The results from the -25mm tests were also sorted by rock type and averaged. These results are presented in Table 13.4-5.

 

The tests show some variation in gold recovery with crush size. The average gold recovery from tests conducted on coarser material (p100 of 100mm or greater) averaged 76% while the gold recovery on samples crushed to approximately 76mm averaged 79%. Gold recovery in the minus 25mm column leach tests averaged 84%. The minus 25mm test results also indicate similar gold recoveries on the composites of sandstone and siltstone and slightly lower recoveries on breccia composites. Sodium cyanide consumptions vary based on the concentration of cyanide used in the column tests and do not seem to vary significantly due to differing rock types or on crush size.

 

One potential issue with the column leach tests on the ROM and coarser crushed siltstone/sandstone blended composites was the high fines content in the pregnant leach solutions. Several of the tests reported a pregnant solution fines content of over 6% solids by weight, which is extremely high. This high fines migration in a heap can quickly fill up a solution storage pond and cause operating problems in the adsorption and pumping circuits. The fines issue needs to be evaluated further in the future. The amount of fines in the pregnant solution would likely be significantly reduced by the introduction of cement agglomeration.

 

121


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

Table 13.4-5        SGS and Rio Alto Column Leach Test Results by Size and Rock Type

 

Avg Crush Size

 

 

 

 

 

Avg ppm

 

 

Avg Leach

 

 

Avg Head Grade g/t

 

 

Avg % Recovery

 

 

Avg Reagent Req’d kg/t

 

p100 mm

 

 

Rock Type

 

 

CN-*

 

 

Time days

 

 

Au

 

 

Ag

 

 

Au

 

 

Ag

 

 

NaCN

 

 

Lime

 

 

Cement

 

ROM

 

 

Mainly sandstone (surface)

 

 

117

 

 

73

 

 

0.85

 

 

5

 

 

76

 

 

7

 

 

0.23

 

 

1.94

 

 

0.00

 

150

 

 

Sandstone & Siltstone (surface)

 

 

100

 

 

81

 

 

0.91

 

 

2.7

 

 

77

 

 

12

 

 

0.33

 

 

1.97

 

 

0.00

 

100

 

 

Sandstone (surface)

 

 

150

 

 

60

 

 

0.31

 

 

4.9

 

 

76

 

 

5

 

 

0.28

 

 

2.21

 

 

0.00

 

76

 

 

Sandstone & Siltstone (surface)

 

 

167

 

 

61

 

 

2.27

 

 

224

 

 

79

 

 

8

 

 

0.50

 

 

2.02

 

 

0.00

 

25

 

 

Sandstone, Siltstone, Breccia (core)

 

 

500

 

 

58

 

 

0.48

 

 

4.8

 

 

85

 

 

24

 

 

1.06

 

 

1.37

 

 

3.21

 

12.5

 

 

Sandstone (surface)

 

 

317

 

 

30

 

 

0.35

 

 

7.2

 

 

78

 

 

9

 

 

0.44

 

 

2.43

 

 

0.00

 

25

 

 

Breccia

 

 

500

 

 

60

 

 

0.84

 

 

3.5

 

 

82

 

 

20

 

 

0.99

 

 

1.49

 

 

4.00

 

25

 

 

Sandstone

 

 

500

 

 

58

 

 

0.40

 

 

5.6

 

 

85

 

 

25

 

 

0.97

 

 

1.22

 

 

0.00

 

25

 

 

Siltstone

 

 

500

 

 

59

 

 

0.45

 

 

4.1

 

 

86

 

 

23

 

 

1.15

 

 

1.64

 

 

5.09

 

 


*Average concentration of cyanide (as CN-) in test leach solutions

 

122


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

13.4.3     SGS Bottle Roll Tests

 

SGS conducted a series of bottle roll tests on splits of the samples tested in the SGS column leach program. The bottle roll tests were conducted for 72 hours on composites crushed to 100% passing 2mm. These results are presented in Table 13.4-6.

 

Table 13.4-6        Summary of SGS 72-hour Bottle Roll Tests

 

 

 

 

 

Crush

 

 

 

Head g/t

 

% Recovery

 

 

 

 

Test
No.

 

Sample Description

 

Size p100
mm

 

NaCN
g/L

 

Au

 

Ag

 

Au

 

Ag

 

NaCN
kg/t

 

Lime
kg/t

 

1

 

Siltstone

 

2

 

0.94

 

0.47

 

9.4

 

76.7

 

18.8

 

1.97

 

5.56

 

2

 

Sandstone

 

2

 

0.94

 

0.28

 

4.9

 

84.5

 

41.9

 

0.92

 

1.59

 

3

 

Blend 4 Sandstone to 1 Siltstone

 

2

 

0.94

 

0.28

 

5.5

 

82.7

 

38.4

 

1.38

 

2.27

 

4

 

Blend 2 Sandstone to 1 Siltstone

 

2

 

0.94

 

0.42

 

6.6

 

80.6

 

32.3

 

1.50

 

2.31

 

5

 

Blend 1 Sandstone to 1 Siltstone

 

2

 

0.94

 

0.48

 

7.9

 

79.8

 

26.2

 

1.81

 

3.25

 

1B

 

Siltstone (Duplicate)

 

2

 

0.94

 

0.43

 

9.5

 

80.1

 

17.2

 

2.00

 

5.75

 

 

Gold recoveries did not vary greatly, ranging from 77% to 84%. The siltstone composite had the lowest gold recovery, averaging approximately 78% in the two tests. The recovery of gold decreased with increasing siltstone content in the series of bottle roll tests. This trend is also shown in the SGS column leach tests results previously shown in Table 13.4-4.

 

Silver recoveries were generally low, averaging 29%. There is a similar trend with decreasing silver recoveries with increasing siltstone content.

 

Lime and cyanide consumptions were both high in all tests, with the tests on the siltstone material the highest. The series of bottle roll test results also show lime and cyanide requirements increasing with increasing siltstone content in the composites. These trends based on siltstone content are not apparent in the larger column leach tests on the coarser ore composites conducted at La Arena by Rio Alto.

 

The SGS report stated that the siltstone sample had higher contents of copper, iron and arsenic than the sandstone composite which could account for the higher reagent consumptions. Gold recoveries should only minimally affected by the level of these three elements in the siltstone samples. Cyanide soluble copper levels are low and should not cause any issues with heap performance.

 

The SGS data also show that the siltstone composite had higher levels of sulfur. It is unknown if the sulfur is due to sulfates (as jarosite), elemental sulfur or sulfides. KCA’s 2009 to 2012 test program showed a decrease in gold recovery with increasing sulfide content.

 

123


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

Head grade assays for copper, iron, arsenic and sulfur in the SGS siltstone and sandstone composites are summarized in Table 13.4-7.

 

Table 13.4-7        Copper, Iron, Arsenic and Sulfur Levels in the SGS Composites

 

Rock Type

 

% Iron

 

% Sulfur

 

Cu
ppm

 

Arsenic
ppm

 

Siltstone

 

10.77

 

1.16

 

80.5

 

1909

 

Sandstone

 

3.36

 

0.27

 

15.9

 

512

 

 

13.4.4     Compacted Permeability Tests

 

A series of compacted permeability tests were conducted by Anddes and PUCP. Anddes’ results are more relevant to determining percolation properties of the ore at various simulated heap heights due to the type and size of test. The tests by PUCP were on small samples and are more oriented to testing soil samples. PUCP’s results are not presented here as they were not used in the evaluations.

 

Anddes’ tests were conducted in an approximate 300mm diameter cylinder on leached minus 25mm residues from the series of column leach tests conducted at La Arena. Initial sample heights were kept constant at about 300mm. The tests were conducted as “rigid” tests, with a solid cylinder wall. KCA conducts similar tests, although preferably with a higher sample test height. KCA has used results from these types of tests successfully in estimating cement requirements at varying heap heights in numerous heap leach projects. Anddes’ results are presented in Table 13.4-8.

 

The percolation rate is dependent on the heap height simulated and on the content of fines present in the samples tested. Figure 13.4-1 presents the variation in percolation rates with fines content and simulated heap heights while Figure 13.4-2 presents the change in rates with rock type and simulated heap heights. The results indicate that material with approximately 20% fines ( minus 75 microns) or greater could have permeability issues, or this material could cause channelling within the heap due to zones with higher fines content.

 

The series of compacted permeability tests were conducted on minus 25mm leached residues. The results can be considered to be a worst case scenario and do not necessarily lead to the conclusion that the approximate minus 100mm coarse crushed ore will have permeability issues. The results do indicate that sandstones will have not have any permeability issues as all tests on this rock type passed. The breccia material had mixed results with higher fines content samples not passing. All the siltstone samples failed the tests, even at cement additions of up to 5 kg/t. Additional testing is required, including testing at a coarser crush size, blending of the rock types and varying the cement levels.

 

124


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

Table 13.4-8        Compacted Permeability Test Results

 

 

 

 

 

 

 

 

 

Classification (SUCS)

 

Permeability (Rigid) cm/s

 

 

Drill
Hole

 

Column
Test No.

 

Rock Type

 

Description

 

Gravel (%)

 

Sand (%)

 

Fines (%)

 

Liquid Limit

%

 

1 kPa

<6m Heap Ht

 

300 kPa

16m Heap Ht

 

800 kPa

45m Heap Ht

 

2000 kPa
110m Heap Ht

 

Cement
(kg/t)

001M

 

C-21

 

ST2

 

Siltstone (100% fines)

 

22.7

 

55.6

 

21.8

 

20

 

5.00E-02

 

0

 

0

 

0

 

5.0

002M

 

C-22

 

BX+BXC

 

Breccia, High & Low Fines Content

 

48.8

 

34.3

 

16.9

 

18

 

2. 10E+00

 

1.00E+00

 

5.40E-01

 

2.50E-01

 

4.0

004M

 

C-23

 

BX+BXC

 

Breccia, High & Low Fines Content

 

17.3

 

30.4

 

52.4

 

26

 

1.40E+00

 

0

 

0

 

0

 

4.0

001M

 

C-32

 

ST1

 

Siltstone (100% fines)

 

19.2

 

14

 

66.8

 

28

 

2.70E-01

 

0

 

0

 

0

 

5.0

001M

 

C-33

 

SD+SDH

 

Compact & Fine Grained Sandstone

 

61.1

 

20.1

 

18.7

 

22

 

4.70E-01

 

1.90E-01

 

5.80E-02

 

1.40E-03

 

0.0

001M

 

C-34

 

BX+BXC

 

Breccia, High & Low Fines Content

 

27.8

 

25.9

 

46.4

 

19

 

5.80E-01

 

0

 

0

 

0

 

4.0

002M

 

C-35

 

ST

 

Siltstone (100% fines)

 

54

 

22.4

 

23.6

 

23

 

4.10E-01

 

2.80E-02

 

1.20E-02

 

2.90E-03

 

5.0

002M

 

C-36

 

SD

 

Sandstone

 

64.8

 

22.3

 

12.9

 

25

 

5.70E-01

 

3.30E-01

 

1.90E-01

 

8.20E-02

 

0.0

003M

 

C-37

 

ST

 

Siltstone (100% fines)

 

34

 

26.1

 

39.9

 

23

 

5.20E-02

 

4.90E-04

 

4.20E-06

 

0

 

5.0

004M

 

C-38

 

ST

 

Siltstone (100% fines)

 

34

 

33.3

 

32.8

 

28

 

1.10E-01

 

0

 

0

 

0

 

5.0

005M

 

C-39

 

ST

 

Siltstone (100% fines)

 

38.9

 

28.2

 

32.9

 

22

 

1.50E-01

 

3.50E-04

 

0

 

0

 

5.0

005M

 

C-40

 

ST

 

Siltstone (100% fines)

 

46.1

 

25.5

 

28.5

 

24

 

3.90E-01

 

2.70E-02

 

5.60E-03

 

1.10E-03

 

5.0

005M

 

C-41

 

SD+SDH

 

Compact & Fine Grained Sandstone

 

66.4

 

22.5

 

11.1

 

17

 

3.10E+00

 

1.80E+00

 

8.90E-01

 

3.20E-01

 

0.0

006M

 

C-42

 

ST

 

Siltstone (100% fines)

 

35.5

 

13.7

 

50.8

 

24

 

3.30E-02

 

0

 

0

 

0

 

5.0

006M

 

C-43

 

SD+SDH

 

Compact & Fine Grained Sandstone

 

73.3

 

17.1

 

9.6

 

18

 

1.20E-01

 

5.60E-01

 

4.70E-01

 

3.50E-01

 

0.0

007M

 

C-44

 

ST

 

Siltstone (100% fines)

 

43.1

 

29.9

 

26.9

 

27

 

3.20E-01

 

7.30E-03

 

8.80E-04

 

8.20E-04

 

5.0

007M

 

C-45

 

SD+SDH

 

Compact & Fine Grained Sandstone

 

68

 

21.4

 

10.6

 

18

 

3.10E+00

 

2.60E+00

 

1.80E+00

 

6.40E-01

 

0.0

008M

 

C-46

 

ST

 

Siltstone (100% fines)

 

49.3

 

31.2

 

19.5

 

27

 

4.30E-01

 

2.60E-02

 

4.30E-03

 

5.50E-05

 

5.0

008M

 

C-47

 

SD+SDH

 

Compact & Fine Grained Sandstone

 

66.9

 

26.9

 

6.2

 

20

 

1.80E+00

 

1.70E+00

 

1.20E+00

 

5.50E-01

 

0.0

008M

 

C-48

 

SULFIDES

 

Sulfides

 

50.6

 

26.9

 

22.4

 

32

 

2.80E-02

 

8.40E-03

 

5.60E-06

 

0

 

5.0

 

125


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 13.4-1       Permeability Rate and Fines Content at Various Simulated Heap Heights

 

 

Figure 13.4-2       Permeability Rate and Rock Type at Various Simulated Heap Heights

 

126


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

13.5                        Estimated Field Recoveries, Leach Times and Reagent Requirements

 

Column leach tests on ROM and coarse crushed column leach tests by KCA, Rio Alto and Tahoe were used in estimating field recoveries, leach times and reagent requirements. These leach test results are summarized in Table 13.5-2.

 

13.5.1     ROM Field Design Parameters

 

The column leach tests conducted on ROM composites or on composites coarse crushed to 100mm or greater were used in the estimation of ROM field data. Data supplied by Tahoe indicate a preliminary p80 ROM size of approximately 100mm to 150mm. Since there are insufficient test results on individual rock types, the results from these series of tests were averaged to estimate the field recoveries, leach times and reagent requirements.

 

For the series of column tests labelled as ROM or at sizes of 100mm or greater (items one through eight as presented in Table 13.5-2), the average gold recovery is 76%. Silver recoveries are low and average 12%. The average sodium cyanide consumption and lime requirement are 0.28 kg/t ore and 2 kg/t ore, respectively.

 

Based on field experience, KCA reduces the column test recoveries by 2-3% for gold and 2-5% for silver for the field recoveries. Factors applied to laboratory column leach test results to estimate field sodium cyanide consumptions on clean, oxide ores vary by column size (weight of sample tested), test procedures, and cyanide strength in the barren leach solutions. Typically, KCA uses 25% to 33% of the column cyanide consumption in smaller columns (generally 75mm to 150mm in diameter and up to 2m in height) and up to 70% to 80% on tests conducted on larger samples (500mm+ in diameter by 6m in height). Cyanide strength in the leach solutions are generally in the 500 to 1000 ppm NaCN range. Based on discussions with Tahoe personnel and KCA’s experience, a factor of approximately 70% was used for ROM ore as most of the tests were conducted in larger columns. Field lime requirements are generally close to the laboratory test results.

 

KCA typically estimates the field leach cycle duration from column leach test data. The method includes studying the shape of the recovery versus solution to solids ratio curve (tonnes of solution per tonne of ore) to determine where it starts to bend. The “solution to solids ratio” at the bend is converted to field time using the heap’s solution application rate, stacked ore density and lift height. The recovery versus time curve is then studied to estimate the days between the bend and when leaching is complete. The days are summed to determine a total leach time.

 

127


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Several of the ROM column tests conducted at La Arena were evaluated for the above information. The “bend” occurs in the 0.3 to 0.5 tonnes of solution per tonne of ore range. Additional leach time to reach the flat part of the curve generally varies from 40 to 60 days. Therefore, at a lift height of 12 meters and a solution application rate of 10 L/hr/m2, a total leach time of 80 days is recommended. Increasing the lift height to 16 meters, the total leach time recommended increases to 90 days. On multiple lift heaps, additional leach time may be required to wash out pregnant leach solutions in lower lifts during upper lift leaching.

 

Therefore, for oxide ROM ore and assuming no permeability or fines migration issues, KCA estimates the parameters shown in Table 13.5-1 for this study.

 

Table 13.5-1        KCA Oxide Ore Parameters - No Permeability or Fines Migration Issues

 

Parameter

 

 

KCA Recommendation

Gold Recovery

 

 

73%

Silver Recovery

 

 

7%

NaCN Consumption

 

 

0.2 kg/t

Lime Requirement

 

 

2.0 kg/t

Leach Time

 

 

80 days (minimum, 12 meter lifts)

 

128


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 13.5-2        Column Test Results Used in Estimating Field Design Criteria

 

Item

 

 

 

 

 

 

 

 

Size

 

 

Head

 

 

Head

 

 

Extraction

 

 

Extraction

 

 

NaCN

 

 

Lime

 

 

Cement

 

 

Days

 

No.

 

 

Test ID / Col No.

 

 

Description

 

 

mm

 

 

Au g/t

 

 

Ag g/t

 

 

Au %

 

 

Ag %

 

 

Cons kg/t

 

 

kg/t

 

 

kg/t

 

 

Leached

 

1

 

 

KCA 60909

 

 

Global Composite A & B

 

 

102 (p80)

 

 

0.94

 

 

3.1

 

 

85

 

 

22

 

 

0.52

 

 

0

 

 

5.95

 

 

71

 

2

 

 

KCA 60978

 

 

P2, Zonal Moyan

 

 

240 (p80)

 

 

0.095

 

 

0.67

 

 

62

 

 

27

 

 

0.10

 

 

0

 

 

5.74

 

 

56

 

3

 

 

C-1

 

 

Truck 1, Sandstone

 

 

ROM

 

 

0.325

 

 

4.7

 

 

75

 

 

4.5

 

 

0.20

 

 

2.3

 

 

0

 

 

60

 

4

 

 

C-3

 

 

Truck 1, Sandstone

 

 

100 (p100)

 

 

0.311

 

 

4.9

 

 

76

 

 

4.6

 

 

0.28

 

 

2.2

 

 

0

 

 

60

 

5

 

 

C-1

 

 

Truck 2: 1:2 Sample 514420 : Sample 514416

 

 

ROM

 

 

1.76

 

 

8.8

 

 

76

 

 

2.9

 

 

0.26

 

 

1.8

 

 

0

 

 

80

 

6

 

 

C-2

 

 

Truck 2: Sample 514420

 

 

ROM

 

 

0.474

 

 

2.1

 

 

78

 

 

13

 

 

0.22

 

 

1.8

 

 

0

 

 

80

 

7

 

 

C-3

 

 

Truck 2: Sample 514425

 

 

150 (p100)

 

 

0.967

 

 

3.5

 

 

84

 

 

11

 

 

0.32

 

 

1.9

 

 

0

 

 

81

 

8

 

 

C-4

 

 

Truck 2: 1:2 Sample 514420 : Sample 514417

 

 

150 (p100)

 

 

0.861

 

 

2.0

 

 

70

 

 

13

 

 

0.34

 

 

2.0

 

 

0

 

 

81

 

9

 

 

KCA 60991

 

 

P1, Zona Este, Huangamarca

 

 

45 (p80)

 

 

0.196

 

 

0.40

 

 

83

 

 

25

 

 

0.22

 

 

0

 

 

5.97

 

 

66

 

10

 

 

KCA 61648

 

 

KCA Old Core, 1:1 Coarse:Fines Mix

 

 

50.9 (p80)

 

 

1.095

 

 

7.1

 

 

89

 

 

10

 

 

0.67

 

 

3.06

 

 

0

 

 

58

 

11

 

 

KCA 61651

 

 

KCA Old Core, 1:2 Coarse:Fines Mix

 

 

39.7 (p80)

 

 

1.054

 

 

6.4

 

 

89

 

 

10

 

 

0.68

 

 

3.02

 

 

0

 

 

58

 

12

 

 

C-15

 

 

Surface, PM1, Sandstone

 

 

75 (p100)

 

 

5.57

 

 

808

 

 

80

 

 

3.3

 

 

0.48

 

 

2.2

 

 

0

 

 

60

 

13

 

 

C-16

 

 

Surface, PM1, Sandstone

 

 

75 (p100)

 

 

5.57

 

 

808

 

 

80

 

 

3.3

 

 

0.60

 

 

2.3

 

 

0

 

 

60

 

14

 

 

C-17

 

 

Surface, PM2, Sandstone

 

 

75 (p100)

 

 

0.17

 

 

7.1

 

 

83

 

 

3.7

 

 

0.12

 

 

1.1

 

 

0

 

 

23

 

15

 

 

C-18

 

 

Surface, PM2, Sandstone

 

 

75 (p100)

 

 

0.17

 

 

7.1

 

 

84

 

 

3.5

 

 

0.17

 

 

1.1

 

 

0

 

 

23

 

16

 

 

C-8

 

 

Surface, PM1+PM2 Blend

 

 

75 (p100)

 

 

2.55

 

 

361

 

 

83

 

 

5.2

 

 

1.25

 

 

1.5

 

 

0

 

 

60

 

17

 

 

C-9

 

 

Truck 2: Sample 514416

 

 

76 (p100)

 

 

3.44

 

 

11

 

 

74

 

 

6.7

 

 

0.45

 

 

2.7

 

 

0

 

 

77

 

18

 

 

C-11

 

 

Truck 2: Sample 514425

 

 

76 (p100)

 

 

1.38

 

 

4.0

 

 

78

 

 

14

 

 

0.37

 

 

2.5

 

 

0

 

 

77

 

19

 

 

C-12

 

 

Truck 2: Sample 514417

 

 

76 (p100)

 

 

1.06

 

 

3.3

 

 

68

 

 

14

 

 

0.54

 

 

2.6

 

 

0

 

 

83

 

20

 

 

C-13

 

 

Truck 2: Sample 514420

 

 

76 (p100)

 

 

0.472

 

 

2.5

 

 

81

 

 

17

 

 

0.51

 

 

2.2

 

 

0

 

 

83

 

Averages Items 1 through 8

 

 

 

 

 

0.72

 

 

3.7

 

 

76

 

 

12

 

 

0.28

 

 

2.00

 

 

 

 

 

71

 

Averages Items 9 through 20

 

 

 

 

 

1.89

 

 

169

 

 

81

 

 

10

 

 

0.51

 

 

2.02

 

 

 

 

 

61

 

 

129


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

13.5.2     Primary Crushed Ore Field Design Parameters

 

The column leach tests conducted on composites crushed to nominally -76mm were used in the estimation of the coarse crushed ore field design parameters. Data supplied by the crusher manufacturer indicate a preliminary p80 crush size ranging from approximately 60mm to 85mm. There are insufficient test results at the primary crushed ore size to estimate field operating data by individual rock types.

 

For the series of column tests labelled as 76mm down to 45mm (items 12 through 20 as presented in Table 13.5-2), the results from similar composites were combined to prevent one rock type or sample location from biasing the averages. There are several potential combinations, all of which lead to average gold recoveries in the 81% to 83% range. For this study, KCA used the results shown in Table 13.5-4 to estimate field recoveries and reagent requirements.

 

Estimates for field gold and silver recoveries were made based on the deductions discussed in Section 13.4.1. However, the low silver recovery from the test on the very high silver grade sample (Item 16) was not used. This leads to an average non-deducted silver recovery of 16%.

 

Sodium cyanide consumption averaged 0.65 kg/t. Based on discussions with Tahoe personnel and KCA’s experience, an average sodium cyanide consumption rate of 0.3 kg per tonne of ore was used. This equates to a factor of approximately 45% of the average consumption.

 

Cement and lime requirements are difficult to estimate based on the lack of data from tests that simulate the planned processing flow sheet on coarse crushed material. The current flow sheet includes primary crushing, then screening at 76mm. The minus 76mm material is agglomerated with 6 kg cement per tonne of minus 76mm ore, then recombined with the plus material prior to conveyor stacking on the heap. Lime is also added at a rate of 1 kg per tonne of ore (whole ore). The cement addition rate appears reasonable based on KCA’s and Anddes’ compacted permeability test results. However, no permeability tests on screened minus 76mm composites have been conducted.

 

Field leach time on coarse crushed ore was estimated in a similar manner as the ROM leach time. Several of the minus 76mm tests were evaluated and leach times determined. There are significant variations in the shapes of the curves, especially when comparing KCA’s and La Arena’s tests. KCA’s tests indicate a “bend” at about 0.4 tonne solution per tonne ore while the “bend” in some of La Arena’s tests are in the 0.5 to 1 tonne solution per tonne ore range. A couple of La Arena’s test had no “bend” in the leach curves. Additional leach time determined from the leach time curves varies from 30 to 60 days. For this study, a 0.4 tonne solution per tonne ore ratio was used with another 40 days of additional leach time. Therefore, at a lift height of 12 meters and a solution application rate of 10

 

130


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

1/hr/m2, a total leach time of 70 days is recommended on coarse crushed ore. Increasing the lift height to 16 meters, the total leach time recommended increases to 80 days. On multiple lift heaps; additional leach time may be required to remove pregnant leach solutions in lower lifts during upper lift leaching.

 

Therefore, for oxide ore crushed to a p80 in the 60mm to 85mm range, KCA estimates the parameters shown in Table 13.5-3 for this pre-feasibility study.

 

Table 13.5-3        KCA Oxide Ore Recommendation - Crushed to p80 (60mm - 85mm range)

 

Parameter

 

 

KCA Recommendation

Gold Recovery

 

 

80%

Silver Recovery

 

 

12%

NaCN Consumption

 

 

0.3 kg/t

Lime Requirement

 

 

1.0 kg/t (whole ore)

Cement Requirement

 

 

6.0 kg/t (-76mm screened material)

Leach Time

 

 

70 days (minimum, 12 meter lifts)

 

131


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 13.5-4                         Test Results Used to Determine Field Parameters on Coarse Crushed Ore

 

 

 

 

 

 

 

 

 

 

 

 

 

Head Grade

 

 

Extraction

 

 

Reagent Consumption

 

 

 

 

Item

 

 

Test ID / Column No.

 

 

Description

 

 

Avg Size
(mm)

 

 

Au g/t

 

 

Ag g/t

 

 

Au %

 

 

Ag %

 

 

NaCN
kg/t

 

 

Lime
kg/t

 

 

Cement
kg/t

 

 

Days
Leached

 

9

 

 

KCA 61648

 

 

P1, Zona Este, Huangamarca

 

 

45 (p80)

 

 

0.196

 

 

0.4

 

 

83

 

 

25

 

 

0.22

 

 

0

 

 

5.97

 

 

66

 

10 & 11

 

 

KCA 61648/651

 

 

KCA Old Core
1:1 & 1:2 Coarse:Fines

 

 

45 (p80)

 

 

1.07

 

 

6.7

 

 

89

 

 

10

 

 

0.68

 

 

3.04

 

 

0

 

 

58

 

16

 

 

C-8

 

 

Surface, PM1+PM2 Blend

 

 

75 (p100)

 

 

2.55

 

 

361

 

 

83

 

 

5.2

 

 

1.25

 

 

1.5

 

 

0

 

 

60

 

17 - 20

 

 

C-9,-11,-12,-13

 

 

Truck 2 Samples

 

 

76 (p100)

 

 

1.59

 

 

5.14

 

 

75

 

 

13

 

 

0.47

 

 

2.5

 

 

0

 

 

80

 

Averages

 

 

 

 

 

 

 

 

1.35

 

 

93

 

 

83

 

 

13

 

 

0.65

 

 

1.8

 

 

 

 

66

 

 

132


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

13.6                        Recommendations and Conclusions

 

The results of the laboratory testing program indicate excellent gold recoveries at both run-of-mine (ROM) and moderate crush sizes with low to moderate reagent requirements implying amenability to heap leaching. Silver recoveries are generally low. Maintaining heap permeability and minimizing channeling at higher heap heights constitutes a risk to the project as additional agglomeration and compacted permeability testing is required.

 

Tahoe recently started leaching ROM ore on a newly constructed heap leach facility at Shahuindo. Leach pad area will be available to conduct field ‘pilot-scale’ heap leach tests. This would be ideal for conducting additional tests on near-surface ROM ore composites. The following is recommended for these tests:

 

·                  Tests on sandstone/siltstone/breccia blends similar to the mine plan at grades similar to those planned for ROM leaching.

 

·                  Tests on individual rock types of sandstone and breccia with low fines content.

 

The available data indicate that siltstones and breccia with high fines content will most likely not percolate in a ROM heap leach. However, if these two rock types pass the compacted permeability tests with no cement required at the recommended coarse crush size, then consideration should be given to conducting a pilot-scale test on the ROM pad on a composite of these two rock types.

 

Splits from each composite tested in the pilot-scale tests should be taken and column leach tests conducted at a coarse crush size of approximately 80% passing 76mm.

 

Column leach tests on both surface and large diameter core samples should be conducted on each of the rock types (except sulfides) at a p80 crush size of 76mm. The samples should be spatially representative of the orebody. Large diameter core holes should twin the latest metallurgical drill holes so the results from the series of column leach tests on the minus 25mm tests can be compared to the 76mm test results. The gold grades of the individual rock types to be tested should be similar to those estimated in the mine plan.

 

Assays for sulfide sulfur, iron, arsenic, mercury and copper should be conducted on each composite tested. Mercury in leach solutions and adsorbed onto carbon should be followed in the next series of tests. Mercury levels in past tests have been low but still present in sufficient quantities that a retort is required to control mercury emissions.

 

Compacted permeability tests on each rock type from the large core drilling program on composites crushed to 76mm should be conducted. A few tests on blended composites containing the different

 

133


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

rock types in a similar ratio as is planned in crushed ore production should also be conducted. Tests at cement levels of 0, 3 and 6 kg/t at varying simulated heap heights up to the maximum planned height above the liner should be completed. If any samples fail, then additional composites should be tested with increased levels of cement until passing percolation rates are achieved at all simulated heights.

 

The potential fines migration issue found in several of the non-agglomerated La Arena column leach tests needs to be evaluated further. The operation of the ROM leach pad and the pilot-scale tests should provide sufficient data to determine if fines migration will be an issue or not.

 

The addition of a secondary crusher should be studied as the data indicate a recovery difference between a 76mm and 25mm crush size of about 4 to 5 percentage points. A trade-off study should be conducted to determine if the additional recovery justifies the increased capital and operating costs of a secondary crushing circuit.

 

134


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.0                        MINERAL RESOURCES ESTIMATE

 

14.1                        Introduction

 

Mineral resource estimation described in this Technical Report for the Shahuindo Project adheres to the guidelines of Canadian National Instrument 43-101. The mineral resources described in this section are based on all drilling completed as of 15 April 2015. A major infill drill program (24,522m) of predominantly RC drilling on 25m x 25m spacing was completed in 2015 with the intent to convert Indicated Resources to Measured Resources within the majority of the oxide resource predominantly inside a $1,400 open pit whittle optimization shell.

 

Hard-boundary domains based on lithologic contacts were used for grade estimation within the intrusive and colluvium lithologies. The grade of mineralization within all other lithologies was estimated within nominal 0.1 g/t Au bulk style interpretations (i.e., grade domain shells), completed in section and plan view. These interpretations are very similar to those completed in 2012; however, the higher-grade domains that were interpreted in 2012 based on a predominantly 50m x 50m drill spacing have been removed in this resource as the recent infill drilling on 25m x 25m spacing does not support the continuity previously suggested. The influence of higher grades in the model was restricted by the use of multiple-pass estimation routines using decreased estimation ranges, further discussed in Section 14.7.

 

Block model cell sizes and grade interpolation methodologies are both similar to parameters used in the 2012 estimate. The parameters chosen were done so in an attempt to reduce any potential localized smearing of gold or silver grades, particularly as the higher grade domains from the 2012 estimate were removed as hard constraints for grade estimation in this update.

 

14.2                        Database

 

The drill data includes all historical drilling and the infill drilling data completed in April 2015. The drill hole information includes collar, downhole survey, assay, lithology and oxidation data. The cut-off date for the database was 15 April 2015.

 

All historical data has been transformed from PSAD 56 datum to WGS 84 datum using the transformation noted below in Table 14.2-1. Drill hole collars laid out in 2014 and 2015 were done relative to the WGS 84 datum.

 

Table 14.2-1                         Grid Transformation Applied to Collar Data in Database

 

EASTING WGS 84

=

EASTING PSAD56

- 260.9878149 m

NORTHING WGS 84

=

NORTHING PSAD56

- 368.5484922 m

 

135


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The drill hole database used for this resource estimate contains 1,039 holes for 164,015 meters. There are 105 drill holes that were not used in the estimate as these holes were either condemnation holes or exploration holes drilled well outside the area of the reportable resource.

 

The majority of the drilling is on either a nominal 50m x 50m grid or was infill RC drilled to a nominal 25m x 25m grid in 2014 and 2015 (Figure 14.2-1), predominantly within the upper portion of the oxide domain. Gaps in the oxide resource still exist on both nominal grids; these gaps are caused either by topography, or they are areas deeper in the oxide portion of the deposit that were not targeted for infill drilling at this stage in the project. The sulfide mineralization is drilled more sporadically than the oxide domain, as it is of secondary importance to the project in this point in time.

 

Assays below detection were set at 50% of the detection limit.

 

The topographic surface bounding the upper elevations of the model was formed from the 2m contour surface generated from the 2009 Horizon aerial survey.

 

 

Figure 14.2-1                    Plan Projection Displaying Zones of Infill Drilling at 25m x 25m Spacing

 

136


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.3                        Geological Modeling

 

14.3.1              Lithologic Domains

 

The intrusive and colluvium lithologic domains were updated for this resource and a breccia lithologic domain was added to the model based on new data and interpretation. The intrusive, previously ‘bulked up’ on 8m plan interpretations, was refined by wireframing the unit in Leapfrog® and Maptek Vulcan™. The sediments were relogged on 100m centers (diamond core only) in an attempt to construct bulk mining domains of sandstone, siltstone and breccia. This was ultimately unsuccessful due to the nature of the geology and the wide spaced section lines. This work is ongoing on a much finer scale (50m and 25m sections) and will be incorporated in future resource updates.

 

The additional data from the 25m x 25m infill RC drilling has increased the confidence of the volume and grade estimate of the colluvium. The intrusive was interpreted on 8m plans in the 2012 resource, so the creation of a valid wireframe in this update is a good advance for more reliable local estimates on the boundaries of the intrusive and the sediments.

 

The relogging program on 100m centers was completed in an effort to try to define larger (mineable) sandstone and siltstone-dominant rock packages for use as geometallurgical domains. This was ultimately unsuccessful, due to conflicts with data between neighboring drill holes on section, and between data on the intervening 50m and 25m cross sections. The interim solution, for this resource update, was to interpolate sandstone, siltstone, and mixed sandstone and siltstone lithologies by means of a spherical (50m ellipse) nearest neighbor estimate.

 

The rationalization of multiple types of logged breccia from historical core (on 100m centers) into one breccia code was completed. The interpretation was bulked up into 8m plans and this was used to hard code the resource model (Figure 14.3-1). The interpretations on 100m centers showed moderate to good visual correlation with the sections on 50m and 25m centers.

 

137


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 14.3-1                    Lithologic Domains — Section E400

 

14.3.2              Structural Domains

 

Two primary structural domains were used in the resource model, with the division between the two domains being the Choloque Fault (Figure 14.3-2). Tahoe has identified a distinct difference in the consistency of mineralization on either side of the Choloque Fault; where south of the Choloque Fault, the mineralization is generally consistent in thickness and attitude and north of the Choloque Fault, the mineralization is less consistent in thickness and attitude and appears to be much more disrupted by northeast and northerly trending structures.

 

Within the primary structural domains, 23 sub-domains have been interpreted and modeled on cross section in the southern area and six sub-domains modelled in the northern area that are much broader than those in the southern area of the deposit. The sub-domains are reflective of local changes in the strike and dip of the mineralization due to the intense folding of the host strata.

 

138


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 14.3-2                    Plan Projection of Structural Domains

 

14.3.3              Oxidation Domains

 

An oxidation model of the deposit spatially defines two zones: an oxide-dominant zone and a sulfide-dominant zone. The oxidation zones are based on cross-sectional interpretations of the presence of oxide and sulfide minerals from diamond core logging. The mixed oxide/sulfide transitional zone in the central core of the deposit is very thin and irregular; preference was given to code transitional material as sulfide, particularly when reviewing the total sulfur assays. The oxide/sulfide surface was wireframed in Leapfrog® and adjusted in Maptek Vulcan™ as necessary to remove any inconsistencies based on spurious data from individual drill holes.

 

14.4                        Grade Estimation Domains

 

14.4.1              Gold Estimation Domains

 

Gold estimation domains were interpreted using a 0.1 g/t Au cut-off boundary. In many areas, the 0.1 g/t Au cut-off is a clear natural break when reviewing the drill data statistically and on cross section in the southern portion of the deposit. There is no clear statistical cut-off for the northern domains, so the same lower grade cut-off as the southern domain was used for consistency.

 

139


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The sub-domains modelled to reflect the differing geometric orientations of the mineralization were constructed on cross section in the southern portion of the deposit and on level plans for the northern portion of the deposit. The sub-domain boundaries in the southern portion were snapped to drill holes as the 0.1 g/t Au grade boundary in this area is reasonably sharp (Figure 14.4-1). The plan interpretations of the northern domains were not snapped to drill holes as the grade boundaries are not always distinct (Figure 14.4-2).

 

The 0.1 g/t Au domain boundary transgresses all sedimentary rock types, with higher grades either located along contacts with the intrusive bodies, trending in a NNW direction, or occasionally displaying a north to northeast alignment along second order structures. Gold grades encountered in the breccia bodies are highly variable, ranging from <0.05 g/t to +10 g/t. The intrusive appears mineralized in some areas of the southern domains and gold grades have been estimated for the intrusive in this area. In the northern domains, the intrusive has very little mineralization and a default grade below the cut-off grade has been applied to the intrusive in this area.

 

Results from infill RC drill holes, completed on 25m x 25m spacing in 2015 do not support the use of higher grade gold cut-off domains as the additional drill data shows that there is more discontinuity at short to medium ranges for higher grade mineralization than previously modeled. It is thought that the effect of the north to northeast trending structures (and possibly other structures) that cut across the main north-northwest trend of mineralization are the cause of this lack of continuity. Infill drilling is ongoing to improve confidence in the structural model in this area.

 

The 0.1 g/t Au domains are considered sufficient to constrain the grade interpolation, given the reasonably dense drilling completed in 2015. Within the 0.1 g/t Au domain, the interpolation of higher grades were restricted during the estimation process (discussed further in Section 14.8).

 

140


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 14.4-1       Au Interpretation - Southern Domains (Cross Section E1200)

 

141


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 14.4-2       Au Interpretation - Northern Domains (Cross Section E400)

 

142


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.4.2     Silver Estimation Domains

 

There is a close correlation between the distribution of gold and silver grades in the Shahuindo deposit; as such, the gold estimation domains were used to constrain the silver estimate. The 0.1 g/t Au domains were viewed as sufficient to constrain the silver grade interpolation. There are very rare occurrences where some isolated silver grades fall outside the 0.1 g/t Au domains, but this is not considered material to the estimate.

 

14.4.3     Other Estimation Domains

 

A suite of other minor elements were also estimated into the model to assist in waste rock characterization studies. These elements have little to no economic impact on the oxide resource or reserve estimate. The minor elements estimated include sulfur, copper, lead, zinc, arsenic, molybdenum, calcium, total iron, sodium and manganese.

 

A review of each element was undertaken in three dimensions and statistically to determine appropriate domains for estimation. A variety of constraints were applied where appropriate, based upon combinations of rock type, oxidation state and gold mineralization domains. A more detailed analysis of the minor elements is presented in Section 14.5 of this report.

 

14.4.4     Sample Selection and Compositing

 

Data from both RC and diamond core were used in this estimate.

 

Data in the northern sub-domains were selected using a plan projection of +/- 4m elevation around the 8m plan interpretations. Data within the southern domains were selected within the cross sectional wireframes. Samples were composited based on combinations of rock type, mineralized domain and oxidation state, depending upon the element concerned. This is explained in more detail in the statistics section.

 

Samples were composited to nominal 2m lengths for all domains, compositing on a best fit length rather than a standard length ensuring no loss of sample in the compositing process. A 2m composite length was chosen as it is 50% of the thickness of a 4m block model cell height, which allows for some short scale ‘granularity’ in the estimate in an attempt to reflect short scale grade variability.

 

143


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.5        Statistics

 

14.5.1     Bulk Density

 

Rock density (specific gravity) was interpolated into the model using nearest neighbour estimates; density values by rock type are presented in Table 14.5-1.

 

Table 14.5-1        Descriptive Statistics of Shahuindo Density Values by Rock Type

 

 

 

 

SG

 

 

Specific Gravity Statistics (g/cm3)

Rock Type

 

 

(g/cm3)

 

 

Count

 

 

Mean

 

 

Median

 

 

Min

 

 

Max

 

 

Std Dev

 

Overburden

 

 

1.80

*

 

15

 

 

2.11

 

 

2.07

 

 

1.68

 

 

2.59

 

 

0.26

 

Unsilicified Sediment (Oxide)

 

 

2.29

 

 

127

 

 

2.31

 

 

2.33

 

 

1.69

 

 

2.69

 

 

0.17

 

Silicified Sediment (Oxide)

 

 

2.37

 

 

57

 

 

2.37

 

 

2.45

 

 

1.83

 

 

2.59

 

 

0.20

 

All Sediment (Mixed)

 

 

2.55

 

 

36

 

 

2.57

 

 

2.61

 

 

2.09

 

 

2.91

 

 

0.18

 

Unsilicified Sediment (Sulfide)

 

 

2.45

 

 

125

 

 

2.50

 

 

2.49

 

 

1.40

 

 

3.40

 

 

0.30

 

Silicified Sediment (Sulfide)

 

 

2.58

 

 

39

 

 

2.63

 

 

2.64

 

 

2.16

 

 

3.40

 

 

0.26

 

Porphyry (Oxide-Mixed)

 

 

2.04

 

 

132

 

 

2.06

 

 

2.09

 

 

1.45

 

 

2.64

 

 

0.25

 

Porphyry (Sulfide)

 

 

2.25

 

 

46

 

 

2.26

 

 

2.31

 

 

1.71

 

 

2.75

 

 

0.27

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mineralized Material (Oxide-Mixed only)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Unsilicified Low Grade (~0.1-0.7 g/t Au)

 

 

2.15

 

 

268

 

 

2.18

 

 

2.20

 

 

1.54

 

 

2.90

 

 

0.25

 

Silicified Low Grade

 

 

2.30

 

 

227

 

 

2.32

 

 

2.36

 

 

1.59

 

 

2.87

 

 

0.23

 

Unsilicified Moderate Grade (0.7-2.0 g/t Au)

 

 

2.13

 

 

178

 

 

2.17

 

 

2.18

 

 

1.40

 

 

2.66

 

 

0.26

 

Silicified Moderate Grade

 

 

2.25

 

 

78

 

 

2.26

 

 

2.34

 

 

1.40

 

 

2.72

 

 

0.28

 

Unsilicified High Grade (>2.0 g/t Au)

 

 

2.10

 

 

40

 

 

2.15

 

 

2.17

 

 

1.45

 

 

2.62

 

 

0.28

 

Silicified High Grade

 

 

2.20

 

 

25

 

 

2.32

 

 

2.35

 

 

1.91

 

 

2.61

 

 

0.23

 

 


* assigned value

 

14.5.2     Gold Statistics

 

The density of gold data is reasonably uniform and did not warrant any form of declustering prior to analysis. The statistics on the 2m composites are very similar for both oxide and sulfide domains and support the use of a soft boundary between the oxide and sulfide domains for estimation purposes (Figure 14.5-1).

 

144


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 14.5-1       Gold statistics plots for all domains

 

Gold distribution of the 2m composites are typically well structured, with minimal outliers; hence very limited grade capping was applied. The only exception to this is domain 1200, which is the intrusive in the southern domain. There are some sporadic higher grades within this domain that required more restrictive capping.

 

Detailed statistics are only presented for the oxide domains (Table 14.5-2) as the sulfide domain is Inferred and has little materiality to the project at this stage in development. Similar criteria have been applied to upper cuts on gold composites within the sulfide domain as per the oxide domain.

 

145


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.5-2        Descriptive Statistics for Gold Oxide Domains

 

 

 

 

Sub-

 

 

Num of

 

 

Mean

 

 

Median

 

 

Std

 

 

 

 

 

Min

 

 

Max Au

 

 

Capping

 

 

Percentile

Domain

 

 

Domain

 

 

Comps

 

 

Au g/t

 

 

Au g/t

 

 

Dev

 

 

CV

 

 

Au g/t

 

 

g/t

 

 

Au g/t

 

 

Applied

North

 

 

11

 

 

7,816

 

 

0.39

 

 

0.21

 

 

0.82

 

 

2.08

 

 

0

 

 

37.17

 

 

7

 

 

0.50

%

North

 

 

22

 

 

219

 

 

0.49

 

 

0.25

 

 

0.7

 

 

1.44

 

 

0.005

 

 

4.44

 

 

NC

 

 

NA

 

North

 

 

44

 

 

1,287

 

 

0.55

 

 

0.21

 

 

1.74

 

 

3.15

 

 

0.005

 

 

26.52

 

 

25

 

 

0.15

%

North

 

 

55

 

 

14,171

 

 

0.52

 

 

0.25

 

 

1.18

 

 

2.29

 

 

0

 

 

37.36

 

 

20

 

 

0.05

%

North

 

 

66

 

 

428

 

 

0.33

 

 

0.19

 

 

0.63

 

 

1.92

 

 

0

 

 

9.28

 

 

6

 

 

0.50

%

South

 

 

1001

 

 

3,933

 

 

0.6

 

 

0.31

 

 

1.1

 

 

1.84

 

 

0.005

 

 

16.65

 

 

8

 

 

0.70

%

South

 

 

1002

 

 

790

 

 

0.38

 

 

0.25

 

 

0.47

 

 

1.23

 

 

0.005

 

 

5.07

 

 

NC

 

 

NA

 

South

 

 

1003

 

 

2,617

 

 

0.51

 

 

0.27

 

 

1.38

 

 

2.72

 

 

0.005

 

 

57.29

 

 

8

 

 

0.50

%

South

 

 

1004

 

 

165

 

 

0.34

 

 

0.24

 

 

0.35

 

 

1.03

 

 

0.02

 

 

3.37

 

 

NC

 

 

NA

 

South

 

 

1006

 

 

34

 

 

0.3

 

 

0.15

 

 

0.58

 

 

1.94

 

 

0.05

 

 

3.06

 

 

NC

 

 

NA

 

South

 

 

1007

 

 

901

 

 

0.34

 

 

0.22

 

 

0.56

 

 

1.68

 

 

0.005

 

 

12.52

 

 

6

 

 

0.15

%

South

 

 

1008

 

 

89

 

 

0.64

 

 

0.26

 

 

1.69

 

 

2.64

 

 

0.05

 

 

11.85

 

 

NC

 

 

NA

 

South

 

 

1009

 

 

627

 

 

0.4

 

 

0.23

 

 

0.63

 

 

1.59

 

 

0.011

 

 

8.35

 

 

NC

 

 

NA

 

South

 

 

1010

 

 

49

 

 

0.23

 

 

0.13

 

 

0.26

 

 

1.15

 

 

0.01

 

 

1.21

 

 

NC

 

 

NA

 

South

 

 

1011

 

 

40

 

 

0.21

 

 

0.15

 

 

0.21

 

 

0.97

 

 

0.007

 

 

0.86

 

 

NC

 

 

NA

 

South

 

 

1012

 

 

430

 

 

0.38

 

 

0.21

 

 

0.61

 

 

1.63

 

 

0

 

 

6.15

 

 

NC

 

 

NA

 

South

 

 

1013

 

 

22

 

 

0.52

 

 

0.45

 

 

0.21

 

 

0.41

 

 

0.2

 

 

1.08

 

 

NC

 

 

NA

 

South

 

 

1014

 

 

78

 

 

0.64

 

 

0.27

 

 

0.94

 

 

1.46

 

 

0.05

 

 

5.79

 

 

NC

 

 

NA

 

South

 

 

1015

 

 

35

 

 

0.45

 

 

0.35

 

 

0.54

 

 

1.2

 

 

0.005

 

 

3.34

 

 

NC

 

 

NA

 

South

 

 

1016

 

 

7

 

 

0.72

 

 

0.85

 

 

0.5

 

 

0.69

 

 

0.15

 

 

1.28

 

 

NC

 

 

NA

 

South

 

 

1018

 

 

7

 

 

0.56

 

 

0.43

 

 

0.51

 

 

0.91

 

 

0.12

 

 

1.63

 

 

NC

 

 

NA

 

South

 

 

1019

 

 

10

 

 

1.5

 

 

0.58

 

 

2.74

 

 

1.83

 

 

0.21

 

 

9.11

 

 

NC

 

 

NA

 

South

 

 

1020

 

 

14

 

 

0.24

 

 

0.23

 

 

0.2

 

 

0.81

 

 

0.08

 

 

0.87

 

 

NC

 

 

NA

 

South

 

 

1021

 

 

12

 

 

0.44

 

 

0.29

 

 

0.46

 

 

1.05

 

 

0.11

 

 

1.76

 

 

NC

 

 

NA

 

South

 

 

1022

 

 

31

 

 

0.57

 

 

0.27

 

 

0.71

 

 

1.24

 

 

0.09

 

 

3.15

 

 

NC

 

 

NA

 

South

 

 

1141

 

 

348

 

 

0.53

 

 

0.28

 

 

0.88

 

 

1.66

 

 

0.02

 

 

9.26

 

 

NC

 

 

NA

 

South

 

 

1200

 

 

9

 

 

2.97

 

 

0.3

 

 

3.21

 

 

1.08

 

 

0.12

 

 

6.51

 

 

6

 

 

30

%

South

 

 

1300

 

 

151

 

 

0.21

 

 

0.11

 

 

0.41

 

 

1.94

 

 

0.01

 

 

4.38

 

 

2

 

 

1.10

%

Total

 

 

34,320

 

 

0.48

 

 

0.24

 

 

1.09

 

 

2.26

 

 

0

 

 

57.29

 

 

 

 

 

 

 

 

146


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.5.3     Silver Statistics

 

The statistics for silver distribution (located within the 0.1 g/t Au domains) show sufficient differences between oxide and sulfide domains to warrant a hard estimation boundary (Figure 14.5-2). This is also evident when reviewing cross sections. The upper end of the distributions are a little less stable than the gold populations and hence slightly more aggressive upper cuts have been applied to silver composites in an attempt to reduce the risk of over-estimation of grade, particularly the domains with smaller amounts of data and erratic high grades.

 

Detailed statistics are only presented for the oxide domains (Table 14.5-3) as the sulfide domain is Inferred and has little materiality to the project at this stage in development.

 

 

Figure 14.5-2       Silver statistics plots for all domains

 

147


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.5-3        Descriptive Statistics for Silver Oxide Domains

 

 

 

 

Sub-

 

 

Num of

 

 

Mean

 

 

Median

 

 

Std

 

 

 

 

 

Min

 

 

Max

 

 

Capping

 

 

Percentile

Domain

 

 

Domain

 

 

Comps

 

 

Ag g/t

 

 

Ag g/t

 

 

Dev

 

 

CV

 

 

Ag g/t

 

 

Ag g/t

 

 

Ag g/t

 

 

Applied

North

 

 

11

 

 

7,816

 

 

3.89

 

 

1.35

 

 

11.89

 

 

3.05

 

 

0

 

 

367

 

 

90

 

 

0.5

%

North

 

 

22

 

 

219

 

 

5.71

 

 

4.07

 

 

7.6

 

 

1.32

 

 

0

 

 

64

 

 

NC

 

 

NA

 

North

 

 

44

 

 

1,287

 

 

6.44

 

 

2.85

 

 

14.49

 

 

4.23

 

 

0

 

 

255

 

 

80

 

 

0.9

%

North

 

 

55

 

 

14,171

 

 

9.10

 

 

2.40

 

 

38.45

 

 

2.29

 

 

0

 

 

2020

 

 

200

 

 

0.7

%

North

 

 

66

 

 

428

 

 

4.65

 

 

2.46

 

 

7.71

 

 

1.66

 

 

0

 

 

94.69

 

 

60

 

 

0.6

%

South

 

 

1001

 

 

3,933

 

 

7.0

 

 

3.23

 

 

14.6

 

 

2.08

 

 

0.05

 

 

270.56

 

 

100

 

 

0.7

%

South

 

 

1002

 

 

790

 

 

5.44

 

 

2.79

 

 

12.20

 

 

2.24

 

 

0.05

 

 

257

 

 

80

 

 

0.6

%

South

 

 

1003

 

 

2,617

 

 

7.13

 

 

3.90

 

 

14.49

 

 

2.03

 

 

0.05

 

 

339.05

 

 

100

 

 

0.6

%

South

 

 

1004

 

 

165

 

 

3.69

 

 

2.28

 

 

5.00

 

 

1.36

 

 

0.20

 

 

43.20

 

 

12

 

 

4.0

%

South

 

 

1006

 

 

34

 

 

1.0

 

 

0.80

 

 

0.51

 

 

0.52

 

 

0.05

 

 

2.30

 

 

NC

 

 

NA

 

South

 

 

1007

 

 

901

 

 

4.21

 

 

2.50

 

 

6.49

 

 

1.54

 

 

0.050

 

 

81.88

 

 

NC

 

 

NA

 

South

 

 

1008

 

 

89

 

 

15.02

 

 

2.55

 

 

47.43

 

 

3.16

 

 

0.30

 

 

290.50

 

 

100

 

 

2.5

%

South

 

 

1009

 

 

627

 

 

5.3

 

 

2.20

 

 

12.14

 

 

2.30

 

 

0.050

 

 

206.95

 

 

90

 

 

0.5

%

South

 

 

1010

 

 

49

 

 

3.24

 

 

1.08

 

 

7.69

 

 

2.37

 

 

0.23

 

 

51.08

 

 

NC

 

 

NA

 

South

 

 

1011

 

 

40

 

 

1.49

 

 

0.80

 

 

3.14

 

 

2.11

 

 

0.12

 

 

20.40

 

 

NC

 

 

NA

 

South

 

 

1012

 

 

430

 

 

6.62

 

 

3.00

 

 

17.06

 

 

2.58

 

 

0

 

 

189

 

 

NC

 

 

NA

 

South

 

 

1013

 

 

22

 

 

3.34

 

 

3.14

 

 

1.30

 

 

0.39

 

 

1.8

 

 

7.27

 

 

NC

 

 

NA

 

South

 

 

1014

 

 

78

 

 

23.66

 

 

3.29

 

 

66.48

 

 

2.81

 

 

0.05

 

 

477.47

 

 

95

 

 

7.0

%

South

 

 

1015

 

 

35

 

 

1.79

 

 

1.00

 

 

2.32

 

 

1.3

 

 

0.05

 

 

8.50

 

 

NC

 

 

NA

 

South

 

 

1016

 

 

7

 

 

2.05

 

 

1.60

 

 

1.5

 

 

0.72

 

 

0.30

 

 

4.40

 

 

NC

 

 

NA

 

South

 

 

1018

 

 

7

 

 

22.60

 

 

7.80

 

 

44.04

 

 

1.95

 

 

1.20

 

 

122

 

 

NC

 

 

NA

 

South

 

 

1019

 

 

10

 

 

9.2

 

 

3.20

 

 

16.49

 

 

1.79

 

 

1.20

 

 

54

 

 

20

 

 

7.5

%

South

 

 

1020

 

 

14

 

 

2.76

 

 

2.50

 

 

1.5

 

 

0.55

 

 

1.40

 

 

7.50

 

 

NC

 

 

NA

 

South

 

 

1021

 

 

12

 

 

6.35

 

 

7.55

 

 

4.23

 

 

0.70

 

 

1.00

 

 

13.32

 

 

NC

 

 

NA

 

South

 

 

1022

 

 

31

 

 

71.67

 

 

14.12

 

 

145.98

 

 

2.03

 

 

0.66

 

 

752.64

 

 

400

 

 

2.0

%

South

 

 

1141

 

 

348

 

 

8.18

 

 

2.50

 

 

24.47

 

 

2.99

 

 

0.05

 

 

382

 

 

150

 

 

0.5

%

South

 

 

1200

 

 

9

 

 

94.85

 

 

23.6

 

 

103.58

 

 

1.09

 

 

3.90

 

 

209

 

 

NC

 

 

NA

 

South

 

 

1300

 

 

151

 

 

2.18

 

 

1.10

 

 

3.61

 

 

1.65

 

 

0.05

 

 

36.30

 

 

8

 

 

4.0

%

Total

 

 

 

 

 

34,320

 

 

7.06

 

 

2.30

 

 

27.53

 

 

3.9

 

 

0

 

 

2020

 

 

 

 

 

 

 

 

148


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.5.4     Minor Elements

 

A suite of other minor elements were reviewed to mainly assist in waste rock characterization studies. These elements are termed ‘minor’ as they have little to no economic impact on the oxide resource or reserve estimate. The minor elements estimated are: sulfur, copper, lead, zinc, arsenic, molybdenum, calcium, total iron, sodium and manganese.

 

A review of each element was undertaken in three dimensions and statistically to determine appropriate domains for estimation. A variety of constraints were applied where appropriate, based upon combinations of rock type and oxidation state. Domains used for the estimation of the minor elements are summarized in Table 14.5-4; descriptive statistics of the minor element data is shown in Table 14.5-5. No upper cuts were applied to any of these elements for the estimation. Hard domains were used for minor element estimation.

 

Table 14.5-4        Hard Domains Used for Minor Element Estimation

 

Element

 

 

Domain 1

 

 

Domain 2

 

 

Domain 3

 

 

Domain 4

As

 

 

Colluvium

 

 

Intrusive

 

 

All Other Sediments-Oxide

 

 

All Other Sediments-Sulfide

Ca

 

 

Colluvium

 

 

Intrusive

 

 

All Other Sediments-Oxide

 

 

All Other Sediments-Sulfide

Cu

 

 

Colluvium

 

 

All Other Lithologies-Oxide

 

 

All Other Lithologies-Sulfide

 

 

 

Fe

 

 

Colluvium

 

 

Intrusive

 

 

All Sediments

 

 

 

Mn

 

 

Intrusive

 

 

All Other Lithologies-Oxide

 

 

All Other Lithologies-Sulfide

 

 

 

Mo

 

 

Colluvium

 

 

All Other Lithologies-Oxide

 

 

All Other Lithologies-Sulfide

 

 

 

Na

 

 

Colluvium

 

 

Intrusive

 

 

All Sediments

 

 

 

Pb

 

 

Colluvium

 

 

Intrusive

 

 

All Sediments

 

 

 

S

 

 

Intrusive-Sulfide

 

 

All Lithologies-Oxide

 

 

All Sediments-Sulfide

 

 

 

Zn

 

 

Colluvium

 

 

All Lithologies-Oxide

 

 

All Other Lithologies-Sulfide

 

 

 

 

149


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.5-5                         Description Statistics for Minor Elements

 

Element

 

 

Sub-Domain

 

 

Count

 

 

Mean

 

 

Median

 

 

Std
Dev

 

 

CV

 

 

Min

 

 

Max

 

 

Units

 

As

 

 

Colluvium

 

 

3,518

 

 

500.10

 

 

419.75

 

 

538.10

 

 

1.08

 

 

2.980

 

 

10,000

 

 

ppm

 

As

 

 

Intrusive

 

 

7,635

 

 

340.20

 

 

144.00

 

 

670.80

 

 

1.97

 

 

1.000

 

 

12,300

 

 

ppm

 

As

 

 

All Sediments-Oxide

 

 

44,530

 

 

697.40

 

 

492.00

 

 

846.30

 

 

1.21

 

 

1.000

 

 

31,800

 

 

ppm

 

As

 

 

All Sediments-Sulfide

 

 

17,278

 

 

652.30

 

 

417.00

 

 

885.00

 

 

1.36

 

 

1.000

 

 

18,500

 

 

ppm

 

Ca

 

 

Colluvium

 

 

3,342

 

 

0.03

 

 

0.01

 

 

0.06

 

 

1.93

 

 

0.005

 

 

1.79

 

 

%

 

Ca

 

 

Intrusive

 

 

7,151

 

 

0.10

 

 

0.03

 

 

0.23

 

 

2.26

 

 

0.005

 

 

3.41

 

 

%

 

Ca

 

 

All Sediments-Oxide

 

 

40,090

 

 

0.02

 

 

0.01

 

 

0.04

 

 

2.27

 

 

0.005

 

 

1.79

 

 

%

 

Ca

 

 

All Sediments-Sulfide

 

 

16,547

 

 

0.10

 

 

0.01

 

 

0.66

 

 

6.4

 

 

0.005

 

 

20.95

 

 

%

 

Cu

 

 

Colluvium

 

 

3,519

 

 

68.30

 

 

54.10

 

 

76.40

 

 

1.12

 

 

5.740

 

 

2,000

 

 

ppm

 

Cu

 

 

Other Lithologies-Oxide

 

 

58,036

 

 

68.70

 

 

27.80

 

 

303.20

 

 

4.41

 

 

 

 

24,728

 

 

ppm

 

Cu

 

 

Other Lithologies-Sulfide

 

 

23,488

 

 

641.10

 

 

98.90

 

 

2,746.80

 

 

4.47

 

 

 

 

197,375

 

 

ppm

 

Fe

 

 

Colluvium

 

 

3,342

 

 

4.36

 

 

4.21

 

 

2.19

 

 

0.5

 

 

0.190

 

 

33.29

 

 

%

 

Fe

 

 

Intrusive

 

 

7,151

 

 

2.98

 

 

2.56

 

 

2.21

 

 

0.74

 

 

0.090

 

 

25.86

 

 

%

 

Fe

 

 

All Sediments

 

 

53,295

 

 

5.20

 

 

4.54

 

 

3.27

 

 

0.63

 

 

0.020

 

 

37.62

 

 

%

 

Mn

 

 

Colluvium

 

 

3,342

 

 

124.30

 

 

44.00

 

 

311.80

 

 

2.51

 

 

1.000

 

 

8,444

 

 

ppm

 

Mn

 

 

Other Lithologies-Oxide

 

 

58,036

 

 

92.20

 

 

13.00

 

 

573.50

 

 

6.22

 

 

 

 

38,524

 

 

ppm

 

Mn

 

 

Other Lithologies-Sulfide

 

 

23,488

 

 

454.80

 

 

26.90

 

 

2,050.00

 

 

4.51

 

 

 

 

50,000

 

 

ppm

 

Mo

 

 

Colluvium

 

 

3,518

 

 

1.53

 

 

1.00

 

 

2.30

 

 

1.5

 

 

0.500

 

 

107.00

 

 

ppm

 

Mo

 

 

Other Lithologies-Oxide

 

 

58,036

 

 

1.30

 

 

0.75

 

 

2.17

 

 

1.68

 

 

 

 

107.00

 

 

ppm

 

Mo

 

 

Other Lithologies-Sulfide

 

 

23,488

 

 

1.26

 

 

1.00

 

 

1.91

 

 

1.52

 

 

 

 

99.30

 

 

ppm

 

Na

 

 

Colluvium

 

 

3,342

 

 

0.008

 

 

0.005

 

 

0.02

 

 

1.86

 

 

0.005

 

 

0.28

 

 

%

 

Na

 

 

Intrusive

 

 

7,151

 

 

0.017

 

 

0.010

 

 

0.070

 

 

4.060

 

 

0.005

 

 

2.11

 

 

%

 

Na

 

 

All Sediments

 

 

53,295

 

 

0.019

 

 

0.005

 

 

0.054

 

 

2.930

 

 

0.005

 

 

1.88

 

 

%

 

Pb

 

 

Colluvium

 

 

3,519

 

 

226.30

 

 

111.20

 

 

411.50

 

 

1.82

 

 

1.000

 

 

10,000

 

 

ppm

 

Pb

 

 

Intrusive

 

 

7,671

 

 

196.90

 

 

28.00

 

 

959.10

 

 

4.87

 

 

1.000

 

 

39,867

 

 

ppm

 

Pb

 

 

All Sediments

 

 

58,310

 

 

292.20

 

 

65.00

 

 

1,326.50

 

 

4.54

 

 

1.000

 

 

146,562

 

 

ppm

 

S

 

 

Intrusive-Sulfide

 

 

3,225

 

 

1.92

 

 

1.31

 

 

2.16

 

 

1.12

 

 

 

 

10.10

 

 

%

 

S

 

 

All Lithologies-Oxide

 

 

58,036

 

 

0.22

 

 

0.03

 

 

0.68

 

 

3.05

 

 

 

 

10.10

 

 

%

 

S

 

 

All Sediments-Sulfide

 

 

20,263

 

 

4.51

 

 

4.46

 

 

3.52

 

 

0.78

 

 

 

 

10.10

 

 

%

 

Zn

 

 

Colluvium

 

 

3,519

 

 

59.00

 

 

33.70

 

 

90.80

 

 

1.54

 

 

0.250

 

 

2,181

 

 

ppm

 

Zn

 

 

All Other Lithologies-Oxide

 

 

58,036

 

 

43.80

 

 

10.70

 

 

162.00

 

 

3.7

 

 

 

 

8,192

 

 

ppm

 

Zn

 

 

All Lithologies-Sulfide

 

 

23,488

 

 

680.60

 

 

48.30

 

 

2,880.00

 

 

4.23

 

 

 

 

109,418

 

 

ppm

 

 

150


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.6                        Variography

 

Gold and silver semi-variograms within the 0.1 g/t Au domain are generally poorly structured for most domains, even with log or normal score transformations applied. The major cause of the poor variogram structures appears to be the conflict of two shorter range mineralized structures which trend north and northeast within the overall mineralized north-northwest trend. This conflict is evident in most domains that have significant data points (Figure 14.6-1). The poor global variogram model for the overall strike of the domains contrasts with the improved variogram model aligned with the northerly or northeast trending short-scale structures. Removing these individual higher grade structures is not possible with the current data density. It is expected that closely-spaced blasthole information and in-pit mapping will aid in defining these structures more accurately.

 

In general, the nugget variance is moderate to high, generally greater than 50%. Ranges of continuity at the total sill are typically around 100-150m, with approximately 75% of the total variance typically seen in the first 25m (Figure 14.6-2). There is no apparent difference in the variograms between the northern and southern domains.

 

The results of the variography led to the use of inverse distance methods for grade estimation rather than ordinary kriging as there were concerns that the use of ordinary kriging would over-smooth the grade estimation relative to the composite grades.

 

 

Figure 14.6-1                    Horizontal Variogram Fan for Gold Domain 1001

 

151


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 14.6-2                    Variograms of Samples Along Strike

 

14.7                        Block Modelling

 

The resource block model was generated using Maptek Vulcan™ mining software and imported into Datamine. The parent block size is 4 mE x 8 mN x 4 mRL. A vertical cell size 4m was used to allow for bench height optimization studies. An 8 mE x 16 mN x 8 mRL background model was created around the resource interpretations in Datamine software to allow for Whittle pit optimizations.

 

All wireframes were checked visually to ensure that there was adequate filling with blocks. All gold domains were projected above the topographic surface, where appropriate, to ensure that there were no edge effects in volume filling, and then trimmed with the surface topography. The block model parameters are shown in Table 14.7-1. Each block was characterized by a series of attributes as described in Table 14.7-2.

 

Table 14.7-1                         Block Model Parameters

 

Parameter

 

 

East

 

 

North

 

 

Elevation

 

Minimum Coordinates

 

 

805,350

 

 

9,155,850

 

 

2,396

 

Maximum Coordinates

 

 

809,350

 

 

9,159,850

 

 

3,356

 

Parent Block size (m)

 

 

4

 

 

8

 

 

4

 

Minimum Sub-Block Size (m)

 

 

1

 

 

2

 

 

1

 

 

152


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.7-2                         Block Model Attributes List

 

Attribute

 

 

Description

IJK

 

 

Parent Cell Identifier

XC

 

 

Centroid of cell easting

YC

 

 

Centroid of cell northing

ZC

 

 

Centroid of cell RL

XINC

 

 

Cell easting dimension

YINC

 

 

Cell northing dimension

ZINC

 

 

Cell RL dimension

ROCK

 

 

0=Colluvium;1=Sandstone, 2=Sandstone+Siltstone; 3=Siltstone; 4=Breccia; 5=Intrusive

RES

 

 

0=Internal Waste; 1=Potential Resource; 999=Background

DOM

 

 

Estimation Domain

RESCODE

 

 

1=Measured, 2=lndicated, 3=lnferred,4=Unclassified

DENSITY

 

 

Bulk Density

OXIDE

 

 

1=Sulfide; 2=Oxide

AU

 

 

Uncapped Gold grade (ppm)

AG

 

 

Uncapped Silver grade (ppm)

AUCUT

 

 

Capped Gold grade (ppm)

AGCUT

 

 

Capped Silver grade (ppm)

AS

 

 

Arsenic grade (ppm)

CA

 

 

Calcium grade (%)

CU

 

 

Copper grade (ppm)

FE

 

 

Total Iron grade (ppm)

MN

 

 

Manganese grade (ppm)

MO

 

 

Molybdenum grade (ppm)

NA

 

 

Sodium grade (%)

PB

 

 

Lead grade (ppm)

S

 

 

Sulphur grade (%)

ZN

 

 

Zinc grade (ppm)

NUMSAMAU

 

 

Number of composites used in estimate

PASSAU

 

 

Estimation Pass

DISTAU

 

 

Average Distance of composites from cell centroid

NUMDHAU

 

 

Number of drill holes used in estimate

 

153


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.8                        Grade Estimation

 

The variographic study performed using the gold composites from the most heavily populated domains generally produced poorly structured variograms with maximum ranges of about 100 meters in the horizontal direction at the appropriate azimuth of each major domain, with a corresponding range of 70 meters in the semi-major direction. Given the generally poorly structured variograms, the decision was made to use in an inverse-distance interpolation.

 

A soft redox boundary was used for both gold and silver estimates. When reviewing cross sections and statistics, there is no clear change to the distribution of metal grades across the base of oxidation.

 

The interpolation parameters applied to the gold and silver domains are summarized in Table 14.8-1. The first-pass search distances take into consideration the results of both the variography and drill hole spacing. The second and third passes were designed to estimate grade into the majority of cells coded to the mineral domains that were not estimated in the first pass. Octant based searches were utilized for the first two estimation passes. A minimum of four octants needed to be estimated and each octant required the use of at least two composites to obtain an estimate. This criteria was removed for the third estimation pass. Interpolation parameters are similar for the minor elements, as per the gold and silver interpolation parameters, but are not tabled in this report as they are not material to the economics of the resource estimate.

 

Gold, silver and minor element grades were interpolated using inverse distance to the third power (ID3) and nearest-neighbor methods. The mineral resources reported herein were estimated by ID3 methods, using capped grades for gold and silver and uncapped grades for minor elements. A nearest-neighbor estimate was completed as a check on the ID3 interpolation for gold and silver.

 

The estimation passes were performed independently for each of the mineral domains, so that only composites coded to a particular domain were used to estimate grade into blocks coded by that domain. Grades were estimated into parent cells only. Small internal waste blocks were estimated separately from the main domains. These only occur in the northern sub-domains. The background model was also estimated, with gold and silver composites capped prior to the estimation to prevent smearing of higher grades into zones of lower grade material.

 

154


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.8-1        Search Parameters Used for Gold and Silver Estimation

 

 

 

Search Ellipse Ranges

Search Ellipse Orientation

First Pass

Second Pass

Third Pass

 

 

 

 

 

 

 

 

 

Min. No.

Max. No.

 

Min. No.

Max. No.

 

Min. No.

Max. No.

Max. No.

 

 

 

Semi-

 

 

Semi-

 

of

of

Search

of

of

Search

of

of

Comps

 

 

Major

Major

Minor

Major

Major

Minor

Comps

Comps

Volume

Comps

Comps

Volume

Comps

Comps

From Any

Au Domain

Variable

Axis

Axis

Axis

Axis

Axis

Axis

Used

Used

Factor

Used

Used

Factor

Used

Used

Drill hole

11

Au/Ag

60

60

25

0°/305°

-38°/215°

-52°/035°

10

16

2

8

16

6

4

16

4

22

Au/Ag

50

50

25

0°/305°

-50°/215°

-40°/035°

10

16

2

8

16

6

4

16

4

33

Au/Ag

50

50

20

0°/305°

-87°/035°

-3°/215°

8

16

2

6

16

6

3

16

4

44

Au/Ag

60

60

25

0°/305°

-60°/215°

-30°/035°

10

16

2

6

16

6

3

16

4

55

Au/Ag

60

60

25

0°/305°

-65°/215°

-25°/035°

10

16

2

8

16

6

4

16

4

66

Au/Ag

60

60

20

0°/305°

-80°/035°

-10°/215°

10

16

2

8

16

6

4

16

4

1001

Au/Ag

50

50

25

0°/300°

-90°/000°

0°/030°

10

16

2

8

16

6

4

16

2

1002

Au/Ag

50

50

25

0°/305°

-25°/215°

-65°/035°

10

16

2

8

16

6

4

16

2

1003

Au/Ag

50

50

25

0°/305°

-52°/215°

-38°/035°

10

16

2

8

16

6

4

16

2

1004

Au/Ag

50

50

25

0°/310°

-40°/220°

-50°/040°

10

16

2

8

16

6

4

16

2

1006

Au/Ag

50

50

25

0°/295°

-60°/205°

-30°/025°

10

16

2

8

16

6

4

16

2

1007

Au/Ag

50

50

25

0°/300°

-35°/210°

-55°/030°

10

16

2

8

16

6

4

16

2

1008

Au/Ag

50

50

25

0°/300°

-52°/030°

-38°/210°

10

16

2

8

16

6

4

16

2

1009

Au/Ag

50

50

25

0°/325°

-45°/055°

-45°/235°

10

16

2

8

16

6

4

16

2

1010

Au/Ag

50

50

25

0°/313°

-60°/223°

-30°/043°

10

16

2

8

16

6

4

16

2

1011

Au/Ag

50

50

25

0°/310°

-48°/040°

-42°/220°

10

16

2

8

16

6

4

16

2

1012

Au/Ag

50

50

25

0°/310°

-48°/040°

-42°/220°

10

16

2

8

16

6

4

16

2

1013

Au/Ag

50

50

25

0°/315°

-85°/035°

-5°/225°

10

16

2

8

16

6

4

16

2

 

155


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.8-1 (continued)  Search Parameters Used for Gold and Silver Estimation

 

 

 

Search Ellipse Ranges

Search Ellipse Orientation

First Pass

Second Pass

Third Pass

 

 

 

 

 

 

 

 

 

Min. No.

Max. No.

 

Min. No.

Max. No.

 

Min. No.

Max. No.

Max. No.

 

 

 

Semi-

 

 

Semi-

 

of

of

Search

of

of

Search

of

of

Comps

 

 

Major

Major

Minor

Major

Major

Minor

Comps

Comps

Volume

Comps

Comps

Volume

Comps

Comps

From Any

Domain

Variable

Axis

Axis

Axis

Axis

Axis

Axis

Used

Used

Factor

Used

Used

Factor

Used

Used

Drill hole

1014

Au/Ag

50

50

25

0°/310°

-85°/220°

-5°/040°

10

16

2

8

16

6

4

16

2

1015

Au/Ag

50

50

25

0°/296°

-90°/000°

0°/026°

10

16

2

8

16

6

4

16

2

1016

Au/Ag

50

50

25

0°/278°

-90°/000°

-0°/220°

10

16

2

8

16

6

4

16

2

1018

Au/Ag

50

50

25

0°/315°

-38°/045°

-52°/225°

10

16

2

8

16

6

4

16

2

1019

Au/Ag

50

50

25

0°/334°

-80°/244°

-10°/064°

10

16

2

8

16

6

4

16

2

1020

Au/Ag

50

50

25

0°/335°

-85°/245°

-5°/065°

10

16

2

8

16

6

4

16

2

1021

Au/Ag

50

50

25

0°/292°

-90°/000°

0°/022°

10

16

2

8

16

6

4

16

2

1022

Au/Ag

50

50

25

0°/292°

-90°/000°

0°/022°

10

16

2

8

16

6

4

16

2

1041

Au/Ag

50

50

25

0°/310°

-36°/220°

-54°/040°

10

16

2

8

16

6

4

16

2

1200 Intrusive-S

Au/Ag

50

50

25

0°/310°

-60°/220°

-30°/040°

10

16

2

8

16

6

4

16

2

1300 Colluvium-S

Au/Ag

50

50

25

0°/310°

-0°/000°

-0°/040°

10

16

2

8

16

4

4

16

2

Colluvium-N

Au/Ag

60

60

20

0°/310°

-0°/000°

-0°/040°

10

16

2

8

16

4

4

16

2

 

156


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.9                        Mineral Resources

 

14.9.1              Mineral Resource Definitions

 

Mineral Resources for the Shahuindo deposit are classified in accordance with Canadian Institute of Mining, Metallurgy and Petroleum (CIM) CIM Definition Standards — For Mineral Resources and Mineral Reserves (2014), whereas:

 

A Mineral Resource is a concentration or occurrence of solid material of economic interest in or on the Earth’s crust in such form, grade or quality and quantity that there are reasonable prospects for eventual economic extraction. The location, quantity, grade or quality, continuity and other geological characteristics of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge, including sampling. Mineral Resources are sub-divided, in order of increasing geologic confidence, into Inferred, Indicated and Measured Categories. An Inferred Mineral Resource has a lower level of confidence than that applied to an Indicated Mineral Resource. An Indicated Mineral Resource had a higher level of confidence than an Inferred Mineral Resource but has a lower level of confidence than a Measured Mineral Resource.

 

An Inferred Mineral Resource is that part of a Mineral Resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An Inferred Mineral Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration. An Inferred Mineral Resource is based on limited information and sampling gathered through appropriate sampling techniques from locations such as outcrops, trenches, pits, workings and drill holes. Inferred Mineral Resources must not be included in the economic analysis, production schedules, or estimated mine life in publicly disclosed Pre-Feasibility or Feasibility Studies, or in the Life of Mine plans and cash flow models of developed mines. Inferred Mineral Resources can only be used in economic studies as provided under NI 43-101.

 

An Indicated Mineral Resource is that part of a Mineral Resource for which quantity, grade or quality, densities, shape and physical characteristics are estimated with sufficient confidence to allow the application of Modifying Factors in sufficient detail to support mine planning and evaluation of the economic viability of the deposit. Geological evidence is derived from adequately detailed and reliable exploration, sampling and testing and is sufficient to assume geological and grade or quality continuity between points of observation. An Indicated Mineral Resource has a lower level of confidence than that applying to a Measured Mineral Resource and may only be

 

157


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

converted to a Probable Mineral Reserve. Mineralization may be classified as an Indicated Mineral Resource by the Qualified Person when the nature, quality, quantity and distribution of data are such as to allow confident interpretation of the geological framework and to reasonably assume the continuity of mineralization. The Qualified Person must recognize the importance of the Indicated Mineral Resource category to the advancement of the feasibility of the project. An Indicated Mineral Resource estimate is of sufficient quality to support a Pre-Feasibility Study which can serve as the basis for major development decisions.

 

A Measured Mineral Resource is that part of a Mineral Resource for which quantity, grade or quality, densities, shape, and physical characteristics are estimated with confidence sufficient to allow the application of Modifying Factors to support detailed mine planning and final evaluation of the economic viability of the deposit. Geological evidence is derived from detailed and reliable exploration, sampling and testing and is sufficient to confirm geological and grade or quality continuity between points of observation. A Measured Mineral Resource has a higher level of confidence than that applying to either an Indicated Mineral Resource or an Inferred Mineral Resource. It may be converted to a Proven Mineral Reserve or to a Probable Mineral Reserve. Mineralization or other natural material of economic interest may be classified as a Measured Mineral Resource by the Qualified Person when the nature, quality, quantity and distribution of data are such that the tonnage and grade or quality of the mineralization can be estimated to within close limits and that variation from the estimate would not significantly affect potential economic viability of the deposit. This category requires a high level of confidence in, and understanding of, the geology and controls of the mineral deposit.

 

Modifying Factors are considerations used to convert Mineral Resources to Mineral Reserves. These include, but are not restricted to, mining, processing, metallurgical, infrastructure, economic, marketing, legal, environmental, social and governmental factors.

 

14.9.2              Shahuindo Mineral Resources

 

The effective date of the Shahuindo Mineral Resource estimate is 15 April 2015.

 

Measured and Indicated oxide resources for the Shahuindo deposit total 143.1 million tonnes with average grades of 0.50 g/t Au and 6.67 Ag g/t, containing 2.28 million ounces of gold and 30.7 million ounces of silver. Inferred oxide resources total 2.6 million tonnes with average grades of 0.42 g/t Au and 7.40 Ag g/t, containing 36,000 ounces of gold and 626,000 ounces of silver. Oxide resources are reported within a $1,400/oz Au optimal Whittle open pit shell using a 0.14 AuEq g/t cut-off grade. The oxide Mineral Resources are summarized in Table 14.9-1.

 

158


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.9-1                         Shahuindo Mineral Resources — Oxide

(0.14 g/t AuEq cut-off within $1,400/oz Au pit shell)

 

 

 

 

Tonnes

 

 

Au Grade

 

 

Ag Grade

 

 

Au Ounces

 

 

Ag Ounces

 

Resource Classification

 

 

(M)

 

 

(g/t)

 

 

(g/t)

 

 

(000s)

 

 

(000s)

 

Measured

 

 

96.5

 

 

0.50

 

 

6.73

 

 

1,546

 

 

20,901

 

Indicated

 

 

46.6

 

 

0.49

 

 

6.53

 

 

736

 

 

9,778

 

Measured and Indicated

 

 

143.1

 

 

0.50

 

 

6.67

 

 

2,282

 

 

30,679

 

Inferred

 

 

2.6

 

 

0.42

 

 

7.4

 

 

36

 

 

626

 

 

Numbers may not add due to rounding

 

The Mineral Resources reported herein represent the in situ resources, with no economic or metallurgical recovery factors applied other than the $1,400 per ounce gold pit shell applied to the oxide resources.

 

Table 14.9-2 through Table 14.9-4 are tabulations of the oxide resources at varying cut-off grades within the $1,400/oz Au pit shell for Measured, Indicated and Inferred Resources, respectively.

 

Table 14.9-2                         Measured Oxide Resources - Grade Tonnage

 

Cut-off

 

 

Tonnes

 

 

Au Grade

 

 

Ag Grade

 

 

Au Ounces

 

 

Ag Ounces

 

AuEq g/t

 

 

(M)

 

 

(g/t)

 

 

(g/t)

 

 

(000s)

 

 

(000s)

 

0.01

 

 

169.1

 

 

0.30

 

 

4.33

 

 

1,631

 

 

23,540

 

0.1

 

 

104.9

 

 

0.47

 

 

6.35

 

 

1,586

 

 

21,426

 

0.14

 

 

96.5

 

 

0.50

 

 

6.73

 

 

1,546

 

 

20,901

 

0.2

 

 

81.6

 

 

0.56

 

 

7.52

 

 

1,470

 

 

19,735

 

0.3

 

 

59.3

 

 

0.68

 

 

9.06

 

 

1,297

 

 

17,285

 

0.4

 

 

42.6

 

 

0.82

 

 

10.73

 

 

1,123

 

 

14,698

 

0.5

 

 

31.4

 

 

0.96

 

 

12.34

 

 

969

 

 

12,458

 

0.6

 

 

24.0

 

 

1.10

 

 

13.78

 

 

848

 

 

10,624

 

0.7

 

 

18.7

 

 

1.24

 

 

15.07

 

 

745

 

 

9,060

 

0.8

 

 

14.9

 

 

1.38

 

 

16.28

 

 

659

 

 

7,774

 

0.9

 

 

12.0

 

 

1.51

 

 

17.35

 

 

581

 

 

6,680

 

1.0

 

 

9.8

 

 

1.65

 

 

18.36

 

 

518

 

 

5,762

 

 

159


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.9-3                         Indicated Oxide Resources - Grade Tonnage

 

Cut-off

 

 

Tonnes

 

 

Au Grade

 

 

Ag Grade

 

 

Au Ounces

 

 

Ag Ounces

 

AuEq g/t

 

 

(M)

 

 

(g/t)

 

 

(g/t)

 

 

(000s)

 

 

(000s)

 

0.01

 

 

97.6

 

 

0.26

 

 

3.66

 

 

816

 

 

11,490

 

0.1

 

 

51.0

 

 

0.46

 

 

6.15

 

 

754

 

 

10,078

 

0.14

 

 

46.6

 

 

0.49

 

 

6.53

 

 

736

 

 

9,778

 

0.2

 

 

39.8

 

 

0.55

 

 

7.21

 

 

705

 

 

9,237

 

0.3

 

 

28.2

 

 

0.68

 

 

8.66

 

 

617

 

 

7,864

 

0.4

 

 

19.2

 

 

0.84

 

 

10.21

 

 

518

 

 

6,294

 

0.5

 

 

13.4

 

 

1.02

 

 

11.79

 

 

438

 

 

5,066

 

0.6

 

 

9.9

 

 

1.20

 

 

13.15

 

 

381

 

 

4,170

 

0.7

 

 

7.7

 

 

1.37

 

 

14.19

 

 

340

 

 

3,526

 

0.8

 

 

6.3

 

 

1.52

 

 

15.18

 

 

307

 

 

3,067

 

0.9

 

 

5.2

 

 

1.66

 

 

16.16

 

 

278

 

 

2,704

 

1.0

 

 

4.4

 

 

1.81

 

 

17.09

 

 

254

 

 

2,400

 

 

Table 14.9-4                         Inferred Oxide Resources - Grade Tonnage

 

Cut-off

 

 

Tonnes

 

 

Au Grade

 

 

Ag Grade

 

 

Au Ounces

 

 

Ag Ounces

 

AuEq g/t

 

 

(M)

 

 

(g/t)

 

 

(g/t)

 

 

(000s)

 

 

(000s)

 

0.01

 

 

7.4

 

 

0.17

 

 

3.38

 

 

41

 

 

809

 

0.1

 

 

2.8

 

 

0.40

 

 

7.03

 

 

37

 

 

642

 

0.14

 

 

2.6

 

 

0.42

 

 

7.40

 

 

36

 

 

626

 

0.2

 

 

2.1

 

 

0.49

 

 

8.57

 

 

33

 

 

582

 

0.3

 

 

1.4

 

 

0.63

 

 

11.18

 

 

28

 

 

489

 

0.4

 

 

0.9

 

 

0.77

 

 

13.35

 

 

23

 

 

402

 

0.5

 

 

0.6

 

 

0.94

 

 

15.51

 

 

19

 

 

321

 

0.6

 

 

0.5

 

 

1.10

 

 

18.60

 

 

16

 

 

275

 

0.7

 

 

0.3

 

 

1.33

 

 

23.58

 

 

13

 

 

236

 

0.8

 

 

0.2

 

 

1.57

 

 

29.21

 

 

11

 

 

210

 

0.9

 

 

0.2

 

 

1.79

 

 

35.31

 

 

10

 

 

198

 

1.0

 

 

0.1

 

 

2.04

 

 

43.14

 

 

9

 

 

188

 

 

Measured oxide resources required a minimum of ten composites within 25m of the block centroid; Indicated oxide resources required a minimum of eight composites within 50m of the block centroid;

 

160


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

and Inferred oxide resources required a minimum of between four and eight composites within 100m of the block centroid. Irrespective of the resource classification, the estimate used a maximum of two composites from a single drill hole for the southern domains and a maximum of four composites from a single drill hole for the northern domains.

 

14.9.2.1                            Sulfide Mineral Resources

 

The sulfide mineral resources at Shahuindo are classified entirely as Inferred due to limited metallurgical characterization and wider drill spacing than in the oxide portion of the deposit, generally from 50m x 50m to 100m x 100m. There have been no economic or mining studies of the sulfide portion of the Shahuindo deposit completed to date; the Inferred sulfide resource is reported at a 0.5 AuEq g/t cut-off per the requirement of “reasonable prospects for eventual economic extraction.”

 

The Inferred sulfide mineral resources for the Shahuindo deposit total 87.7 million tonnes with average grades of 0.71 g/t Au and 21.08 g/t Ag, containing 2.0 million ounces of gold and 59.4 million ounces of silver, as shown in Table 14.9-5.

 

Table 14.9-5                         Shahuindo Mineral Resources — Sulfide

(0.5 g/t AuEq cut-off)

 

 

 

 

Tonnes

 

 

Au Grade

 

 

Ag Grade

 

 

Au Ounces

 

 

Ag Ounces

 

Resource Classification

 

 

(M)

 

 

(g/t)

 

 

(g/t)

 

 

(000s)

 

 

(000s)

 

Inferred

 

 

87.7

 

 

0.71

 

 

21.08

 

 

2,002

 

 

59,441

 

 

Table 14.9-6 is a tabulation of the Shahuindo Inferred sulfide resources at varying cut-off grades.

 

161


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.9-6                         Inferred Sulfide Resources - Grade Tonnage

 

Cut-off

 

 

Tonnes

 

 

Au Grade

 

 

Ag Grade

 

 

Au Ounces

 

 

Ag Ounces

 

AgEq g/t

 

 

(M)

 

 

(g/t)

 

 

(g/t)

 

 

(000s)

 

 

(000s)

 

0.1

 

 

349.0

 

 

0.29

 

 

8.04

 

 

3,254

 

 

90,216

 

0.2

 

 

196.8

 

 

0.45

 

 

12.21

 

 

2.848

 

 

77,272

 

0.3

 

 

153.6

 

 

0.52

 

 

14.65

 

 

2,568

 

 

72,355

 

0.4

 

 

116.3

 

 

0.61

 

 

17.66

 

 

2,281

 

 

66,034

 

0.5

 

 

87.7

 

 

0.71

 

 

21.08

 

 

2,002

 

 

59,441

 

0.6

 

 

68.7

 

 

0.81

 

 

24.41

 

 

1,788

 

 

53,877

 

0.7

 

 

55.3

 

 

0.90

 

 

27.62

 

 

1,601

 

 

49,136

 

0.8

 

 

45.8

 

 

0.98

 

 

30.59

 

 

1,444

 

 

45,074

 

0.9

 

 

38.5

 

 

1.06

 

 

33.40

 

 

1,312

 

 

41,345

 

1.0

 

 

32.6

 

 

1.15

 

 

36.15

 

 

1,206

 

 

37,905

 

2.0

 

 

9.2

 

 

1.89

 

 

60.72

 

 

560

 

 

17,976

 

3.0

 

 

3.2

 

 

2.58

 

 

88.70

 

 

264

 

 

9,070

 

4.0

 

 

1.4

 

 

3.29

 

 

112.61

 

 

144

 

 

4,926

 

5.0

 

 

0.7

 

 

4.08

 

 

128.02

 

 

87

 

 

2,717

 

 

The classification of Inferred Resources required at least 4 drill hole composites within 100m of the block centroid, with a maximum of two composites from a single drill hole for the southern domains and a maximum of four composites from a single drill hole for the northern domains.

 

14.10                 Resource Model Checks

 

14.10.1       Composites vs Model Grades

 

Gold and silver composites coded by sub-domain were compared to the Measured and Indicated resource within the model sub-domains. Sub-domains with less than 100,000 tonnes were removed from the comparison as they typically have very few composites.

 

As shown in Table 14.10-1, the average gold composite values compare favorably to the block model gold values, with three sub-domains displaying slightly higher grades in the resource model. The overall gold grade estimate is slightly below the average composite grade. Silver comparisons are slightly more variable, particularly in the southern sub-domains where there are smaller amounts of composites.

 

162


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 14.10-1                  Composites vs Resource Model Grades

 

 

 

 

 

 

 

Composites

 

 

Resource Model

 

 

 

 

 

 

 

 

 

 

Au

 

 

Ag

 

 

 

 

 

Au

 

 

Ag

 

Domain

 

 

Sub-Domain

 

 

Count

 

 

(g/t)

 

 

(g/t)

 

 

Tonnes

 

 

(g/t)

 

 

(g/t)

 

North

 

 

11

 

 

7,816

 

 

0.39

 

 

3.89

 

 

40,388,439

 

 

0.34

 

 

4.15

 

North

 

 

12

 

 

219

 

 

0.49

 

 

5.71

 

 

405,694

 

 

0.23

 

 

4.62

 

North

 

 

44

 

 

1,287

 

 

0.55

 

 

6.44

 

 

11,650,605

 

 

0.58

 

 

6.79

 

North

 

 

55

 

 

14,171

 

 

0.52

 

 

9.10

 

 

66,549,549

 

 

0.48

 

 

8.49

 

North

 

 

66

 

 

428

 

 

0.33

 

 

4.65

 

 

3,571,893

 

 

0.36

 

 

6.37

 

Total Northern Domains

 

 

23,921

 

 

0.48

 

 

7.14

 

 

122,566,180

 

 

0.44

 

 

6.83

 

South

 

 

1001

 

 

3,933

 

 

0.60

 

 

7.03

 

 

23,542,517

 

 

0.57

 

 

7.41

 

South

 

 

1002

 

 

790

 

 

0.38

 

 

5.44

 

 

5,011,830

 

 

0.35

 

 

5.48

 

South

 

 

1003

 

 

2,617

 

 

0.51

 

 

7.13

 

 

11,929,335

 

 

0.50

 

 

7.78

 

South

 

 

1004

 

 

165

 

 

0.34

 

 

3.69

 

 

1,982,346

 

 

0.29

 

 

3.12

 

South

 

 

1007

 

 

901

 

 

0.34

 

 

4.21

 

 

3,729,064

 

 

0.30

 

 

4.36

 

South

 

 

1008

 

 

89

 

 

0.64

 

 

15.02

 

 

542,995

 

 

0.56

 

 

11.54

 

South

 

 

1009

 

 

627

 

 

0.40

 

 

5.27

 

 

1,654,303

 

 

0.36

 

 

4.66

 

South

 

 

1010

 

 

49

 

 

0.23

 

 

3.24

 

 

171,115

 

 

0.22

 

 

2.95

 

South

 

 

1012

 

 

430

 

 

0.38

 

 

6.62

 

 

3,000,419

 

 

0.37

 

 

7.25

 

South

 

 

1014

 

 

78

 

 

0.64

 

 

23.66

 

 

397,175

 

 

0.63

 

 

19.35

 

South

 

 

1015

 

 

35

 

 

0.45

 

 

1.79

 

 

139,539

 

 

0.48

 

 

1.55

 

South

 

 

1022

 

 

31

 

 

0.57

 

 

71.67

 

 

119,792

 

 

0.70

 

 

78.21

 

South

 

 

1141

 

 

348

 

 

0.53

 

 

8.18

 

 

973,408

 

 

0.43

 

 

6.37

 

Total Southern Domains

 

 

10,093

 

 

0.51

 

 

6.90

 

 

53,193,837

 

 

0.49

 

 

7.08

 

Total

 

 

34,014

 

 

0.48

 

 

7.07

 

 

175,760,017

 

 

0.45

 

 

6.90

 

 

14.10.2 Nearest Neighbor Check Estimate

 

A nearest-neighbor model was estimated to compare with the Measured and Indicated resources within the ID(3) model. Sub-domains with less than 100,000 tonnes were removed as they typically have insufficient data points for valid comparison. The nearest neighbor estimate was limited to the first search pass and constrained within the same domains as the ID(3) resource estimate. As shown in Figure 14.10-1 through Figure 14.10-3, there is good correlation between the two estimates with some variance occurring in areas of lower data density at the margins of the deposit.

 

163


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 14.10-1 Inverse Distance (ID3) vs Nearest Neighbor Estimate by Easting

 

 

Figure 14.10-2 Inverse Distance (ID3) vs Nearest Neighbor Estimate by Northing

 

 

Figure 14.10-3 Inverse Distance (ID3) vs Nearest Neighbor Estimate by Elevation

 

164


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

14.10.3 Visual Comparisons

 

Visual comparisons on cross sections and plans display a close correlation of composite grades and resource model grades. There does appear to be minor smearing of higher grades on a local level, though this is not seen as a material issue due to the majority of the higher-grade composites and corresponding block grades being surrounded by lower grade material.

 

14.10.4 Additional Information and Discussion

 

14.10.4.1                                             Gold-Equivalent Calculation

 

Gold-equivalent grades in the Shahuindo resource block model were calculated using the individual gold and silver grades for each block and metal prices of $1,200 per ounce gold and $15 per ounce silver. The formula used to calculate the AuEq grade is AuEq g/t = Au g/t + (Ag g/t x 15/1200).

 

14.10.4.2                                             Confidence of Key Criteria

 

The classification of the resource estimate as Measured, Indicated and Inferred is based on the confidence of the input data and geological interpretation, and grade estimation parameters, as summarized in Table 14.10-2.

 

Table 14.10-2                  Confidence Levels of Key Criteria

 

Items

 

Discussion

 

Confidence

Drilling Techniques

 

RC and diamond drilling with documented good quality techniques.

 

High

Logging

 

Standard nomenclature now adopted.

 

Moderate

Drill Sample Recovery

 

High recoveries of RC and diamond core samples.

 

High

Sub-sampling Techniques and Sample Preparation

 

Samples are reliable to adequately represent both styles of mineralization.

 

High

Quality of Assay Data

 

Data is reliable, based on QAQC results and observed and documented practices.

 

High

Location of Sample Points

 

Survey of all collars conducted with DGPS by professional surveyors. Topographic surface is based on 2m survey contours. Historical downhole surveys are of good quality, however the January-March 2015 campaign was not downhole surveyed.

 

Moderate

Data Density and Distribution

 

Drilling on nominal 25m x 25m spacing for the majority of the oxide domains consisting of RC and diamond drilling to establish continuity. Drilling on nominal 50m x 50 spacing for the majority of the sulfide domains, although some large data gaps do exist.

 

High — Oxide
Moderate - Sulfide

Geologic Controls

 

Logging and mapping checked on site. Work still required to determine finer scale geological controls, particularly in the northern portion of the deposit.

 

Moderate

Database Integrity

 

Multiple audits; assay certificates checked.

 

High

Geologic Interpreation

 

Mineralization interpretations are considered reliable for oxide domains as bulk mining entities. Further work required on 50m and 25m sections to determine local controls. Sulfide domains require metallurgical test work, and more detailed structural and geological review and more drilling.

 

Moderate

 

165


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

(Table 14.10-2 continued) Confidence Levels of Key Criteria

 

Items

 

Discussion

 

Confidence

Estimation and Modelling Techniques

 

Inverse distance cubed is an industry standard estimator in high-sulfidation deposits with moderate nuggets and relatively short ranges of continuity.

 

High

Cut-off Grades

 

Reasonable cut-off grades applied for the proposed mining method. Ag has been discounted as adding any value to the cut-off grade, given that Ag lies almost entirely within the Au mineralization envelopes, and has 15% metallurgical recovery.

 

High

Mining Factors or Assumptions

 

Parent block size for oxides is in line with the SMU planned for mining.

 

High

Metallurgical Factors or Assumptions

 

Metallurgy is based on extensive test work for both ROM and agglomeration phases of the oxide project. Metallurgy is of an unknown quantity for sulfide mineralization.

 

High — Oxide
Low - Sulfide

Tonnage Factors (in situ bulk densities)

 

Sufficient bulk density work for global averages.

 

Moderate

 

14.10.4.3           Discussion

 

As demonstrated by closely-spaced drilling, geologic interpretation, and resource modelling, the Shahuindo deposit is characterized by continuous, near-surface mineralization that extends over a strike of approximately four kilometers. Mineralization is disseminated on fractures and within folded and faulted sedimentary units, with higher grades generally related to high-angle structures at variable orientations, areas of increased silicification, and along zones of dense fracturing and brecciation.

 

Block model cross sections through the southern and northern portions of the Shahuindo deposit are shown in Figure 14.10-4 and Figure 14.10-5, respectively.

 

There are several areas proximal to the existing resource that have early indications of potential to expand the overall resource at Shahuindo and Tahoe believes there is good potential to add to the resource with additional exploration. Exploration targets near the Shahuindo deposit are discussed further in Section 24 — Other Relevant Data and Information.

 

To the best of Tahoe’s knowledge, there are no specific environmental, permitting, legal, title, taxation, socio-economic, marketing, political, or other factors which could materially affect the Mineral Resources at Shahuindo.

 

166


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 14.10-4             Shahuindo Resource Model (Section 500N)

 

167


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 14.10-5             Shahuindo Resource Model - Section 1100N

 

168


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

15.0                        MINERAL RESERVE ESTIMATES

 

The Mineral Resources for Shahuindo have been converted to Mineral Reserves based upon the following modifying factors:

 

·                  Only Measured and Indicated Mineral Resources are included in Mineral Reserves;

 

·                  Only the Mineral Resources within the $ 1,400/oz Au optimized pit limit are considered;

 

·                  Mining dilution, mining recovery and metallurgical recovery factors are applied; and

 

·                  The Measured and Indicated Mineral Resources are legally, economically and technically feasible to extract.

 

The Mineral Reserve estimate was completed by first identifying the ultimate pit limits using the economic parameters detailed in Section 15.3 and pit optimization techniques. The results of the optimization were used for guidance in the final pit design to allow access for equipment and personnel. Several phases of mining were defined to enhance the economics of the project. Tahoe used phased pit designs to define the production schedule using MineMax ™ open pit net present value (NPV) scheduler software to optimize the NPV under a set of mining constraints. The cash flow model was developed using costs calculated from first principles and experience at Tahoe’s La Arena mine to determine the maximum value of the Shahuindo deposit and confirm the Mineral Reserves.

 

15.1                        Mineral Reserves

 

15.1.1              Mineral Reserve Definitions

 

Mineral Reserves for the Shahuindo deposit are classified in accordance with CIM Definition Standards — For Mineral Resources and Mineral Reserves (2014), whereas:

 

A Mineral Reserve is the economically mineable part of a Measured and/or Indicated Mineral Resource. It includes diluting materials and allowances for losses, which may occur when the material is mined or extracted and is defined by studies at Pre-Feasibility or Feasibility level as appropriate that include application of Modifying Factors. Such studies demonstrate that, at the time of reporting, extraction could reasonably be justified. Mineral Reserves are sub-divided in order of increasing confidence into Probable Mineral Reserves and Proven Mineral Reserves. A Probable Mineral Reserve has a lower level of confidence than a Proven Mineral Reserve.

 

A Probable Mineral Reserve is the economically mineable part of an Indicated, and in some circumstances, a Measured Mineral Resource. The confidence in the Modifying Factors applying to a Probable Mineral Reserve is lower than that applying to a Proven Mineral Reserve. The Qualified Person(s) may elect to convert Measured Mineral Resources to Probable Mineral Reserves if the confidence

 

169


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

in the Modifying Factors is lower than that applied to a Proven Mineral Reserve. Probable Mineral Reserve estimates must be demonstrated to be economic, at the time of reporting, by at least a Pre-Feasibility Study.

 

Proven Mineral Reserve is the economically mineable part of a Measured Mineral Resource. A Proven Mineral Reserve implies a high degree of confidence in the Modifying Factors. Application of the Proven Mineral Reserve category implies that the Qualified Person has the highest degree of confidence in the estimate with the consequent expectation in the minds of the readers of the report. The term should be restricted to that part of the deposit where production planning is taking place and for which any variation in the estimate would not significantly affect the potential economic viability of the deposit. Proven Mineral Reserve estimates must be demonstrated to be economic, at the time of reporting, by at least a Pre-Feasibility Study. Within the CIM Definition standards the term Proved Mineral Reserve is an equivalent term to a Proven Mineral Reserve.

 

Modifying Factors are considerations used to convert Mineral Resources to Mineral Reserves. These include, but are not restricted to, mining, processing, metallurgical, infrastructure, economic, marketing, legal, environmental, social and governmental factors.

 

15.1.2              Shahuindo Mineral Reserves

 

Proven and Probable Mineral Reserves for the Shahuindo mine are 111.9 million tonnes with average grades of 0.53 g/t Au and 6.82 g/t Ag, containing 1.91 million ounces of gold and 24.5 million ounces of silver. Mineral Reserves for the Shahuindo mine were developed by applying relevant economic criteria in order to define the economically extractable portions of the Measured and Indicated Mineral Resource. The Mineral Reserve Estimate for the Shahuindo mine is shown in Table 15.1-1. The Mineral Reserves are reported as in situ dry tonnes at a cut-off grade of 0.18 g/t Au and include 5% mining dilution and 98% mining recovery.

 

Table 15.1-1                         Shahuindo Mineral Reserves

 

 

 

 

Tonnes

 

 

Au Grade

 

 

Ag Grade

 

 

Au Ounces

 

 

Ag Ounces

 

Reserve Classification

 

 

(M)

 

 

(g/t)

 

 

(g/t)

 

 

(000s)

 

 

(000s)

 

Proven

 

 

82.7

 

 

0.54

 

 

6.92

 

 

1,424

 

 

18,400

 

Probable

 

 

29.2

 

 

0.51

 

 

6.54

 

 

483

 

 

6,142

 

Proven & Probable

 

 

111.9

 

 

0.53

 

 

6.82

 

 

1,906

 

 

24,541

 

 

Numbers may not add due to rounding

 

The effective date of the Shahuindo Mineral Reserve estimate is 01 November 2015 using metal prices of $1,200 per ounce gold and $15.00 per ounce silver. Mineral Reserves reported for the Shahuindo deposit are inclusive of Mineral Resources.

 

170


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The Mineral Reserve for the Shahuindo deposit is based upon mineralized material reported as Measured and Indicated Mineral Resources with dilution and mining losses considered. Process recovery factors or additional plant losses were not considered, though metallurgical recovery was incorporated into the optimization. Inferred Resources contained within the final pit design are included in the Mineral Reserve as dilution with zero metal grades.

 

Tahoe is not aware of any specific metallurgical, infrastructural, environmental, legal, title, taxation, socio-economic or marketing issues that would impact the Mineral Reserve Estimate as presented.

 

15.2                        Cut-off Grade

 

The cut-off grade value of 0.18 g/t Au was used to determine the minable portion of the Measured and Indicated Resources at Shahuindo is predicated on the assumption that mine production will feed the leach pads and processing facility at capacity throughout the mine life. All costs that are incremental with production are included in the cut-off value calculation. Costs in the cut-off value calculation include the variable and fixed costs directly related to processing, smelting, refining, general and administrative (G&A) costs directly related to production, royalties, and project costs related to production and the plant facilities that do not have a measurable payback.

 

Costs excluded from the cut-off value calculation include exploration, capitalized development costs, capital infrastructure costs, in-mine projects having a measurable economic benefit, and non-cash charges. The cut-off grade assumes the mining costs for an economic open pit is a sunk cost and is not used in the calculation of the cut-off grade. Sustaining capital and expansion capital costs are excluded from the cut-off value cost basis as these costs are not incremental to a specific unit of production but rather common to large portions of the mineral deposit.

 

Cut-off grades to define the Mineral Reserves were calculated using operating costs from Tahoe’s La Arena mine which is very similar to Shahuindo; the estimated metallurgical performance was sourced from test work and engineering first principles were used to derive operating costs or obtained from La Arena’s cost structure. The minimum cut-off grade of 0.18 g/t Au was derived from the equation:

 

COG (Au g/t)

=

Diluted Process Cost

Recovery x Metal Price with Royalties and Sales Costs

 

The resulting cut-off grade was used to determine the Mineral Reserves reported in Table 15.1-1. Silver is considered to have too little value contribution to be included in the cut-off grade calculation. The economic assumptions used to determine the cut-off grade are presented in Table 15.2-1 and used as the basis for the pit optimization described in Section 15.5.

 

171


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 15.2-1                         Cut-Off Grade Assumptions

 

Gold Price (US$/oz)

 

 

1,200

 

Processing Cost (US$/tonne)

 

 

5.47

 

Royalties & Sales Costs (US$/oz Au)

 

 

38

 

Au Recovery (%)

 

 

82

 

Au Recovery x Au Price (US$)

 

 

31.16

 

Diluted Process Cost (US$/oz Au)

 

 

5.70

 

 

15.3                        Assumptions and Parameters

 

The Mineral Reserves are constrained by a pit geometry that has been determined by technical and cost and recovery inputs. The lists of assumptions used for the open pit is presented in Table 15.3-1.

 

Table 15.3-1                         Pit Optimization Parameters for Shahuindo Mineral Reserve

 

Mining (US$/tonne — ore & waste)

 

 

2.44

 

Processing (US$/tonne)

 

 

1.57

3

Sustaining Pad Construction Capex (US$/tonne)

 

 

0.68

 

Crushing & Agglomeration (US$/tonne processed)

 

 

1.39

 

G&A (US$/tonne mined)

 

 

1.83

 

Total Processing (US$/tonne processed)

 

 

5.47

 

Oxide Gold Recovery (%)

 

 

82

 

Oxide Silver Recovery (%)

 

 

15

 

Gold Price (US$/oz)

 

 

1,200

 

Silver Price (US$/oz)

 

 

15

 

Metal Payables (%)

 

 

99.9

 

Royalties (%)

 

 

1

 

Mining Losses (%)

 

 

2

 

Mining Dilution (%)

 

 

5

 

Sales Costs (US$/oz)

 

 

12.37

 

Mining Rate (ore mtpa)

 

 

12

 

Total Mining Rate (ore + waste mtpa)

 

 

32

 

 


3 includes processing power and reagents costs.

 

172


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The base mining cost of $2.44/tonne includes the indirect and direct cost of mining in-situ rock. This cost was obtained from quotes from STRACON GYM Mining Contractors who currently have an alliance contract at Tahoe’s La Arena gold mine. It also included a sustaining cost of $0.68 per tonne for pad construction costs and a pit dewatering cost of $0.03/tonne of rock.

 

The processing, G&A and refining costs are based on actual costs experienced at Tahoe’s La Arena mine and processing test work conducted by Tahoe to better define metal recoveries and reagent consumption. Shahuindo processing costs are expected to be slightly higher than La Arena due to increased reagent consumption. The reagent consumption estimate is based on leach column test work.

 

15.4                        Dilution

 

The resource model was created using 3-dimensional mineralized domains to confine the estimation reporting grade and proportion of each block within the various domains. The domains were then diluted back to the block size based on the contribution of each domain to the block. The resource model contains block dimensions of 8m long by 4m wide by 8m high. The 8m block length is aligned with the general north-west to south-east trend of the deposit to better reflect the mineralization trend. A dilution of 5% at zero grade and an ore loss of 2% has been applied as Tahoe believes that this represents an appropriate amount of dilution for statement of Mineral Reserves based on operating experience at La Arena.

 

15.5                        Pit Optimization

 

The optimized economic pit shells selected for the basis of open pit designs were created using the GEOVIA Whittle™ software package. Whittle ™ is a well-known commercial product that uses geologic, mining, metallurgical and economic inputs to determine the pit shell with the highest net value.

 

The optimization used economic parameters for various mining and processing scenarios to define the best operating scenario for the project that created the most value. The pit optimization used only Measured and Indicated Resources for processing. All Inferred material was considered to be waste. The Mineral Resource contained no sulfide classified as Measured or Indicated Resources; therefore, all sulfide material within the pit was classified as waste.

 

The optimization was completed to provide the best economical pit size. A pit phasing strategy was developed based on mining smaller pits inside the optimal pit shell to produce a starter pit and six subsequent mining phases.

 

173


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

15.6                        Pit Optimization Results

 

The inputs for the Whittle pit optimization were based on the criteria listed in Table 15.3-1. Using GEOVIA Whittle™, a series of nested pit shells were generated by applying a range of revenue factors (selling price) to the optimization process.

 

The pushbacks were selected from the generated pit shells considering the following criteria:

 

·                  Significant increases in waste (step change).

 

·                  The pushback would allow an operational/practical bench to be generated.

 

The pushbacks selected were pit shells 5, 10, 15, 20, and 36. The selection of the optimal shell (i.e., final shell) for the pit design considered value and risk. The pit shell selected had an NPV of $512 million (pit shell 36). This shell was selected as it had a revenue factor of one at a gold cut-off grade of 0.18 g/t and processed 36,000 tonnes per day.

 

The GEOVIA Whittle™ results for pit shells examined are shown in Figure 15.6-1.

 

 

Figure 15.6-1                    Graph of Whittle Results

 

174


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 15.6-1 illustrates Best Case, Specified Case and Worst Case for pit shells 5, 10, 15, 20 and 36 in terms of NPV, ore tonnes, waste tonnes and other pertinent information.

 

Table 15.6-1                         Pit Size vs Value

 

 

 

 

 

 

 

 

 

 

Ore

 

 

Au

 

 

Au

 

 

Ag

 

 

Ag

 

 

Waste

 

 

Total

 

 

 

 

 

 

 

Au Price

 

 

Ag Price

 

 

Tonnes

 

 

Grade

 

 

Ounces

 

 

Grade

 

 

Ounces

 

 

Tonnes

 

 

Tonnes

 

 

Strip

 

Pit

 

 

($/oz)

 

 

($/oz)

 

 

(000s)

 

 

(g/t)

 

 

(000s)

 

 

(g/t)

 

 

(000s)

 

 

(000s)

 

 

(000s)

 

 

Ratio

 

5

 

 

456

 

 

5.7

 

 

4,484

 

 

1.3

 

 

188

 

 

11.44

 

 

1,650

 

 

6,118

 

 

10,601

 

 

1.36

 

10

 

 

576

 

 

7.2

 

 

10,652

 

 

1.04

 

 

357

 

 

10.24

 

 

3,408

 

 

15,883

 

 

26,535

 

 

1.49

 

15

 

 

696

 

 

8.7

 

 

33,554

 

 

0.81

 

 

869

 

 

8.42

 

 

8,771

 

 

52,969

 

 

86,523

 

 

1.58

 

20

 

 

816

 

 

10.2

 

 

53,119

 

 

0.71

 

 

1,208

 

 

8.03

 

 

13,567

 

 

75,258

 

 

128,378

 

 

1.42

 

36

 

 

1200

 

 

15

 

 

115,404

 

 

0.54

 

 

1,995

 

 

7

 

 

25,788

 

 

142,489

 

 

257,893

 

 

1.23

 

 

 

 

 

Best

 

 

Specified

 

 

Worst

 

 

 

 

 

Best

 

 

Best

 

 

 

 

 

Worst

 

 

 

 

Discounted

 

 

Discounted

 

 

Discounted

 

 

Best Ore

 

 

Waste

 

 

Mine

 

 

Specified

 

 

Mine

 

 

 

 

Cash Flow

 

 

Cash Flow

 

 

Cash Flow

 

 

Tonnes

 

 

Tonnes

 

 

Life

 

 

Mine Life

 

 

Life

 

Pit

 

 

($000s)

 

 

($000s)

 

 

($000s)

 

 

(000s)

 

 

(000s)

 

 

(years)

 

 

(years)

 

 

(years)

 

5

 

 

130,891

 

 

128,299

 

 

130,396

 

 

6,674

 

 

3,927

 

 

1.6

 

 

2

 

 

1.57

 

10

 

 

211,141

 

 

208,204

 

 

208,214

 

 

14,888

 

 

11,647

 

 

2.46

 

 

3

 

 

2.42

 

15

 

 

388,877

 

 

386,575

 

 

377,578

 

 

47,128

 

 

39,395

 

 

4.92

 

 

4.88

 

 

4.92

 

20

 

 

463,925

 

 

460,976

 

 

437,613

 

 

67,786

 

 

60,591

 

 

6.49

 

 

6.45

 

 

6.56

 

36

 

 

519,330

 

 

512,607

 

 

441,315

 

 

115,385

 

 

142,508

 

 

10.27

 

 

10.35

 

 

10.35

 

 

The optimal shell chosen (pit 36) used a gold price of $1,200 per ounce and contained 115 million tonnes of ore. Material classified as Inferred Mineral Resources were used to define the pit size, as this material presents an opportunity, but Inferred Mineral Resources were not included in the reporting of Mineral Reserves or used in the evaluation of the mineral economics. Pit shell 36 was the basis for the final mine design of the pit and infrastructure; a larger $2,000 per ounce gold pit shell was used as a boundary to ensure that potential long term resources were not sterilized. Figure 15.6-2 is an illustration of the ultimate pit shell 36.

 

175


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 15.6-2                    Plan of Whittle Shell 36

 

176


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

16.0                        MINING METHODS

 

Tahoe’s Shahuindo mine consists of an open pit mine and processing facility that is currently in the start-up and commissioning stage. The open pit will be mined in a sequence of phased cutbacks. The mining method used is a conventional drill, blast, shovel and dump truck operation. The mining will be executed under an alliance style contract similar to mining operations at Tahoe’s La Arena mine. Mining will be carried out on two 12 hour shifts, operating 7 days a week.

 

16.1                        Geotechnical

 

Tahoe commissioned Anddes to conduct a geotechnical review and slope angle design for the open pit (Anddes, 2015d). The final version of the report was submitted in October 2015. The Anddes report consisted of a review of the studies provided by Golder and Associates (2012), and further recommendations were made for the slope parameters of the Shahuindo mine. The recommendations made by Anddes are included in Table 16.1-1, and were based on the material strength properties and structures within the sector and the depth of the sector.

 

Table 16.1-1                         Anddes and Associates Geotechnical Parameter Recommendations

 

Geotechnical

 

 

Bench

 

 

Bench

 

 

Maximum

 

 

Maximum Overall Inter

 

Sector

 

 

Height (m)

 

 

Width (m)

 

 

Batter Angle (°)

 

 

Ramp Angle (°)

 

Zone 1

 

 

8

 

 

8

 

 

63

 

 

33

 

Zone 2

 

 

8

 

 

8

 

 

55

 

 

30

 

Zone 2

 

 

8

 

 

8

 

 

55

 

 

30

 

Zone 2A

 

 

8

 

 

8

 

 

45

 

 

24

 

Zone 3

 

 

8

 

 

8

 

 

75

 

 

37

 

Zone 3A

 

 

8

 

 

8

 

 

58

 

 

31

 

 

The average Rock Mass Rating (RMR) (Bieniawski, 1976) ranges from 23 to 44 from test work conducted on 12 geotechnical holes (fair to poor rock mass quality), 40 to 53 for the intrusive units (fair) and 29 to 40 for the breccias (poor). Rock mass shear strengths were evaluated using the semi-empirical Hoek-Brown failure criterion (2002), which can incorporate varying levels of disturbance to the rock mass caused by mining. The shear strength of discontinuities were evaluated based on the results of laboratory direct shear testing, indirect or subjective measurements of discontinuity characteristics, and engineering judgment based on Anddes’ experience in similar rock masses at other large open pit mining projects.

 

Slope stability analyses included kinematic assessments based on the structural mapping and core/borehole logging data, and subsequent deep-seated limit equilibrium analyses of the inter ramp and

 

177


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

overall pit slopes to validate the kinematic bench and inter ramp designs and evaluate the influence of the rock mass competency, discrete fault zones, groundwater pressures and the possible influence of shear strength.

 

The pit configuration proposed by Anddes was used in the pit optimization process. However, this model only calculated the inter-ramp angle which does not include ramp accesses. The overall slope angle used for the optimization at the Shahuindo mine was 28 degrees. This was shallower than the recommendation of Anddes, as allowance was made to include ramp access and for the topographic terrain variability. For the mine design of the Shahuindo mine, the recommendations of Anddes were used and are included in Table 16.1-2, and Figure 16.1-1.

 

The Shahuindo open pit falls within Zone 3 of the Peru Seismic zoning. According to this zone, the Shahuindo mine must adhere to the Standard E.030 earthquake resistant design of National Building Regulations (2006). This standard accounts for the high seismicity with a factor zone (Z) of 0.4. According to the historical information collected by Silgado (1978), an area close to the Shahuindo mine has recorded earthquakes of VI intensities in the modified Mercallie Scale.

 

Probabilistic analysis has determined the maximum acceleration for Shahuindo is 0.17 m/s2 for a one in 100 year event with a 10% chance of exceeding within 50 years. A value of 0.085 m/s2 within a one in 100 year event has been factored into the design of slopes.

 

Table 16.1 -2                      Shahuindo Geotechnical Parameters

 

 

 

 

 

 

 

 

 

 

Optimisation

 

 

Mine Design

 

 

 

 

Bench

 

 

Bench Width

 

 

Overall Slope

 

 

Maximum Batter

 

 

Maximum Overall

 

Area

 

 

Height (m)

 

 

(m)

 

 

Angle (°)

 

 

Angle (°)

 

 

Slope Angle (°)

 

Zone 1

 

 

8

 

 

8

 

 

28

 

 

63

 

 

33

 

Zone 2

 

 

8

 

 

8

 

 

28

 

 

55

 

 

30

 

Zone 2

 

 

8

 

 

8

 

 

28

 

 

55

 

 

30

 

Zone 2A

 

 

8

 

 

8

 

 

28

 

 

45

 

 

24

 

Zone 3

 

 

8

 

 

8

 

 

28

 

 

75

 

 

37

 

Zone 3A

 

 

8

 

 

8

 

 

28

 

 

58

 

 

31

 

 

178


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 16.1-1                    Geotechnical Zone Areas

 

16.2                        Hydrogeology and Hydrology

 

In October 2012, Ausenco Vector (Ausenco) delivered a technical memorandum of the hydrogeological studies that were conducted during March 2012 through Oct 2012 (Ausenco, 2012). The report involved a program of fieldwork drill holes and piezometers, hydrogeological characterization and numerical modeling of the phases within the pit in natural condition and after mining was completed. The outcomes of the report also took into consideration the work completed and recommended by Anddes and Golder Associates (2012).

 

MODFLOW-SURFACT finite software was used to model the expected water flow rates into the pit to be the following;

 

·                  For the starter pit, the level of groundwater intercepted slightly inflows of 0.9 L/s; pore pressures are not determinants in the pit slope stability.

 

·                  For the final stage, the level of groundwater intercepted inflows of about 7.7 L/s.

 

179


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Montgomery Watson Harza (MWH) were commissioned in 2015 to update the hydrologic and hydrogeologic models for the Shahuindo property, including a site-wide water balance, in support of the modification to the existing EIA (Montgomery Watson Harza, 2015). MWH estimated annual precipitation to be 600 mm/year in the upper elevations of the project area and up to 1,400 mm/year in the lower parts of the valleys. MHW determined that the water table was on average 45m below the surface, though in topographic extremes the depth varied from 1.1m to 189m below surface.

 

MWH identified 11 hydrogeological units which were included in their model. Two types of aquifers were identified; the first is in the co-alluvial and alluvial unconsolidated material lying on bedrock and the second in fractured rock material, principally the Chimu sandstone formation, which is the best host rock for a water supply.

 

Annual projected groundwater inflows into pit over the life of mine are listed in Table 16.2-1.

 

Table 16.2-1                         Predicted Water Inflows during Mining

 

 

 

 

Projected Inflow

 

Year

 

 

L/s

 

1

 

 

0

 

2

 

 

0

 

3

 

 

1

 

4

 

 

12

 

5

 

 

17

 

6

 

 

17

 

7

 

 

16

 

8

 

 

15

 

9

 

 

12

 

10

 

 

18

 

11 (post-mining)

 

 

20

 

12 (post-mining)

 

 

25

 

 

Water inflows during mining will be controlled via the use of in-pit sumps and dewatering pumps with water routed to holding ponds for use in processing. It is likely all of this water will be consumed by the process facilities in the dry season, but a portion will require treatment prior to discharge during the wet season.

 

180


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

16.3                        Mine Layout

 

The open pit designs are based on an optimized pit shell followed by a detailed design and development of phased plans. Geotechnical parameters and recommended pit slopes are outlined in Section 16.1. The following criteria were used for the open pit design:

 

·                  The designs employ a minimum cutback width of 25m.

 

·                  The haul roads were designed at 27m, (23m operational width plus 4m for berms and drainage) to allow for two-way safe passage of the 90 tonne capacity haul trucks that have an operating width of 6.1m. Single lane ramps were used at the base of the pit with a width of 14m on the last 4 benches.

 

·                  Maximum center line haul road gradient of 10%. For sections of the haul road that may curve along the outside of the pit, the inside gradient of the ramp has a maximum gradient of 11-12%.

 

The open pit at Shahuindo contains eight phases. The cutbacks have been designed considering the best ramp positions, pit access, geotechnical recommendations and overall volume. The stages of the open pit are designed to smooth the tonnage movement per period, starting with small starter pits within the overall final pit footprint. The phases are mined in order from Pit 0 to Pit 8. The highest elevation for the Shahuindo pit is 3,154 mRL and the deepest component is 2,696 mRL The highest pit wall of the design is 270m in height.

 

The mine waste facilities have been designed as a two stage facility consisting of:

 

·                  Starter waste dump used for the waste material until period 2018.

 

·                  Main waste dump constructed out of the waste from the starter pit.

 

·                  20Mt of waste is planned to backfill the Northern Phase 6 area of the open pit, or alternatively a new waste facility in the northwest valley will be included later in the mine life.

 

The location of the dumps has been located close to the pits to minimize hauling. The footprint of the waste dump has been drilled to ensure no sterilization of the future resources. The main waste dump is a valley fill dump; the dump and the under drainage system for the waste dump was designed by Anddes. The overall slope of the waste dump was designed at 2.5:1 (horizontal: vertical).

 

The waste dump will be constructed in 10m lifts working from the bottom up. The first stage of the waste dump has a capacity of 20Mt and the main waste dump has a capacity of 100Mt. The starter waste dump was designed to minimize the capital expenditure at the start of the project. Table 16.3-1 outlines the waste dump capacities that includes the main and starter waste dump volumes. The waste

 

181


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

is assumed to have an average bulk density of 1.75 tonnes/ m3; this includes a swell and compaction factor of waste to be approximately 1.3 or an increase of 30% of the original volume.

 

Initially some waste will be used to build and or widen haul roads and some good quality waste material is also scheduled for the construction of the life of mine leach pad base.

 

Table 16.3-1                         Waste Dump Volumes

 

 

 

 

Top

 

 

Bottom

 

 

Volume

 

 

Capacity

 

Waste Dump

 

 

Elevation

 

 

Elevation

 

 

(m3)

 

 

(t)

 

Starter Waste

 

 

2650

 

 

2830

 

 

11,692,400

 

 

20,461,700

 

Main Waste

 

 

2540

 

 

2910

 

 

58,287,500

 

 

102,003,200

 

Total

 

69,979,900

 

 

122,464,900

 

 

Two suitable locations in valleys to the northwest and southwest of the pit were considered for leach pad construction. The southwest valley was chosen as the final location for the Phase 2 LOM leach pad due to no restrictions on land ownership as per the waste dump area, and proximity to the processing plant. Geotechnical investigations by Anddes show the area is suitable for the leach pad. At the effective date of this report, the designs are well advanced by Anddes with detailed engineering in progress. The Phase 1 leach pad locations were chosen on areas amenable to easy construction with minimal capital expenditure, and allow for gravity feed to the process plant. The Phase 1 leach pads have a short construction time and low capital expenditure; this allowed a short lead time to first production at the Shahuindo Mine.

 

The mine site layout has been designed taking into consideration the future expansion of the Shahuindo open pit and infrastructure so no sterilization will occur in the upcoming projects. The final layout for the Shahuindo open pit is presented in Figure 16.3-1. This layout is considered to be the final layout for the project.

 

182


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 16.3-1                    Shahuindo Mine Layout Plan

 

16.4                        Mining

 

The Shahuindo mine has been planned as an open pit truck and shovel and excavator operation. The conventional truck and loading unit method provides reasonable cost benefits and selectivity for this type of deposit. Only open pit mining methods are considered for mining at Shahuindo.

 

Mining of the Shahuindo open pit is to be conducted under an alliance agreement with local contractor STRACON GyM. The material at Shahuindo will be drilled and blasted on 8m benches, using 156mm diameter blast holes and a powder factor of 0.25 — 0.20 kg/BCM. Loading of ore and waste will be with diesel powered excavators and rigid frame dump trucks. The ore will be hauled to the dump leach pad or crusher, with the waste hauled to the waste dump.

 

It is expected that the drill penetration rate will be consistent between ore and waste. In addition, the deeper benches do not show any changes in the mechanical properties of the rock mass with only the oxide zone being mined. Blasting parameters were chosen by the mining contractor after reviewing the rock properties. The unconfined compressive strength (UCS) varies from 16 MPa in high alteration areas up to 120 MPa in the bedrock. The average penetration rate is 40 m/h which approximately corresponds to a UCS of 32 MPa. Table 16.4-1 shows the drilling and blasting parameters for the Shahuindo open pit.

 

183


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 16.4-1                         Drill and Blast Technical Parameters

 

Drilling Parameter

 

 

Units

 

 

Ore

 

 

Waste Rock

 

Hole Diameter

 

 

mm

 

 

156

 

 

156

 

Drilling Pattern

 

 

Burden/Spacing (m)

 

 

4.78 / 5.5

 

 

5.22 / 6

 

Bench Height - Nominal

 

 

Meters

 

 

8

 

 

8

 

- Operative

 

 

Meters

 

 

9-10

 

 

9-10

 

Sub Drilling

 

 

Meters

 

 

0.8

 

 

0.8

 

Re-Drilling

 

 

% Total

 

 

2.70%

 

 

2.70%

 

Penetration Rate

 

 

m/hr

 

 

40

 

 

40

 

Powder Factor

 

 

kg/BCM

 

 

0.25

 

 

0.20

 

 

An unsensitized gassable bulk emulsion matrix is the primary explosive used for blasting. The emulsion matrix is shipped as an oxidizer and must be sensitized with a chemical gassing technology to become detonable prior to use. This product is being successfully used at Tahoe’s La Arena mine, producing an acceptable rock size distribution after blasting due to high shock energy produced. The logistics for this product are already in place at the mine site. Initiation will be by non-electric detonators using cord and surface delays to control the initiation sequence to produce good fragmentation.

 

The Shahuindo mine will operate with an over-trucking model which means that the production will be limited by the loading fleet, rather than by truck availability.

 

The running surface on the haul roads of 23m width has been designed using three times the truck width following international operational practices and Peruvian safety regulations. Single-lane haul roads of 14m width were incorporated in the bottom four benches of the pit to maximize ore recovery. The designed haul roads include two 0.5m drains on each side of the ramp and one additional safety berm.

 

For the run of mine dump, limited leach blending will be required for some softer materials. A blend ratio of 2:1 (two coarse ore to one fine ore) will be employed as a minimum where required to ensure no permeability problems arise.

 

After 2018, the crushing and agglomeration plant will be commissioned with no restrictions on blending.

 

Tahoe will mine the Shahuindo open pit using the same mining method as the La Arena mine. The La Arena mine has been used as the basis for the mining method, operational structure and machinery at Shahuindo, as it represents the best value for the project. The Shahuindo mine will also utilize the same mining contractor as the La Arena mine; STRACOM GyM has already started operation under an alliance agreement.

 

184


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

16.5                        Pit Design

 

16.5.1              Bench Height

 

Pit designs were created to use 8m benches for mining. This corresponds to the resource model block heights which Tahoe believes to be reasonable with respect to dilution and equipment size anticipated to be used in mining.

 

16.5.2              Final Pit Design

 

The final ultimate open pit design for the Shahuindo deposit is illustrated in Figure 16.5-1.

 

16.5.3              Comparison of Final Pit Design to the Optimum Whittle shell

 

A comparison between the LOM pit design and the Whittle optimization was completed with the results illustrated in Table 16.5-1. There was a total difference of about one percent when comparing the design to the chosen Whittle shell (shell 36). The difference is attributed to the following factors;

 

·                  Slope parameters in the design incorporated individual geotechnical sectors, where the Whittle optimization assumed an overall slope angle of 28 degrees.

 

·                  Waste tonnes were increased slightly due to the design which included the life of mine haul roads while maintaining the minimum mining width.

 

·                  Areas that were below the minimum mining width or deemed not mineable at this point of time were omitted from the design. Further drilling may define these areas as mineable into the future.

 

Table 16.5-1                         Comparison of Pit Design to Whittle Shell

 

Item

 

Difference

Ore tonnes

 

97

%

Au grade

 

99

%

Ag grade

 

99

%

Au ounces

 

96

%

Ag ounces

 

96

%

Waste tonnes

 

105

%

Total tonnes

 

101

%

 

185


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 16.5-1                    LOM Pit Design

 

186


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

16.6                        In-pit Inferred Resources

 

Inferred Mineral Resources inside the pit total 1.9 million tonnes with average grades of 0.50 g/t Au and 8.77 g/t Ag. While Inferred Mineral Resources were considered as waste and not used in the economic analysis, successful conversion to either Measured or Indicated classifications through further drilling would result in an increase of approximately 30,000 ounces of gold and 530,000 ounces of silver to the life of mine production totals.

 

16.7                        Mine Production Schedule

 

The mining strategy at Shahuindo consists of two phases: Phase 1entails mining higher-grade starter pits and delivering the ore to the two Phase 1 leach pads (pads 1A and 2A) for ROM leaching. Phase 2 includes the addition of a crushing and agglomeration process facility, a large leach pad (pad 2b), and mining the remainder of the deposit at a higher rate.

 

16.7.1              Initial Mining Strategy: Phase 1

 

The short term strategy for the mining operation at Shahuindo will commence with the mining of a smaller operation that does not include crushing and agglomeration. The smaller operation consists of mining small starter pits that will have a duration of approximately 27 months and two leach pads with a combined capacity of 11.5 million tonnes. The initial strategy was designed to take advantage of the near-surface coarse-grain sandstone-hosted ore which does not require crushing and agglomeration.

 

The initial starter pit is located in a sandstone dominant location at the southern end of the final pit design, located close to the leach pads. Fine-grained high-grade ore from the northern starter pits will be blended with sandstone and placed on the top lift of the Phase 1 leach pads. Good quality waste material and very low grade ore from the initial starter pit will be used for construction of the heap leach Phase 2b pad buttress and other leach pad facilities. Currently, it is anticipated that approximately 4 million tonnes of fill material will be required for the construction of the heap leach pad Phase 2b. The starter pit has a mine life of 2.25 years; this will enable time for further processing blending tests to be completed for the Phase 2 leach pad with revenue from the starter pit used to assist with the capital expenditure for the larger heap leach operation (Phase 2).

 

The location of the starter pits and the development of the Phase 1 leach pads is shown in Figure 16.7-1. Construction of the Phase 1 leach pad (pad 1A) and process facilities commenced in May 2015 and were complete in November 2015. Mining of the starter pit commenced in November 2015 utilizing 75 tonne excavators and 35 tonne tip trucks. An average of approximately 28,000 tonnes per day (ore and waste) will be mined in Phase 1.

 

187


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 16.7-1                    Site Plan at the end of 2017

 

16.7.2              Mining Strategy: Phase 2

 

The mining strategy for Phase 2 will include a crushing and agglomeration processing facility and the Phase 2 leach pad (pad 2B). This facility and leach pad is scheduled to be constructed during 2016 and 2017, ready for production at the start of 2018. Phase 2 includes an increase in total tonnes mined from 28,000 tonnes per day in Phase 1 to a maximum of 89,000 tonnes per day, which will require an upgrade to a larger sized fleet. The Phase 2 leach pad will process a maximum of 13.1 million tonnes of ore per year. The Phase 2 site layout plan is included in Figure 16.7-2.

 

188


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 16.7-2                    Final Phase 2 Site Plan

 

Phase 2 includes a stockpile located close to the crushing and agglomeration facility. The stockpile capacity is about 8 million tonnes of ore. This stockpile is used to smooth the mining fleet requirements, to maximize the productivity of the mining equipment to reduce costs, and for blending and optimization of ore grades to the pad.

 

16.7.3              Mining Schedule

 

The mining schedule for Phase 1 was developed using Gemcom MineSched™ software considering a maximum fleet capacity of 28,000 tonnes per day. The Phase 1 ore production was driven by the space available on the leach pad and the amount of near-surface high-grade sandstone-hosted ore.

 

The mining schedule for Phase 2 was developed using the MineMax™ open pit scheduling software which maximizes the NPV using linear programming. The Phase 2 mining schedule was constrained by three loading units with a maximum total capacity of 90,000 dry tonnes per year and by the crushing and agglomeration facility which has a maximum capacity of 36,000 tonnes per day.

 

189


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The waste material is hauled to the waste dump as previously described in Section16.3. The ore is hauled to either a low-grade stockpile or to the crusher pad where trucks can direct tip into the crusher feed bin, which has a live capacity of 240 tonnes. A track feeder feeds the material from the crusher feed bin to a Mining Machinery Developments (MMD) sizer that crushes the ore to 80% passing 100mm. At the end of the open pit mine life, the material in the low-grade stockpiles will be loaded into trucks at the stockpiles and rehandled to the crusher bin.

 

The geochemical characterization study described in Section 20.0 has been imported into the geological model used by the mine planning engineers. The distribution of potentially acid generating (PAG) material in the model is included in the mine schedule to ensure that it is mined at an appropriate time to allow the material to be encapsulated at the destination and not be in contact with the elements. Information from blast hole samples will also be used to improve the accuracy of the model as mining takes place.

 

The mine production schedules for the Shahuindo mine are summarized in Table 16.7-1. The tonnes are reported in-situ dry tonnes after applying 2% ore losses and a 5% dilution factor.

 

Table 16.7-1                                    Mine Production Schedule

 

 

 

 

Unit

 

 

2016

 

 

2017

 

 

2018

 

 

2019

 

 

2020

 

 

2021

 

Ore Tonnes

 

 

k tonnes

 

 

5,756

 

 

5,602

 

 

10,289

 

 

13,412

 

 

13,039

 

 

12,352

 

Au Grade

 

 

g/t

 

 

0.68

 

 

0.54

 

 

0.64

 

 

0.48

 

 

0.48

 

 

0.51

 

Ag Grade

 

 

g/t

 

 

5.95

 

 

5.73

 

 

7.24

 

 

6.45

 

 

7.05

 

 

6.47

 

Waste Tonnes

 

 

k tonnes

 

 

4,954

 

 

4,113

 

 

21,835

 

 

18,895

 

 

19,246

 

 

19,893

 

Strip Ratio

 

 

waste:ore

 

 

0.86

 

 

0.73

 

 

2.12

 

 

1.41

 

 

1.48

 

 

1.61

 

Total Tonnes

 

 

k tonnes

 

 

10,710

 

 

9,715

 

 

32,124

 

 

32,306

 

 

32,285

 

 

32,245

 

Au Mined

 

 

k oz

 

 

126

 

 

97

 

 

212

 

 

206

 

 

200

 

 

201

 

Ag Mined

 

 

k oz

 

 

905

 

 

1,090

 

 

2,524

 

 

2,741

 

 

2,954

 

 

2,568

 

 

 

 

 

Unit

 

 

2022

 

 

2023

 

 

2024

 

 

2025

 

 

Total

 

 

 

 

Ore Tonnes

 

 

k tonnes

 

 

16,066

 

 

14,405

 

 

12,732

 

 

7,236

 

 

110,890

 

 

 

 

Au Grade

 

 

g/t

 

 

0.50

 

 

0.59

 

 

0.52

 

 

0.49

 

 

0.53

 

 

 

 

Ag Grade

 

 

g/t

 

 

7.79

 

 

7.16

 

 

6.36

 

 

7.30

 

 

6.86

 

 

 

 

Waste Tonnes

 

 

k tonnes

 

 

16,395

 

 

15,922

 

 

17,497

 

 

11,106

 

 

149,855

 

 

 

 

Strip Ratio

 

 

waste:ore

 

 

1.02

 

 

1.11

 

 

1.37

 

 

1.53

 

 

1.35

 

 

 

 

Total Tonnes

 

 

k tonnes

 

 

32,461

 

 

30,327

 

 

30,230

 

 

18,342

 

 

260,485

 

 

 

 

Au Mined

 

 

k oz

 

 

258

 

 

273

 

 

215

 

 

113

 

 

1,900

 

 

 

 

Ag Mined

 

 

k oz

 

 

3,599

 

 

3,143

 

 

2,663

 

 

2,246

 

 

24,470

 

 

 

 

 


*Note:           The total material moved and grades are slightly different (~1%) to the Mineral Reserve in Section 15.0 due to rounding differences between software packages.

 

190


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

16.8                        Mining Equipment

 

Phase 1 mining will use a smaller mining fleet and no crushing and agglomeration circuit. Phase 2 will include a crushing and agglomeration circuit coupled with an upsized mining fleet.

 

The mobile equipment selection was conducted by anticipating the fleet requirements that could be used in the open pit operation. The Phase 1 mining fleet includes a CAT 374 excavator matched with a fleet of 35 tonne 8 x 4 tip trucks. Phase 1 mining assumes an average rate of 28,000 tonnes per day (ore and waste). The Phase 2 mining fleet includes RH900 shovels matched with a fleet of 90 tonne Caterpillar rigid frame haul trucks. Phase 2 mining assumes an average production rate of 87,000 tonnes per day (ore and waste).

 

Table 16.8-1 shows the size of machinery that will be required at each stage of pit development. Only primary equipment units are listed.

 

Table 16.8-1                         Primary Mining Equipment Required for Shahuindo

 

Mining Phase

 

Primary Mining Equipment

 

Quantity

 

Phase 1

 

Excavator CAT 374

 

2

 

 

32 Tonne Actros Tip Truck (maximum)

 

11

 

 

Sandvik D245 Drills

 

1

 

 

Dozer (Track and Wheel)

 

2

 

Phase 2

 

RH90 Shovel

 

3

 

 

90 Tonne CAT 777D Haul Trucks (maximum)

 

34

 

 

Sandvik D245 Drill

 

3

 

 

Dozer (Track and Wheel)

 

3

 

 

A general overview of the ancillary equipment needed for the production stages of mining is outlined in Table 16.8-2.

 

191


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 16.8-2                         Ancillary Equipment Fleet Size

 

Equipment

 

 

2015

 

 

2016

 

 

2017

 

 

2018

 

 

2019

 

 

2020

 

 

2021

 

 

2022

 

 

2023

 

 

2024

 

 

2025

 

 

2026

 

Tractor CAT D8T

 

 

1

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

Tractor CAT 834

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

Grader CAT 16M

 

 

0

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

Grader CAT 14M

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

Water Truck

 

 

1

 

 

1

 

 

1

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

Fuel Truck

 

 

1

 

 

1

 

 

1

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

Lube Truck

 

 

1

 

 

1

 

 

1

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

 

2

 

Excavator CAT 374

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

1

 

 

The ramp up from Phase 1 to Phase 2 will require a fleet change out over a six month period to reach full implementation. This ramp up has been included in the mining schedule.

 

The mobile equipment selection was conducted by anticipating the fleet requirements, the key parameters used for the calculation of fleet requirements are based on scheduled time, availability, truck and material parameters, and is included in Table 16.8-3. Mining will be conducted by the same contractor, STRACON GyM, utilized at Tahoe’s La Arena mine under an alliance agreement. The mining equipment utilized at La Arena is very similar to the proposed mining fleet at the Shahuindo mine. The data for the mining productivities and costs were based on the La Arena mine.

 

Table 16.8-3                         Maximum Loader Productivity Estimate

 

STRACON GyM Digging Production

 

 

Units

 

 

Caterpillar 374

 

 

RH90C

 

Availability

 

 

%

 

 

88

 

 

88

 

Utilization of Available Time

 

 

%

 

 

83

 

 

83

 

Hours/Day

 

 

hours

 

 

17.53

 

 

17.6

 

Productivity

 

 

tonne (wet)/hour

 

 

825

 

 

1,650

 

Moisture Content

 

 

%

 

 

4

 

 

4

 

Daily Production

 

 

tonne (wet)/day

 

 

14,462

 

 

29040

 

Daily Production

 

 

tonne (dry/day

 

 

13,906

 

 

27923

 

Yearly Production per Digging Unit

 

 

Mtpa

 

 

5.08

 

 

11.9

 

 

Truck productivity is based on haulage routes and travel speeds. The haulage routes were drawn from the pit designs to each of the potential destinations. Additional haulage lines were drawn for

 

192


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

each bench within the pit designs. The speeds were flagged into the haulage string description fields based on location and haul gradient.

 

GEOVIA MineSched™ and Maptek Vulcan™ software were used to calculate the truck hours based on assigned speeds for loaded and empty trucks along each of the haul routes. Resulting haulage strings were drawn by GEOVIA MineSched™ and verified to ensure proper routing of haulage was followed.

 

The available hours per day were adjusted by mechanical availability and operator efficiency. The mechanical availabilities start at 88%, the operator efficiency or utilization factor used is 83%, which accounts for break times, lunches, and shift start-ups and shut downs.

 

Sandvik D245s drills were selected for blast hole and assay drilling. These drills provide the productivity required for production at a low unit cost per meter drilling up to an 8 meter high bench using single pass drilling. Other equipment selected for support functions including dozers, graders, water trucks and other miscellaneous equipment.

 

193


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

17.0        RECOVERY METHODS

 

The Shahuindo Project will be developed in two phases. During Phase 1 (years 2016—2017), acceptable recoveries are achievable from ROM ore direct from the mine to the heap leach pad. In Phase 2 (2018 through the end of the mine life), ore will be crushed and agglomerated to achieve increased recoveries, acceptable percolation, and pad stability over the life of mine.

 

The Phase 1 pilot leach pad (pad 1A) has an area of 18 Ha; a second pad (pad 2A) will be constructed in 2016 to be ready to receive material in 2017. The adsorption-desorption-refining (ADR) process plant capacity has been initially designed to treat 10,000 tonnes of ore per day and will be expanded to process an average of 12,200 tonnes of ore per day in 2016 and 16,500 tonnes of ore per day in 2017. The pilot pad and 10,000 tpd ADR plant have been completed, with commissioning in December 2015.

 

For Phase 2, the crushing, storage, agglomeration and stacking system, and ADR plant are designed to handle 36,000 dry tonnes per day. Cement (up to 6 kg/tonne) and lime (around 2 kg/tonne) will be added to the crushed ore and the mixture agglomerated at three specially designed transfer points by the addition of a barren solution (or water). The agglomerated ore will be delivered to the Phase 2 leach pad (pad 2B) by downhill regenerative overland conveyors. A series of stackable/shiftable conveyors and grasshopper conveyors will deliver ore to a stacking conveyor that will place it onto the pad in 8 or 16 meter high lifts.

 

During the first half of 2016, Tahoe geologists will work to refine the geological model by additional drilling and relogging to aid in improving the geometallurgical model to increase confidence in the proposed material blending schemes. The geometallurgical model will also be improved with pilot leach testing of the different lithologies at varying coarse to fine ratios. The execution plan for Phase 2 will be finalized based on these test programs. Agglomeration recoveries and strength test work are ongoing at SGS in Lima and at the La Arena metallurgical lab.

 

17.1        Phase 1 - Run of Mine Processing

 

17.1.1     Processing Flow Path — Run of Mine Material

 

In Phase 1, gold is recovered via dump leaching of ROM ore, which is trucked to the Phase 1 leach pads and dumped on the leach pad to form lifts. The lifts are irrigated uniformly with a sodium cyanide solution by an irrigation system. As the solution passes through the lift, gold is dissolved, forming a pregnant (gold-enriched) solution. The pregnant solution percolates through the lifts and flows into the solution pond.

 

194


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The pregnant solution is pumped from the solution pond to the ADR circuit where the gold is recovered onto activated carbon. The carbon is stripped of gold to form a solution and the gold is extracted by the process of electrowinning to form a precipitate. The precipitate is dried, mixed with flux and smelted to produce doré. The doré is weighed, sampled and shipped to a refinery for sale.

 

A specific process has been designed for capture, condensation and storage of mercury during the precipitate drying process. The mercury is removed and disposed of by a qualified third party transporter. The plant design includes retort furnace storage to prevent mercury vaporization at ambient temperatures.

 

Slag produced as part of the smelting process is crushed and any prills of gold are recovered and recycled for smelting. Stripped carbon is regenerated and recycled to the adsorption circuit. A flow sheet of the ROM leaching operation is illustrated in Figure 17.1-1.

 

195


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 17.1-1       ROM Process Flow Sheet

 

196


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

17.1.2     Run of Mine Leach Process

 

The mineralized material is transported from the mine face to the leach pad using dump trucks. In order to maximize recovery, the ROM ore will be blended directly from the pit. The scheduling of the ROM ore from the pit will require input from the onsite metallurgical department to ensure the mining blend maximizes the recovery of gold from the ROM ore. The ROM ore will initially be placed on the leach pad at a rate 10,000 tpd, ramping up to an average of 12,200 tpd in 2016 and 16,500 tpd in 2017 as the plant capacity is expanded.

 

Lime is added at the required quantity to the leach pads using the mining fleet at the time the irrigation pads are being formed. A spray irrigation system is used to apply the cyanide solution of 200 ppm cyanide concentration at 400 m3/h at to each pad lift. The vertical height of each lift has been designed at 8m by Anddes (2015e, 2015f, 2015h). As the solution passes through the heap, the solution will leach the gold and silver out of the ore. The pregnant (gold-enriched) solution is collected in the pregnant leach solution (PLS) collection pond and pumped by two 14-inch x 12-inch horizontal centrifugal pumps to a series of adsorption columns.

 

The cyanide for heap irrigation is first prepared at 27% concentration. Eight tonnes of sodium cyanide (NaCN) is added to fresh water in a 25m3 preparation/agitation tank and the concentrated solution transferred via pump to a storage tank of 140m3 capacity. The concentrated cyanide solution is metered into the barren leach solution to increase the cyanide level up to 200 ppm before pad irrigation. A second cyanide preparation tank is located near the desorption area for gold stripping. Cyanide concentration for stripping is 0.5% (5,000 ppm). Both cyanide mixing units have a scrubber, pH meter and hydrogen cyanide detector.

 

The solution application will advance in nominal 6,000m2 cells (60m x 100m). The barren solution is pumped by 305mm x 355mm (12-inch x 14-inch) horizontal pumps. The number of pumps will gradually be increased as the leaching area increases according to the ore tonnes placed. Each leach cell has an irrigation system consisting of a 200mm (8-inch) header and four 100mm (4-inch) sub-headers. The wobblers network are a 6m x 6m triangle pattern with No. 7 wobblers, 19mm (¾-inch) connection fitting and low angle (18°) outlets to minimize solution losses.

 

The irrigation rate is between 8 to 10 liters per hour per square meter of leaching area. Emitters are 16mm hose installed at 63cm spacing. Each emitter will handle 4 liters per hour. At any given time, there will be a minimum of five irrigation systems under leaching connected to sub-headers, with two systems on standby (one being installed on a new cell with fresh ore, and one being dismantled after 80 days leaching cycle). The flow rate of pregnant solution to the collection pond will be 367 m3/hour per leaching cell under the 10,000 tpd plant capacity scenario.

 

197


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The test work conducted indicates that irrigating the ROM ore for 80 days is required. The irrigating of each lift for the 10,000 tpd rate is shown in Table 17.1-1.

 

Table 17.1-1        Phase 1 Leach Pad Schedule

 

Leach Pad Phase 1

Vertical Lift Height
(meters)

 

Irrigated Duration
(days)

 

Lift 1

8

 

40

 

Lift 2

8

 

60

 

Lift 3 - Final Height

8

 

80

 

 

The 10,000 tpd ADR plant has the capacity to process a solution rate of 400 m3/hr at the projected mine head grades and volume under irrigation. Diligent monitoring of the leach pad will be required as to insure potential permeability/channeling do not negatively impact gold recovery from the ROM ore.

 

17.1.3     Process Plant

 

Five adsorption circuits are currently available for the treatment of pregnant solution in the ADR plant. Each circuit consists of six columns containing 4 tonnes of activated carbon. The activated carbon adsorbs the gold, silver and some minor impurities such as mercury and copper. The columns have a total treatment capacity of 1,750 m3/h.

 

The carbon from the adsorption tanks, containing approximately 4 kg of gold per tonne carbon is taken to the desorption plant where the gold is extracted from the carbon using a sodium hydroxide solution in a desorption reactor. The gold and silver is recovered through electrowinning to obtain a precipitate that is dried in the press filters, which then goes through the smelting stage to obtain the doré bars.

 

The barren solution that flows from the adsorption circuit returns to the leach circuit through the barren tank, and the level of reagents is adjusted prior to being fed back into the process. The carbon in the adsorption circuit is stripped and regenerated twice weekly in the 8m3 desorption reactor. The carbon regeneration takes place in batches in two steps:

 

1.     acid wash every adsorption cycle

 

2.     thermal regeneration every 3 adsorption cycles.

 

The acid wash adsorption cycle consists of thoroughly washing the carbon with fresh water to ensure that no entrainment of cyanide solution is present. It is then washed with hydrochloric acid (HCI) at a concentration of 2.5%. The acid wash is required to dissolve and remove carbon scale; the duration of this step, including water rinsing, takes approximately three hours.

 

 

198


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The thermal regeneration cycle involves dewatering the carbon solution on a vibrating screen and then heating the carbon up to 750°C for 10 to15 minutes in the regeneration kiln, which regenerates the carbon. After the regeneration kiln, the carbon is dropped into a water quenching tank at room temperature, and is then dewatered and screened to remove fines (minus 6 mesh). The coarse fraction of carbon (6 x 12 mesh) will return back to the adsorption circuit, while the fine carbon is filtered and stored. The fine fraction weight is calculated to be approximately 0.5 tonne of carbon per month depending on the quality of the carbon.

 

17.2        Phase 2 — Crushing and Agglomeration

 

17.2.1     Process and Flow Path

 

For Phase 2, the ROM material will be trucked to the crushing pad via 90 tonne haul trucks and fed into a 240 tonne hopper. The material that is -100mm reports directly to the primary crushed ore stockpile and the oversize material is fed to the crusher where it is reduced to p80 of -100mm and fed to the stockpile. The stockpile has a live capacity of two hours and a total capacity of 24 hours.

 

The material is extracted from the stockpile via a vibrating feeder and is fed through a static screen, where the fine (-75mm) fraction reports to the agglomeration feed conveyor and the course fraction (+75mm) reports directly to the overland conveyor.

 

The cement and lime addition is conducted on the agglomeration feed conveyor where the quantity of cement and lime added is controlled by a weightometer. The barren solution combined with the lime and cement is added to the agglomeration conveyors at three transfer points before it is added to the overland conveyor. The crushing and agglomeration flow sheet is illustrated in Figure 17.2-1.

 

The agglomerated material is fed to the leach pad via the downhill regenerative overland conveyor. A series of stackable/shiftable conveyors and grasshopper conveyors will deliver the ore to a stacking conveyor that places it onto the pad in 8 or 16 meter high lifts. The conveying and stacking flow sheet is illustrated in Figure 17.2-2.

 

The process flow path for the material is the same as Phase 1 for the leaching, adsorption and desorption as described in in Section 17.2.1. An expansion is required for Phase 2 to accommodate the increased capacity to 36 ktpd. The expansion will necessitate increasing the ADR trains from one to four and increasing the PLS pond capacity from 25,000m3 to 80,000m3. The expansion will also increase the number carbon strips required from two to seven per week.

 

199


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 17.2-1 Crushing, Stockpile, Screening and Agglomeration Flow Sheet

 

200


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 17.2-2 Overland Conveyor and Stacking System Flow Sheet

 

201


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

17.2.2     Process Plant

 

The processing of Phase 2 ore is the same as Phase 1 as described in Section 17.1.3. Due to the increase in tonnes to be treated on a daily basis, the Phase 2 processing plant will include an extra reactor for gold desorption with two additional electro winning cells and two DC rectifiers to accommodate the larger flows.

 

17.3        Heap Leach Pad Design by Anddes

 

The leach pad designs have been completed by Anddes (2015a, 2015c). The initial Phase 1 heap leach pad (pad 1A) has been constructed and is in operation. Field investigations for the Phase 2 leach pad (pad 2B) were completed in the second quarter of 2015. The current pre-feasibility design has a maximum capacity of 208 million tonnes of ore, with a total lined area of 2,218,800 m2. The design includes five ponds that include a PLS collection pond, an event pond, raincoat pond and two sedimentation ponds. The Phase 2 pad design criteria are summarized in Table 17.3-1.

 

Table 17.3-1        Phase 2 Leach Pad Design Criteria

 

Description

Unit

Design Criteria

Dry tonnes per day

tonne/day

36,000

Bulk density

tonne/m3

1.7

Overall slope

H:V

2.5H:1V

Operating time

months

120

Average ore moisture

%

4.2

Nominal irrigation rate

L/h/ m2

10

Maximum irrigation rate

L/h/ m2

11

Irrigation type

wobblers/emitters

Maximum irrigation flow

m3/hr

1500

Evaporation losses (irrigation)

%

3

Evaporation losses (ponds)

%

100

Evaporation losses (irrigated cells)

%

90

Free percolation flow (drain-down

hr

24

PLS pond capacity

m3

80,000

Sedimentation pond 1

m3

10,000

Sedimentation pond 2

m3

8,000

Raincoat pond

m3

40,000

Big event pond

m3

300,000

Pond slope

H:V

2:1

Leak detection system

yes

Maximum height

m

180

Maximum capacity

tonnes

208 million

 

202


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Pond capacities are based on water balance studies conducted by Anddes (2015b). The use of raincoats (HPDE covers) on pad 2B will be required to minimize the amount of water requiring treatment prior to discharge during the wet season. The HDPE covers will act to prevent infiltration of precipitation into the leach pad, minimize dilution of the leach solutions and reduce the amount of effluent requiring treatment. However, even with the use of raincoats, the Phase 2 process facility will not be in water balance during an average precipitation year. Quantities to be discharged during average precipitation years with the use of raincoats will vary from zero to a maximum of approximately 40,000 m3 per year. The effluent to be discharged during an extreme wet year can reach a maximum average of 46.4 L/s. A water treatment plant will be installed in prior to commissioning of the Phase 2 leach pad to handle the potential discharge of process solutions.

 

17.4        Phase 1 and 2 Process Parameters

 

The main process parameter for Phase 1 and Phase 2 are summarized in Table 17.4-1.

 

Table 17.4-1        Phase 1 and Phase 2 Process Parameters

 

Parameter

ROM

Crush Ore

Dry tonnes of ore/day*

14,300

36,000

Au Head grade

0.64 g/t

0.52 g/t

Average flow rates

400 m3/H

1600-1800 m3/H

Leach time

80-90 days

75-85 days

Lift height

8 meters

8-16 meters

Crush size

100% minus 300mm
(p80 minus 150mm)

100% minus 75mm

NaCN consumption

0.2 kg/tonne of ore 1.5

0.3 kg/tonne of ore

Lime consumption

kg/tonne of ore

1.0 kg/tonne of ore

Cement consumption

no addition

6 kg/tonne (-75mm fraction)

Average Au Recovery

73%

80%

 


*tonnes processed

 

 

 

203


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

18.0        PROJECT INFRASTRUCTURE

 

The infrastructure and services to support the Shahuindo mine include the following major components:

 

·      Site Access Road;

 

·      Power supply including back-up power and distribution;

 

·      Water supply for process water, potable water and fire water;

 

·      Sewage system and solid waste disposal;

 

·                  Project buildings including truck shop, explosive magazines, warehouse, maintenance/process warehouse, fuel station and offices;

 

·      Camps for construction and operations including dining facilities; and

 

·      Miscellaneous site services such as security, first aid clinic and communications.

 

18.1        Services and Infrastructure

 

18.1.1     Roads

 

Access to Shahuindo is via a national highway that runs north-south along the east side of the Condabamba river. From the highway, the Shahuindo site is west of the junction at Pomabamba on an unsealed road four kilometers long. There is a concrete bridge on concrete piers which crosses the Condebamba river. The bridge over the river is 90m long and 3.5m wide, built approximately 15 years ago. The Company plans to upgrade the bridge in 2017.

 

A private road enters the mine property a few kilometers from the west side of the bridge. This 11 kilometer unsealed road provides access to the camps, offices, mine, process plant and other project facilities. This road will be improved during construction of Phase 1.

 

All site access and haul roads will be designed according to the Company’s internal standards (Shahuindo Internal Transit Standard) for widths and grade to ensure safe and efficient operations. The location of the access roads are shown in Figure 18.1-1.

 

204


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Figure 18.1-1       Mine Access Road

 

18.1.2     Power Supply

 

The startup power supply will be with generators supplying 1.2MW. Permanent power supply for Phase 2 operations will be from the National Commercial Grid. The total long-term power requirement is calculated to be 7.4MW.

 

The temporary power demand for Phase 1 will be supplied by three small diesel generators for loads near the process plant (800Kw); warehouse, camp and offices (350kw); and at the maintenance workshops (250kW). When permanent power is available in Oct 2017, the small generators will be replaced by one 1.8MW diesel generator as a back-up power source for the site.

 

The Shahuindo substation will connect to the national grid in 2017 at 220kV, distributed on site at 23kV and further stepped down to 4160V, 460V, 220V and 110V. The substation is located at 9152654N 806437E, 4.9 kilometers from the mine and 6.5 kilometers from the process plant.

 

205


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

For Phase 2, power for crushing, agglomeration and ore stacking will be supplied from the process plant substation via 22.9 kV electric overhead line to a secondary distribution system of three small motor control centers located close to the crushing plant, overland conveyors and mobile stacking system.

 

An internal 23 kV line from the plant to the camp (passing through the crusher/conveyor area) will be installed in 2016 to carry energy from the plant to the workshops and camps. The flow will be reverse when connection to the grid is made in 2017, with power coming from the substation feeding the camps, workshops crusher/agglomeration/conveyor system and then the plant.

 

18.1.3     Water Supply

 

Total fresh water consumption for the Phase 1 project will average 10.5 L/s in the dry season with a maximum of 12.7 L/s. This consumption rate, with the use of raincoats, will increase to an average of 33.6 L/s in the dry season and an average of 33.9 L/s (maximum 50.2 L/s) during Phase 2.

 

Total project water supply will be sourced from an 18,000 m3 collection pond of run-off water (3 L/s) and a water borehole source located 300m west of Shahuindo pit (25 L/s). The balance of the required flow will come from pit dewatering (15L/s) which will be pumped at the beginning of year two of mine operations, with water stored in the major events pond during the wet season. There is an option to develop a second water well on one of the high flow hydrogeological test holes.

 

Fresh water for the process plant and leaching will gravity flow from the collection pond to the PLS pond via a 150mm diameter by 3.2 kilometers long HDPE pipeline.

 

Acquisition of a 75 m3/day potable water plant is planned in 2016 for drinking and cooking water.

 

For fire water, an exclusive fire water reserve of 200 m3 will be stored in the bottom half of the process water tank. Additional water trucks will be rented locally for the three temporary small generators in case of a fire emergency.

 

18.1.4     Sewage System

 

There are currently two sewage treatment plants of 40 m3/day capacity each at the mine site. One is located next to the construction camp and the second located next to the new operations camp. Sludge volume generated in both treatment plants are collected and utilized locally for compost production with the treated water recycled back to the process plant. The plant from the construction camp will be relocated to the new camp in early 2017.

 

A third sewage treatment unit of 40 m3/day will be installed in 2016 for the process plant and electrical maintenance areas.

 

206


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

18.1.5     Solid Waste Disposal

 

Solid waste will be disposed fully in compliance of local regulations. There are currently two waste transfer facilities; one of which is a hazardous material storage / hazardous waste transfer station.

 

Solid waste will be disposed of in a solid waste landfill off site. Hazardous materials not permitted to be disposed of in a landfill will be transported to the appropriate facilities.

 

Specific hazardous waste such as used oil, and batteries must disposed of by a Specialized Solid and Dangerous Waste service provider. A certified transport and disposal company will collect all waste to transport offsite for final disposal.

 

18.2        Project Buildings

 

The Shahuindo mine buildings include administration offices, mine warehouse, maintenance shop, explosive magazine, construction camp and permanent camp, kitchen & dining facilities, fuel storage, security buildings, and medical center.

 

18.2.1     Truck Shop

 

The mining fleet for Phase 1 consists of 21 Volvo 8x4 40-tonne trucks, two Cat 374 excavators, two D-8 dozers and a grader. The truck shop for Phase 1 is designed with a semi-open arrangement to include repair bays for small trucks, ancillary equipment, light vehicles, wash and welding areas.

 

For Phase 2, the mining fleet will be 90-tonne dump trucks (Cat 777 or equivalent) with corresponding loading and ancillary equipment. This fleet will have a total capacity for 36,000 tonnes per day. A permanent truck shop will be built in the second half of 2017 to accommodate and service the larger equipment.

 

18.2.2     Explosive Magazine

 

The explosive magazine has one emulsion storage silo installed for the Phase 1 start up. In 2016 this will be increased to two silos and then four silos in Phase 2 (year 2018).

 

Explosives will be delivered by supplier trucks to the site. Each silo has a 60-tonne capacity and is equipped with a pneumatic system for unloading. The silos are configured to have drive-through loading for the Mobile Manufacturing Unit (MMU) truck that will be used to deliver the product to the drill holes. Blending and mixing of the emulsion with the gasifying agent will be accomplished inside of the MMU truck.

 

207


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Two additional storage magazines are included: one powder magazine for storage of boosters, detonation cord, and accessories used to initiate the blasting; and one magazine to store blasting caps. Each of these magazines is located in the explosives storage area near the ANFO/Emulsion silos west of the open pit, separated from the bulk explosives by earthen berms as per regulation.

 

18.2.3     Warehouse and Process Maintenance

 

The warehouse storage area and a covered maintenance work shop area are presently available for Phase 1. The infrastructure will be expanded for Phase 2.

 

18.2.4     Fuel Stations

 

The main diesel storage facility in Phase 1 consists of two project owned 60,000 gallon storage tanks. This facility is complete with fuel dispensing systems. In the first half of 2018, two additional tanks will be installed to achieve a total site storage capacity of 240,000 gallons which is enough fuel to operate the site for 18 days at full mining capacity.

 

There are two additional tanks - one 1,000 gallon diesel storage tank located in the process plant area to supply diesel fuel for the elution boiler, carbon regeneration kiln and the refining furnace; and a second tank of 8,000 gallons dedicated to the emergency generator.

 

Fuel will be delivered to the mine site via the supplier tanker trucks. All storage tanks will be placed in a 110% capacity concrete containment to assure no fuel is leaked to the environment.

 

18.2.5     Offices

 

Administration buildings/offices are already in place at the construction camp and includes water and power supply along with sewage facilities. This facility will be relocated near the new permanent camp in early 2016.

 

18.2.6     Construction and Operations Camps

 

The Shahuindo mine has an existing camp (Sulliden exploration camp) on site with single and multi-room layouts that currently house 500 people. The existing camp has been expanded for use as a construction camp. The expansion included ten modular tent-style housing units each able to accommodate 32 workers, as well as one module with 64 beds for staff workers.

 

Modular bathroom/shower units are equipped with toilets, urinals and showers for each tent including the staff module. The associated sewage treatment system is able to treat the amount of waste generated.

 

208


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The new operations camp is being arranged for up to 800 people near the clinic, dining room and offices. It consists of four new barracks and six refurbished barracks relocated from the construction camp.

 

The majority of the work force is local and are transported by bus from Cajabamba and surrounding villages.

 

18.2.7     Dining Facilities

 

Temporary dining facilities are currently present on site to cater for approximately 1,000 workers and construction personnel. A permanent cooking and dining facility will be built in 2016.

 

18.3        Miscellaneous Site Services

 

18.3.1     Laboratory

 

Chemical assays for full support to the Shahuindo operation will be provided by the La Arena assay laboratory operated by a third party lab, CERTIMIN (certified ISO 9001). The La Arena facility has the equipment and technical capability to conduct the recommended metallurgical column tests (permeability tests) during the course of operations at Shahuindo.

 

For liquid samples such as PLS, barren solution and other solutions used at the refinery, there will be a temporary satellite lab for gold, silver, cyanide concentration and lime quality control.

 

Doré samples will be preliminary assayed at the La Arena laboratory and later in Lima at an external lab.

 

18.3.2     Security

 

Access to the facility will be limited to two main gates to access process and camp areas. Approximately 2 kilometers of fencing is already installed primarily for safety and security reasons. The entrance to the project is currently manned 24 hours a day 7 days a week for identification control, random checks, drug and alcohol monitoring and vehicle check-in/out.

 

18.3.3     Medical Center/Clinic

 

A medical center and ambulance are already present at the construction camp, but will be relocated next to the new operations camp. Emergency medical staff on site include one physician, one paramedic, one nurse and one driver/rescue person.

 

In the event high level medical intervention is needed, the ambulance is equipped and prepared for emergency transport to either Cajabamba Hospital (40 kilometers) or Cajamarca Hospital (100 kilometers).

 

209


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

18.3.4     Communications

 

The infrastructure for radio, telephone and internet communications between Lima, the La Arena mine and the Shahuindo mine is currently in service.

 

A recent upgrade was made to the system connecting the construction camp to the surrounding facilities such as the process plant, new operations camp, future crushing & agglomeration plant, Cajabamba and Cajamarca City. The existing data room and control center will be relocated from the construction camp to the new permanent camp.

 

210


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

19.0        MARKET STUDIES AND CONTRACTS

 

19.1        Metal Contracts

 

The Shahuindo mine will produce gold in the form of doré bars. The weight of the doré bars and preliminary assays are used to calculate gold and silver content and the overall value of each shipment.

 

Several internationally recognized precious metal refineries have expressed interest in refining gold and silver from Shahuindo’s production. The initial production will be refined at Metalor Technologies S.A., (Metalor) refinery in Marin, Switzerland. Metalor is currently used to refine the Company’s La Arena production. Required due diligence for refining Shahuindo’s production by the refinery is underway. Once sustainable production levels are achieved, alternative refining arrangements may be explored.

 

Consistent with the Company’s other doré production, once doré bars are delivered to Metalor’s vault in Lima, Metalor will credit 95% of the estimated gold content in the Shahuindo gold bars to the Company’s pool account. The remaining gold and silver content are credited to the account of Shahuindo SAC when the final assays have been agreed with the refinery.

 

Several of the large international bullion banks have expressed interest in purchasing the Shahuindo production. Production will be tendered to the banks on a monthly basis to ensure market pricing and timely cash collection.

 

The Company anticipates typical shipping and refining costs to be approximately USD 4.50 per ounce of gold refined, based on the historical experience at Tahoe’s La Arena mine.

 

19.2        Mining Alliance

 

Shahuindo has entered into a mining alliance with STRACON GyM, a prominent mining contractor in Peru. The mining alliance is based on a philosophy of ‘best for project’ decision making and run by a board or leadership team made up of three representatives from Shahuindo SAC and three representatives from STRACON Gym. The scope of the alliance includes all civil construction and all mining operations including associated indirect support activities. STRACON GyM provides the mining fleet equipment to Shahuindo SAC.

 

The materials, services, pay roll and equipment used for the in scope activities of the alliance are variously paid by Shahuindo SAC, or STRACON GyM, whichever is determined to be best for the project. STRACON GyM is compensated by reimbursement of their costs and a percent fee on all in-scope costs and is eligible for an incentive bonus at the end of each year of 10% of all fees, conditional on safety, productivity and efficiency targets being met.

 

211


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The Shahuindo mining alliance is very similar to the successful mining alliance currently operating at La Arena. It offers reduced capital costs to Shahuindo, significant flexibility in LOM planning and fleet requirements, significant ‘know how’ in civil construction, mining and fleet management and significant reduction of risk to achieving the annual mine production plan.

 

212


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

20.0                                ENVIRONMENTAL STUDIES, PERMITTING AND SOCIAL OR COMMUNITY IMPACT

 

The environmental and social aspects of the Shahuindo Project are summarized in this chapter. Environmental studies, laws and regulations, permitting, preliminary closure plan, and social impacts are discussed.

 

20.1        Environmental Management Plan

 

Tahoe currently has an established comprehensive Environmental Management Plan that is based on North American practices and regulations. The operating plan that will be implemented at Shahuindo will include Tahoe’s mandate that the Shahuindo mine meet or exceed the Company’s Environmental Management Plan. The Company’s environmental management plan includes regularly and systematic monitoring of:

 

·      Air quality

 

·      Surface Water Quality

 

·      Groundwater Quality

 

·      Stream Sediment Geochemistry

 

·      Blast Vibration

 

·      Noise Levels

 

·      Waste Rock Geochemistry (ARD monitoring)

 

·      Waste Disposal Practices

 

·      Reagent Handling and Storage

 

·      Reclamation and Reforestation Progress

 

20.2        Environmental Studies

 

20.2.1     Environmental Impact Statement

 

The Shahuindo mine is operating under an initial Environmental Impact Statement (EIA, Estudio de Impacto Ambiental) approved in 2013. The EIA was prepared according to Ministry of Energy and Mines (MEM) requirements and complies with Peruvian regulations.

 

Baseline studies conducted for the EIA included all physical, biological and social aspects related to the construction and operation of the Phase 1 project.

 

213


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Baseline studies included:

 

·      Meteorology and Climate

 

·      Air Quality

 

·      Noise and Vibration

 

·      Geomorphology

 

·      Geology

 

·      Soils and Land Use

 

·      Hydrology and Hydrogeology

 

·      Sediment Geochemistry

 

·      Flora and Fauna

 

·      Hydrobiology

 

·      Archaeology

 

·      Landscape

 

·      Traffic

 

·      Environmental Liabilities

 

The Shahuindo EIA determined that the project will have some impacts on the environment as a result of normal construction and operation activities, although with the implementation of the designed mitigation measures, the environment will recover during the years following closure. The Company has committed to insuring suitable water quality for five caserios (villages) downstream of the mine during construction and operations.

 

20.2.2     Geochemical Characterization

 

Shahuindo SAC is performing a Geochemical Characterization Study to better understand rock material geochemistry and the water quality associated with the exposure to material extracted during operations. This study will support the establishment of geochemical criteria for future component design and water management through quantitative modelling.

 

Activities performed include:

 

·      Analysis of the geochemical background information;

 

·      Geochemical sampling plan;

 

·      Development of geochemical assay program;

 

·      Analysis and interpretation of geochemical assays results;

 

214


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·      Definition of Geo Environmental Units (GEU); and

 

·      Pit block model and mine plan assessment for quantification of GEU

 

20.2.2.1     Analysis of Geochemical Background Information

 

Background geochemical data includes results from humidity cell tests conducted by KCA for the EIA (Defilippi, et. al., 2012), geochemical analyses of exploration drill core, and the project geological and geochemical databases. Dominant lithologies and alteration were identified and assessed and their relative sulfur contents evaluated. Dominant lithologies were determined to be siltstone, sandstone, breccia and intrusive rocks. Predominant alteration assemblages noted were phyllic (quartz-sericite), argillic and silicic. Approximately 50% of the material within the pit has a sulfur content less than 0.1%; approximately 15% of the material within the pit has elevated (>1%) sulfur content.

 

20.2.2.2     Geochemical Characterization

 

Based on analysis of the baseline data, further sampling and analytical programs were undertaken to better characterize the rock geochemistry, including a statistical analysis of sulfur content of the material within the pit. Thirty-seven (37) core samples, representing the primary rock and alteration types were collected and analyzed; the results of which are summarized in Table 20.2-1.

 

Table 20.2-1        Sulfur Analysis

 

Lithology

Total Sulfur Content

<0.1%

0.1% - 0.5%

0.5% - 1.0%

1.0% - 5.0%

>5.0%

 

PH

AR

SI

PH

AR

SI

PH

AR

PH

AR

PH

AA

Siltstone

3

1

1

1

1

2

1

2

1

Sandstone

1

1

2

1

1

1

1

1

1

Intrusive

1

1

1

1

1

1

1

Breccia

1

1

1

1

Quaternary

1

1

1

Sample Total

7

4

3

5

2

2

2

1

5

1

4

1

 

Note: PH: phyllic alteration / AR: argillic alteration / SI: silicic alteration

 

 

Completed rock characterization studies include mineralogical studies (microscopy and petrographic studies), Acid-Base Accounting (ABA) static analysis and paste pH analysis, total rock chemistry (WRA), sequential extraction (seven stage) analysis, and humidity cells tests. Mineralogical studies and humidity cell tests and were performed on ten of the 37 core samples. Selection of the samples was based on their further utility in the hydro-geochemical modeling.

 

215


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

ABA results showed acid generation potential for samples with greater than 0.1% sulfur content. Paste pH results corroborated the ABA results and showed increasing acid generation potential with increasing sulfur content. ABA analyses by KCA (Defilippi, et. al., 2012) determined the spent ore is potentially acid-neutralizing. The ABA results, corroborated by the paste pH tests, suggest the neutralization potential of the spent ore outweighed the acid generating potential i.e., net neutralizing).

 

Sequential extraction analyses showed sulfur present as both primary and secondary sulfides. Total iron present in sulfidic material averaged about 3% (pyrite and/or chalcopyrite). Relevant amounts of iron were also found in the oxide stage (magnetite, hematite or goethite) and a minor fraction was found as silicates (likely associated with biotite). Total copper content was reported around 80 ppm, mainly associated with sulfides (chalcopyrite, chalcocite or covellite). Lead content associated with both sulfides and oxides was below 400 ppm.

 

Ten humidity cell tests, each with 20 week duration, were completed. Weekly leachate analyses from humidity cells generally showed lower pH values (<2.5) for samples with higher sulfur content, with pH decreasing through cycle advance for all cells. A high correlation between sulfate and sulfur content was verified. It was observed that in leachate from samples with less sulfur content, sulfate concentration diminished quickly to one order of magnitude with respect to cycle 0.

 

Using the maximum permissible limit (LMP, as determined by statute DS 010-2010 MINAM) as a reference, excess iron and zinc were verified in cells with more than 1% sulfur content. Excess copper, cadmium and arsenic were shown until cycle 10. While there is no LMP for magnesium and aluminum, high concentration of aluminum in high sulfur content (>1%) samples and high magnesium concentrations in some low sulfur content samples (0.1-0.3%) were found.

 

20.2.2.3     Definition of Geo Environmental Units (GEU)

 

Results of the geochemical characterization test work were used to classify ore and waste material into Geo Environmental Units (GEU). These GEUs define material based on its acid generation and metal leaching potential (Arcos, 2013).

 

Formulae developed for the GEU classification form the basis for the modelling of the deleterious elements, including:

 

·      NAG (non-acid generation): <0.1% S

 

·      PAG-Low ML (potential acid generation and low potential of metal leaching): 0.1 < S% < 0.3

 

·      PAG-Mod ML (potential acid generation and medium potential of metal leaching): 0.3 < S% <1

 

·      PAG-High ML (potential acid generation and high potential of metal leaching): > 1% S

 

216


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The main factor that correlated to metal leaching and acid generation of the Shahuindo material was sulfur content.

 

20.2.2.4     Quantification of GEU material

 

The GEU criteria were integrated into the resource block model and mine schedule to determine the distribution of GEUs extracted (ore and waste) over the life of mine; the results of which are presented in Figure 20.2-1.

 

 

Figure 20.2-1       Annual Distribution of Extracted GEU

 

The analysis shows that during the first two years of the mine life (2016-2017), about 75% of waste rock will be NAG; 20% will be PAG-LOW; and the combined PAG-MED & PAG-HIGH will be less than 5%. Modeling suggests during the first years of production, effluent from the waste dump will not exceed

 

217


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

permissible limits for metal content, even at 5 pH. Over the remainder of the mine life (2018-2025), the amount of NAG waste rock extracted will reduce to 40-50% and the PAG-MOD & PAG-HIGH will increase up to 25%. Higher metal concentrations in the waste dump effluent during this time would be expected. The Company is actively investigating appropriate ARD prevention and mitigation/treatment solutions to be implemented prior to Phase 2 operations.

 

20.2.3     Site Monitoring

 

Shahuindo SAC conducts ongoing environmental monitoring programs as committed to in the EIA environmental management plan that includes air quality (particulate matter and GHG), surface water and groundwater quality, sedimentation and sediment geochemistry, noise levels, and sound pressure (vibration). Frequency of reporting to the authority (Ministry of Energy and Mines, OEFA and Ministry of Agriculture) is quarterly and biannual in the case of biological monitoring.

 

20.2.4     Closure Plan

 

The Shahuindo mine has been designed to meet and comply with the environmental standards and legislated closure requirements of Peru. In accordance with Peruvian requirements, company standards, and accepted industry practices, the development, operation, and reclamation plans are designed to:

 

·      Assure long-term physical and geochemical stability;

 

·      Comply with national environmental regulations;

 

·      Recover areas affected by project components;

 

·      Mitigate pre-existing risk conditions;

 

·                  Assure that post-closure use of the altered area and its aesthetics are compatible with the environment;

 

·      Execute a Community Relations Plan during the operation, closure and post-closure stages; and

 

·                  Complete a Progressive Closure and Final Closure of the operation, such that post-closure conditions get to a state of passive care.

 

The closure plan includes the following actions to be taken:

 

·      During operations:

 

·                  Concurrent reclamation activities will be initiated as soon as portions of the project are no longer required (Progressive Closure). Progressive closure activities will be completed whenever possible, especially the covering of waste dumps to minimize infiltration from storm events.

 

Closure activities will take place whenever possible on all facilities that will no longer be used in the final stage of the mine life; this will occur during the rinsing of the leach pads.

 

218


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·      At closure:

 

·                  The open pit will remain as a permanent feature, with berms installed and roads closed to prevent public access. Any potential acid generating material on the pit floor will be covered with non-acid generating waste. It is expected that the pit will fill with water and form a pit lake. Overflow will be treated in a remediation plant and/or by a passive treatment facility.

 

·                  The heap leach will be rinsed to remove trace cyanide to adequate discharge levels. The heap will undergo minor re-contouring, followed by placement of a low-permeability soil cap and revegetated. The low-permeability soil cap will be designed to prevent infiltration from precipitation, but any leach effluent which occurs will be discharged to the pit lake for treatment if necessary.

 

·                  The solution ponds will be closed following procedures established in the approved closure plan. These procedures include de-compaction, re-contouring of containment embankments and infilling of ponds back to the adjacent land level using inert material from borrow areas followed by a natural covering (cap) of low-permeability soil, then re-vegetated.

 

·                  The water storage ponds will be left intact for future use by the local population or reclaimed depending on community desires and/or requirements. Side slopes and other affected areas will be re-vegetated according to the approved closure plan.

 

·                  Exposed leach pad berms will be re-graded with the exposed liner either removed or buried.

 

·                  The processing plant and support facilities will be removed and the land re-vegetated.

 

·                  Concrete pads and foundations will be demolished and foundations removed.

 

·                  Operating surfaces will be reclaimed and re-vegetated.

 

·                  The waste rock facility will be constructed in lifts at a natural angle of repose. With setbacks between lifts, the overall waste dump slopes will be approximately 2.5(H):1.0(V) and will remain at this gradient at closure. A cap consisting of low-permeability soil will be placed over the facility and re-vegetated.

 

·                  Road accesses to hazardous areas (open pits, waste dump and leach pad) will be close, with access restricted to allow essential monitoring and maintenance work to be carried out. Where practical, roads will be turned over to the local communities for future use.

 

·                  A program of physical and geochemical monitoring will take place during the active closure and post-closure periods.

 

219


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

20.2.5     Existing Environmental Conditions

 

There are surface disturbances associated with informal mining activity within the project area, primarily in the Algamarca anticline and La Chilca Baja areas. The Company has an expectation that a certain level of environmental remediation will need to be conducted at these sites.

 

With a perceived exhaustion of easily-mineable mineralization in the Algamarca anticline area, there may be a risk of informal miners moving to exploit other areas within Tahoe’s concessions. An inventory of existing environmental conditions within the concessions was submitted as part of the EIA process. At the effective date of this report, Shahuindo SAC is in negotiation with the informal miners at Algamarca to terminate their mining activities and start other legal and productive activities in the area. Shahuindo SAC has committed to support this transition over the next 6 months.

 

The informal miners at La Chilca were vacated in August 2015. Shahuindo SAC now has full access and possession of the area and is performing an environmental base line study to evaluate the conditions.

 

20.3        Permits

 

At the effective date of this report, the majority of permits required for Phase 1 operations have been approved, with the outstanding permits in the final stages of approval. The following discussion summarizes the required permits for both exploration and operation activities and the approval status of the permits.

 

20.3.1     Exploration

 

The Ministry of Energy and Mines granted several approvals for Sulliden to conduct their exploration activitiesk between 2003 and 2014. These permits were transferred to Shahuindo SAC upon their acquisition by Rio Alto in 2014. The primary permits include:

 

·      Impact Study Semi Detailed (EIAsd) - approved by R.D. 229-2010-MEM/AAM on 15 July 2010;

 

·                  First modification of Impact Study Semi Detailed (EIAsd) approved by R.D. 083-2010-MEM/AAM on 15 March 2011;

 

·                  Second modification of Impact Study Semi Detailed (EIAsd) approved by R.D. 096-2012-MEM/AAM on 27 March 2012; and

 

·                  Technical Supporting report of Impact Study Semi Detailed (ITS-EIAsd) approved by R.D. 146-2014-MEM-DGAAM on 26 March 2014.

 

220


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

20.3.2     Mine Construction and Operations

 

20.3.2.1     Environmental Impact Assessment (EIA)

 

Shahuindo SAC conducts construction activities under an (EIA) approved by R.D. 339-2013-MEM/AAM on 10 September 2013; the First Technical Sustentatory Report of Environmental Impact Assessment (ITS-1-EIA) approved by R.D. 613-2014-MEM-DGAAM on 18 December 2014 and the Second Technical Sustentatory Report of Environmental Impact Assessment (ITS-2-EIA) approved by R.D. 265-2015-MEM-DGAAM on 7 July 2015, The EIA documented the baseline environmental and socioeconomic environment of the Shahuindo project and surrounding area and provided an analysis of the project’s potential impacts to air quality, sound levels, surface and groundwater, soils, flora and fauna, archaeological resources and socioeconomic measures, and an Environmental Management Plan which included prevention and mitigation measures.

 

The approval of the EIA allowed the company to proceed with the permit applications required for construction and operation of the Shahuindo mine, in accordance with Peruvian regulations. Examples of these permits include water use license, archaeological permits, beneficiation concession (process plant operations), and implementation of the mine plan (Mining Permit), among others.

 

The currently approved EIA is applicable for construction and Phase 1 operations. Shahuindo SAC has submitted an EIA modification (MEIA) to cover the expanded Phase 2 project. The MEIA is under review by the Peruvian authorities with receipt of approval expected in 2016.

 

20.3.2.2     Certificate for the Inexistence of Archaeological Remains (CIRA).

 

During 2003 and 2007, Sulliden performed archaeological surveys in the project area in support of environmental permits necessary for them to conduct exploration activities. The surveys indicated the presence of sites considered to have potential archaeological significance. Sulliden undertook an Archaeological Evaluation (PEA is the Spanish acronym) to determine whether a Certificate for the Inexistence of Archaeological Remains could be granted. This certificate is a pre-requisite for the Ministry of Energy and Mining and is necessary for the start-up of operations.

 

Shahuindo SAC continued archaeological investigations within the project and has received the following permits:

 

·                  Certificate for the Inexistence of Archaeological Remains approved by CIRA No 173-2013 on 11 July 2013 and issued by the Ministry of Culture.

 

·                  Certificate for the Inexistence of Archaeological Remains corresponding to four potential areas of interest indicated in CIRA No 173-2013 approved by CIRA No 232-2015 on 15 September 2015 and issued by the Ministry of Culture.

 

221


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                 Archaeological Monitoring Plan (PMA) was approved by R.D. No 125-2015-DDCCAJ/MC on 29 May 2015 and issued by the Ministry of Culture.

 

20.3.2.3     Mine Closure Plan

 

The Mine Closure Plan was approved by R.D No 132-2015-MEM-DGAAM on 10 March 2015 by the Ministry of Energy and Mines. This permit specifies that all components of the project will be closed in three gradual stages (progressive, final and post closure). It also includes the budget for the closure and the amount of guarantees to be paid for the closure bond.

 

20.3.2.4     Beneficiation Concession

 

On 25 November 2015, Shahuindo SAC received the Beneficiation Concession which authorized the operation of the processing plant and major processing components for Phase 1 operations. The license was issued by the Ministry of Energy and Mines by means of Resolution No. 2468-2015-MEM/DG -Water Usage Permits (process water).

 

20.3.2.5     Water Usage Permits

 

Shahuindo SAC was granted the Water Use license by Resolution No.1157.2015-ANA-AAA.M on 12 November 2015, issued by the National Water Authority.

 

20.3.2.6     Mining Plan

 

On 27 November 2015, Shahuindo SAC received the license authorizing the start of activities for the development and commissioning of the Phase 1 project. Site inspection of the constructed components is scheduled for January 2015 with approvals for full operations expect to follow shortly. Commissioning activities are currently being conducted under a temporary commissioning permit.

 

20.3.2.7     Operation Permits

 

At the effective date of this report, Shahuindo SAC has obtained operations permits for fuel storage, reagent storage and use, explosive magazines, explosives handling and use, and power generation.

 

Resolution No. 3111190008604 approved on 11 November 2015 and issued by the Superintendencia Nacional de Administracion Tributaria (SUNAT) approved reagent storage and use. Resolution No. 02446-2015-SUCAMEC/GEPP approved on 10 November 2015 was issued by the Superintendencia Nacional de Control de Servicios de Seguridad, Armas, Municiones y Explosivos de Uso Civil (SUCAMEC) approving explosives handling and use.

 

222


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

20.3.2.8     Permanent Power Concession

 

This permit is required for the connection to the transnational power grid and substation operations. Approval was received from the Comité de Operación Económica del Sistema Interconectado Nacional (COES) after acceptance of required environmental and social studies and construction plans.

 

20.3.2.9     Easements and Right-of-Way

 

Easements to accommodate subsidiary power lines to the project site, access roads, and roads internal to the project.

 

20.3.2.10  District and Provincial Municipality Licenses

 

District and/or Provincial licenses may be required for exploration, development, construction, and operating activities.

 

20.4           Social Impact

 

20.4.1        Location of the Study Area

 

Shahuindo is located in the department of Cajamarca, in the province of Cajabamba and the district of Cachachi, (Figure 20.4-1). The project area is characterized by varied topography with several areas heavily dissected by rivers and streams. Altitudes range from 2,500m to 3,350m above sea level.

 

20.4.2        Social Baseline Study

 

According to the ESIA Modification, the Area of Influence has been further divided into Direct and Indirect Areas of Influence . The Direct Area of Influence (Figure 20.4-1) is defined as those people and or places which may directly experience either positive or negative social effects from the Shahuindo mine to varying degrees. Fourteen villages have been identified within the Direct Area of Influence and include Algamarca, La Fila, Liclipampa Alto, Pauquilla, Rosahuayta, San Jose, Araqueda, Quillishpampa, Moyan Alto, Moyan Bajo, Pampachancas, Shahuindo, Liclipampa Bajo and Siguis. Within the Direct Area of Influence, the four communities of San Jose, Shahuindo, Moyan Alto and Moyan Bajo will experience some levels of resettlement. A detailed Resettlement Action Plan, structured in accordance with International Finance Corporation (IFC) Performance Standard 5 for Land Acquisition and Involuntary Resettlement has been prepared to mitigate the effects from resettlement and land acquisition.

 

The Indirect Area of Influence is composed of people and or places that may experience positive social impacts and reduced negative social impacts compared to those located in the Direct Area of Influence. Communities within the Indirect Area of Influence include those living in the districts of Cachachi and Condebamba.

 

223


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 20.4-1       Location of Direct Influence Area

 

224


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

20.4.3     Public Consultation and Engagement Plan

 

Shahuindo SAC is committed to proactive and transparent engagement with the communities, public institutions and government agencies located within the project’s area of influence. The company’s public consultation and engagement plan is built around the following commitments:

 

·      Compliance with Peruvian legislation regarding community consultation and engagement;

 

·                  Implementation of a consultation and communication plan in an open, honest and transparent manner with neighboring populations and interest groups to create an atmosphere of mutual trust;

 

·                  Actions based on comprehensive understanding of the social, economic and cultural context in which the mine is developed;

 

·                  Contributions to strengthening local social organizations through participation in the development of the mine and in the activities that may affect them; and

 

·                  Engagement with local communities throughout the baseline study stage of the ESIA through a participatory monitoring program and the extension of this program throughout the construction, operation and closure stages.

 

To ensure that the Company communicates effectively, Shahuindo SAC has established the following methods of communication and access to information:

 

·      Two public information offices, one at the mine site and one in the town of Cajabamba;

 

·      The development and distribution of project information;

 

·      Use of local radio to provide information about progress of the mine;

 

·      Guided tours of the project site; and

 

·      Informative workshops.

 

20.4.4     Community Development Program

 

The Company recognizes its role and responsibility to contribute to local sustainable development by utilizing its ability to mobilize technical and financial resources to support the implementation of initiatives for local development during the construction and operational stages of the mine.

 

The objectives of the community development program include:

 

·                  Strengthening the local productive capacities to generate opportunities for alternative employment for the population in the Direct Area of Influence;

 

·      Strengthen technical capacities of the stakeholders in the areas of influence;

 

·                  Providing capacity building initiatives to local organizations and leaders to better manage local development initiatives in a transparent and participatory manner; and

 

225


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                 Creating and consolidating channels of coordination and dialogue between the local communities and the mine.

 

The Company will focus its sustainable development initiatives in the following areas:

 

·                  Local Employment and Purchase of Local Goods and Services. Training for local people within the Direct Area of Influence in multifaceted disciplines and the purchase of goods and services from local providers.

 

·                  Economic Production. Improvement to local productive capacities and infrastructure (agriculture, livestock and fish farming) and the sustainable management of forest resources.

 

·                  Small Business Development and Entrepreneurship. Promotion of entrepreneurship and small business programs.

 

·                  Local Social Development. Work with national, regional and local levels of government to implement projects aimed at training to improve general employability, education and health.

 

·                  Strengthening Local Institutions. Strengthen the capacity of local stakeholders, such as local governments and grassroots organizations, among others.

 

226


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

21.0        CAPITAL AND OPERATING COSTS

 

All capital and operating costs used in this study are in 2015 US dollars. Where costs will be incurred in Peruvian Nuevo Soles, an average conversion rate of 3.10 Soles per US dollar was used. Sales tax (Impuesto General A Las Ventas, IGV) is not included in the capital or operating cost estimates.

 

21.1        Capital Cost Estimate

 

21.1.1     List of Areas

 

Project capital and sustaining capital for the Shahuindo project are divided into three primary areas:

 

·      Mine — includes leach pad and waste dump construction;

 

·      Plant — includes crushing, conveying and agglomeration equipment and infrastructure; and

 

·      Other — includes site infrastructure, roads, land acquisition and certain social projects.

 

21.1.2     Basis of Estimate

 

Capital costs for the Shahuindo project have been derived from construction contracts currently in place, contractor and vendor quotes, costs incurred for similar projects at the La Arena mine and engineering first principles. Mine construction capital costs (leach pads and waste dumps) are based on contractual rates with the on-site mining contractor. All mining equipment is assumed owned by the contractor and rented based on annual contractual rates. These costs have been included in the operating expenses. Plant equipment for all areas was estimated, quoted, or purchased in 2015 dollars. No growth allowance has been included.

 

The cost associated with reclamation and closure is included in the cash flow model beginning in 2021 through 2031. Mine operating costs include the cost of constructing waste piles and heap leach piles to slopes that facilitate regrading at mine closure.

 

21.1.3     Capital Estimate

 

Total capital for the project is estimated to be $320.3 million dollars beginning on 01 January 2016; including construction capital of $179.6 million and $140.7 million in sustaining capital. Anticipated life of mine capital expenditures by year are shown in Table 21.1-2.

 

227


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 21.1-1        Estimated Capital Expenditure Summary by Year (US$M)

 

 

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

Project Capital

 

 

 

 

 

 

 

 

 

 

Mining

27.45

Process Plant

18.94

86.63

Other

28.54

11.81

6.26

Sustaining Capital

 

 

 

 

 

 

 

 

 

 

Mining

28.14

21.89

17.05

17.7

13.76

10.05

14.67

4.33

2.71

Process Plant & Other

0.34

4.3

2.79

1.24

0.38

0.37

0.17

0.27

0.26

0.25

Total Capital

75.27

130.88

30.94

18.29

18.08

14.13

10.23

14.94

4.59

2.97

 

Major component capital expenditures are summarized in Table 21.1-2.

 

Table 21.1-2        Major Component Capital Expenditures — Life of Mine

 

Component

US$M

Leach Pad Construction (incl. raincoats)

118.56

Waste Dump Construction

32.24

Haul Roads

0.66

Process Plant (incl. stockpile construction)

28.30

Crushing / Agglomeration / Conveyance

84.05

Water Supply

0.18

Camps, Offices, Communication Systems

7.86

Workshops

6.26

Substation

11.46

Access Roads / Bridge Upgrade

11.41

Engineering & Environmental Studies

3.46

Land Purchases, Social Projects, Other Capital

15.88

Total Capital Expenditures

320.31

 

21.2        Operating Cost Estimate

 

Operating costs were determined by quotes received from the mining contractor, STRACON GyM, actual operating costs incurred at the La Arena mine, engineering first principles and management experience at similar operations. Labor costs are included using a project specific staffing plan. The average cash operating cost over the life of the mine is estimated to be $9.28 per ore tonne.

 

228


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The life of mine operating costs summarized in Table 21.2-1 are the projected costs for ore defined as oxide ore for leaching.

 

Table 21.2-1        Operating Cost Summary

 

Operating Cost

Value

Mining Cost ($/tonne mined)

$

1.91

Mining Cost ($/ ore tonne mined)

$

4.50

Process Plant Operating Cost ($/tonne processed)4

$

2.55

General Administration ($/tonne processed)

$

2.23

 

Operating costs were determined by year, with power consumption and operating costs increasing in 2018 as a result of transitioning from run of mine heap leaching to utilizing a crush, convey and agglomeration system.

 

The operating costs presented are based upon the assumption that all major mining equipment is leased throughout the mine life. Maintenance of leased equipment has been included.

 

Operating costs are presented without any added contingency or growth allowances.

 


4 Includes $1.42 /tonne ore for crushing and agglomeration beginning in 2018

 

229


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

22.0        ECONOMIC ANALYSIS

 

The financial evaluation presents the determination of the Net Present Value (NPV), and payback period (time in years to recapture the capital investment), and the Internal Rate of Return (IRR) for the project. Annual cash flow projections were estimated over the life of the mine based on the estimates of capital expenditures, production costs and sales revenue. The sales revenue is based on the production of a gold/silver doré. The estimates of capital expenditures and site production costs have been developed specifically for this project and have been presented in earlier sections of this report.

 

22.1        Mine Production Statistics

 

Mine production is reported as ore and overburden from the mining operation. The annual production figures were obtained from the mine plan as reported in Section 16.8 of this report.

 

The life of mine ore quantities and grades are presented in Table 22.1-1.

 

Table 22.1-1        Life of Mine Production

 

 

 

 

 

 

Contained

 

Tonnes

Gold Grade

Silver Grade

Contained Gold

Silver Ounces

 

(000s)

(g/t)

(g/t)

Ounces (000s)

(000s)

Oxide Ore

110,890

0.53

6.86

1,898

24,465

Waste

149,855

 

22.2        Process Plant Production Statistics

 

The oxide ore will be processed using heap leaching technology to produce gold/silver doré. Metallurgical recoveries for gold and silver are:

 

Gold       79% LOM Recovery (73% 2016-2017 / 80% 2018+)

 

Silver      12% LOM Recovery (7% 2016-2017 / 12% 2018+)

 

The estimated life of mine metal production (i.e., metal in doré) is estimated to be 1.504 million ounces of gold and 2.834 million ounces of silver.

 

230


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

22.3        Capital Expenditures

 

22.3.1     Project Capital

 

The financial indicators have been determined with 100% equity financing of the initial capital. Any acquisition costs or expenditures prior to 01 January 2016 have been treated as ‘sunk’ costs and have not been included in this analysis

 

The total project capital carried in the financial model for new construction is expended over a three year period. The cash flow will be expended in the year of first production and certain costs carried over into future years for major projects including crushing and agglomeration, substation and a maintenance shop. The project capital is presented in Table 22.3-1.

 

Table 22.3-1        Project Capital

 

Project Capital

US$M

Mining

27.5

Process Plant

105.6

Other

46.6

Total

179.70

 

 

22.3.2     Sustaining Capital

 

Capital cost expenditures during the production period are included in the financial analysis under Section 21.1.3. The total life of mine sustaining capital is estimated to be $140.7 million (Table 22.3-2). This capital will be expended over a ten year period.

 

Table 22.3-2        Sustaining Capital

 

Sustaining Capital

US$M

Mining

130.3

Process Plant & Other

10.4

Total

140.7

 

22.3.3     Working Capital

 

A ten day delay of receipt of revenue from sales is used for accounts receivable. A delay of payment for accounts payable of 30 days is also incorporated into the financial model. All of the working capital is recaptured at the end of the mine life and the final value of these accounts is $0.

 

231


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

22.4        Salvage Value

 

No allowance has been made for salvage value of the capital equipment for this analysis.

 

22.5        Revenue

 

Annual revenue is determined by applying estimated gold and silver prices to the annual payable metal estimated for each operating year. Escalating metal prices, as shown in Table 22.5-1, have been applied to the life of mine production without hedging. The revenue is the gross value of payable metals sold before refining and transportation charges.

 

Table 22.5-1        Gold and Silver Prices

 

Metal

 

2016

 

2017

 

2018

 

2019 - 2025

 

LOM
Average

 

Gold $/troy ounce

 

$

1,100

 

$

1,200

 

$

1,300

 

$

1,400

 

$

1,340

 

Silver $/troy ounce

 

$

14.75

 

$

17.25

 

$

20.00

 

$

23.50

 

$

21.65

 

 

22.6        Shipping and Refining

 

The gold and silver doré will be shipped to a precious metal refinery with refining charges negotiable at the time of agreement. Costs are estimated at $4.50 per ounce of gold, similar to the refining contract in place at the La Arena mine. There are no refining charges for silver per se, as silver is used as a credit against doré treatment charges. Refining charges over the life of mine are estimated at $0.06 per tonne of ore. Refining terms used in the financial analysis are shown in Table 22.6-1.

 

Table 22.6-1        Gold and Silver Refining Terms

 

Doré Refining Terms

 

Payable Gold

 

99.9%

 

Payable Silver

 

99.5%

 

 

22.7        Operating Costs

 

The average Cash Operating Cost over the life of the mine is estimated to be $9.28 per ore tonne. Cash Operating Cost includes mine operations, process plant operations and general administrative costs. Table 22.7-1 shows the estimated operating cost by area per tonne of ore placed on the leach pad.

 

232


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 22.7-1        Life of Mine Operating Cost

 

Cash Operating Cost

 

$/ore tonne

 

Mine

 

$

4.50

 

Process Plant

 

$

2.55

 

General Administration

 

$

2.23

 

Total Operating Cost

 

$

9.28

 

 

22.8        Total Cash Cost

 

The average Total Cash Cost over the life of the mine is estimated to be $9.83 per ore tonne. Total Cash Cost consists of Operating Cost plus worker profit share and certain production taxes which are calculated at $0.55 per ore tonne.

 

22.8.1     Worker Profit Share and other production taxes

 

Mining companies in Peru are obliged to pay workers a participation of 8% on the net profits of the company (Shahunido SAC) up to a maximum of 18 times base salary. The amount is permitted as a tax deduction in calculating corporate income tax. The Worker Profit Share and other production taxes are estimated at $60.6 million over the life of mine.

 

22.8.2     Reclamation and Closure

 

Non-cash accretion expense in the amount of $24.0 million over the life of mine has been included in the financial model and will impact net earnings. A cash flow estimate of $37.4 million for reclamation and closure was included in the working capital adjustment.

 

22.8.3     Depreciation

 

Depreciation is calculated using the units of production method and may not correlate to the depreciation taken for tax purposes. The project capital and sustaining capital used a unit of production method based on gold ounces produced.

 

22.8.4     Taxation

 

Income tax is calculated at rates substantially enacted and applied to the net taxable income, which is computed by subtracting the allowable deductions and carry forward losses from revenues.

 

The financial model includes corporate income taxes at a 28% (2015-2016), 27% (2017-2018) and 26% (2019-end of mine life) rate on taxable income.

 

233


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

The Company is also subject to a Special Mining Tax (SMT) and Modified Mining Royalty (MMR), as discussed in detail in Section 4.6. The SMT is applied on operating income based on a sliding scale with progressive marginal rates ranging from 2% to 8.4%. The MMR is applied based on a sliding scale ranging from 1% to 12% against operating income but may not be lower than 1% of the company’s sales revenues. The SMT and MMR have been included in Income tax for the purposes of this study.

 

Cash income taxes paid are estimated to be $196.2 million over the life of mine.

 

Deferred income taxes are estimated based on the difference between depreciation taken for accounting and tax purposes. The substantially enacted tax rate is then applied to the difference to create the deferred tax expense (benefit). The deferred tax benefit is estimated at $12.7 million over the mine life.

 

22.9        Project Financing

 

The project was evaluated on an unleveraged and un-inflated basis.

 

22.10      Net Income After Tax

 

Net Income after Tax amounts to $338.6 million.

 

22.11      NPV and IRR

 

The economic analysis indicates that the project has an Internal Rate of Return (IRR) of 40.6% with a payback period of 4.1 years after taxes. See Table 22.11-1.

 

Table 22.11-1      Economic Indicators (US$M)

 

Economic Indicators

 

Before Taxes

 

After Taxes

 

NPV @ 5%

 

$

462,203

 

$318,863

 

IRR

 

 

40.6%

 

Payback

 

 

4.1 years

 

 

22.12      Sensitivities

 

Table 22.12-1 through Table 22.12-4 compare the base case project after tax financial indicators with the financial indicators when different variables are applied. Variables included in the sensitivity analysis include changes to metal prices, operating cost, capital expenditures, and metallurgical recovery. Changes in metal prices have the most impact on the project economics, followed by changes to operating cost.

 

234


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 22.12-1      NPV Sensitivity Analysis on Metal Prices

 

Change in Metal Prices

 

NPV @ 0%

 

NPV @ 5%

 

NPV @ 10%

 

IRR%

 

Payback

 

+20%

 

$

723,045

 

$

508,619

 

$

362,690

 

67.7

%

3.3

 

+10%

 

$

597,309

 

$

413,960

 

$

289,289

 

53.1

%

3.6

 

Base Case

 

$

471,200

 

$

318,863

 

$

215,413

 

40.6

%

4.1

 

-10%

 

$

342,701

 

$

221,333

 

$

139,143

 

29.0

%

4.8

 

-20%

 

$

202,022

 

$

113,741

 

$

54,457

 

17.1

%

6.1

 

 

Table 22.12-2      NPV Sensitivity Analysis on Operating Cost

 

Change in Operating
Cost

 

NPV @ 0%

 

NPV @ 5%

 

NPV @ 10%

 

IRR%

 

Payback

 

+20%

 

$

348,725

 

$

225,158

 

$

141,508

 

29.0

%

4.9

 

+10%

 

$

411,022

 

$

273,026

 

$

179,417

 

34.8

%

4.4

 

Base Case

 

$

471,200

 

$

318,863

 

$

215,413

 

40.6

%

4.1

 

-10%

 

$

530,361

 

$

363,820

 

$

250,632

 

46.7

%

3.8

 

-20%

 

$

588,728

 

$

407,955

 

$

285,031

 

53.1

%

3.6

 

 

Table 22.12-3      NPV Sensitivity Analysis on Total Capital

 

Change in Capital

 

NPV @ 0%

 

NPV @ 5%

 

NPV @ 10%

 

IRR%

 

Payback

 

+20%

 

$

409,200

 

$

263,661

 

$

165,625

 

29.1

%

4.8

 

+10%

 

$

440,142

 

$

291,213

 

$

190,477

 

34.2

%

4.5

 

Base Case

 

$

471,200

 

$

318,863

 

$

215,413

 

40.6

%

4.1

 

-10%

 

$

502,354

 

$

346,596

 

$

240,419

 

49.0

%

3.7

 

-20%

 

$

533,592

 

$

374,233

 

$

265,224

 

60.2

%

3.4

 

 

Table 22.12-4      Sensitivity Analysis on Metal Recovery

 

Change in Recovery

 

NPV @ 0%

 

NPV @ 5%

 

NPV @ 10%

 

IRR%

 

Payback

 

+2%

 

$

508,599

 

$

347,156

 

$

237,466

 

44.2

%

3.9

 

+1%

 

$

489,905

 

$

333,014

 

$

226,443

 

42.4

%

4.0

 

Base Case

 

$

471,200

 

$

318,863

 

$

215,413

 

40.6

%

4.1

 

-1%

 

$

452,456

 

$

304,682

 

$

204,358

 

38.9

%

4.2

 

-2%

 

$

433,662

 

$

290,459

 

$

193,265

 

37.2

%

4.3

 

 

235


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

22.13      Shahuindo Financial Model

 

The life of mine base case assumptions for the Shahuindo financial model are summarized in Table 22.13-1. The detailed life of mine financial model is included in Table 22.13-2.

 

Table 22.13-1      LOM Base Case Summary - Assumptions

 

Production Statistics

Base Case

Mine

Ore (ktonnes)

110,890

Gold Grade (g/t)

0.53

Silver Grade (g/t)

6.86

Contained Gold (kozs)

1,900

Contained Silver (kozs)

24,470

Waste (ktonnes)

149,855

Total Tonnes Mined (ktonnes)

260,745

Processing

Ore Placed on Pad (ktonnes)

110,890

Gold Production (kozs recovered)

1,504

Silver Production (kozs recovered)

2,834

Gold Recovery

79%

Silver Recovery

12%

Revenues, Capital Cost & Operating Cost

Revenues ($000)

$

2,110,507

Project Capital ($000)

$

179,629

Sustaining Capital ($000)

$

140,676

Mining Cost ($/tonne mined)

$

1.91

Mining Cost ($/ore tonne mined)

$

4.50

Process Plant Operating Cost ($/tonne processed)

$

2.55

General Administration ($/tonne processed)

$

2.23

Treatment & Transportation Charges ($/tonne processed)

$

0.06

Total Operating Cost ($/tonne processed)

$

9.28

Economic Indicators before Taxes

NPV @ 0% ($000)

$

667,385

NPV @ 5% ($000)

$

462,203

NPV @ 10% ($000)

$

322,836

Economic Indicators after Taxes

NPV @ 0% ($000)

$

471,200

NPV @ 5% ($000)

$

318,863

NPV @ 10% ($000)

$

215,413

IRR

40.6%

Payback (yrs)

4.1

 

236


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 22.13-2      Shahuindo Life of Mine Financial Model

 

Base Case

 

Total

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

2030

 

2031

 

2032

Mining Operations

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Ore

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Beginning Inventory (kt)

 

110,890

 

110,890

 

105,133

 

99,531

 

89,242

 

75,830

 

62,791

 

50,439

 

34,374

 

19,969

 

7,236

 

 

 

 

 

 

 

Mined (kt)

 

110,890

 

5,756

 

5,602

 

10,289

 

13,412

 

13,039

 

12,352

 

16,066

 

14,405

 

12,732

 

7,236

 

 

 

 

 

 

 

Ending Inventory (kt)

 

 

105,133

 

99,531

 

89,242

 

75,830

 

62,791

 

50,439

 

34,374

 

19,969

 

7,236

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Grade (g/t)

 

0.53

 

0.68

 

0.54

 

0.64

 

0.48

 

0.48

 

0.51

 

0.50

 

0.59

 

0.52

 

0.49

 

 

 

 

 

 

 

Silver Grade (g/t)

 

6.86

 

5.95

 

5.73

 

7.24

 

6.45

 

7.05

 

6.47

 

7.79

 

7.16

 

6.36

 

7.30

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contained Gold (kozs)

 

1,900

 

126

 

97

 

212

 

206

 

200

 

201

 

258

 

273

 

215

 

113

 

 

 

 

 

 

 

Contained Silver (kozs)

 

24,470

 

1,102

 

1,032

 

2,395

 

2,779

 

2,954

 

2,568

 

4,023

 

3,314

 

2,606

 

1,698

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Waste

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Beginning Inventory(kt)

 

149,855

 

149,855

 

144,901

 

140,789

 

118,954

 

100,059

 

80,813

 

60,921

 

44,525

 

28,603

 

11,106

 

 

 

 

 

 

 

Mined (kt)

 

149,855

 

4,954

 

4,113

 

21,835

 

18,895

 

19,246

 

19,893

 

16,395

 

15,922

 

17,497

 

11,106

 

 

 

 

 

 

 

Ending Inventory (kt)

 

 

144,901

 

140,789

 

118,954

 

100,059

 

80,813

 

60,921

 

44,525

 

28,603

 

11,106

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Material Mined (kt)

 

260,745

 

10,710

 

9,715

 

32,124

 

32,306

 

32,285

 

32,245

 

32,461

 

30,327

 

30,230

 

18,342

 

 

 

 

 

 

 

Waste to Ore Ratio

 

1.35

 

0.86

 

0.73

 

2.12

 

1.41

 

1.48

 

1.61

 

1.02

 

1.11

 

1.37

 

1.53

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Leach Pad Operations

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Beginning Ore Inventory (kt)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Ore Placed on Pad

 

110,890

 

4,446

 

6,022

 

11,179

 

13,000

 

13,039

 

12,352

 

13,140

 

13,140

 

13,140

 

11,431

 

 

 

 

 

 

 

Mined Ore - Processed (kt)

 

110,890

 

4,446

 

6,022

 

11,179

 

13,000

 

13,039

 

12,352

 

13,140

 

13,140

 

13,140

 

11,431

 

 

 

 

 

 

 

Ending Ore Inventory

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Grade (g/t)

 

0.53

 

0.79

 

0.52

 

0.60

 

0.48

 

0.48

 

0.51

 

0.55

 

0.62

 

0.52

 

0.41

 

 

 

 

 

 

 

Silver Grade (g/t)

 

6.86

 

6.59

 

5.63

 

6.84

 

6.56

 

7.05

 

6.47

 

8.52

 

7.44

 

6.30

 

6.28

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contained Gold (kozs)

 

1,898

 

113

 

101

 

216

 

202

 

200

 

201

 

233

 

262

 

218

 

151

 

 

 

 

 

 

 

Contained Silver (kozs)

 

24,465

 

942

 

1,090

 

2,458

 

2,741

 

2,954

 

2,568

 

3,599

 

3,143

 

2,663

 

2,308

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Dore

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Recovery Gold (%)

 

79%

 

73.00%

 

73.00%

 

80.00%

 

80.00%

 

80.00%

 

80.00%

 

80.00%

 

80.00%

 

80.00%

 

80.00%

 

 

 

 

 

 

 

Recovery Silver (%)

 

12%

 

7.00%

 

7.00%

 

12.00%

 

12.00%

 

12.00%

 

12.00%

 

12.00%

 

12.00%

 

12.00%

 

12.00%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Recovered Gold (kozs)

 

1,504

 

83

 

74

 

173

 

162

 

160

 

161

 

187

 

210

 

175

 

121

 

 

 

 

 

 

 

Recovered Silver (kozs)

 

2,834

 

66

 

76

 

295

 

329

 

354

 

308

 

432

 

377

 

320

 

277

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Payable Metals

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Dore

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Payable Gold (kozs)

 

1,502

 

83

 

74

 

173

 

162

 

160

 

161

 

186

 

209

 

174

 

121

 

 

 

 

 

 

 

Payable Silver (kozs)

 

2,823

 

68

 

76

 

293

 

327

 

353

 

307

 

430

 

375

 

318

 

276

 

 

 

 

 

 

 

 

237


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

Table 22.13-2 (continued)        Shahuindo Life of Mine Financial Model

 

Base Case

 

Total

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

2030

 

2031

 

2032

 

Income Statement ($000)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold ($/oz)

 

$

1,362.17

 

$

1,100.00

 

$

1,200.00

 

$

1,300.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

$

1,400.00

 

Silver ($/oz)

 

$

22.76

 

$

14.75

 

$

17.25

 

$

20.00

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

$

23.50

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Revenues

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Dore - Au

 

$

2,046,275

 

$

90,758

 

$

88,794

 

$

224,564

 

$

226,231

 

$

223,841

 

$

224,945

 

$

260,846

 

$

293,070

 

$

244,246

 

$

168,978

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Dore - Ag

 

$

64,232

 

$

1,005

 

$

1,310

 

$

5,869

 

$

7,690

 

$

8,288

 

$

7,205

 

$

10,098

 

$

8,819

 

$

7,473

 

$

6,475

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Total Revenues

 

$

2,110,507

 

$

91,763

 

$

90,104

 

$

230,433

 

$

233,921

 

$

232,129

 

$

232,150

 

$

270,944

 

$

301,889

 

$

251,720

 

$

175,454

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Operating Cost

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mining

 

$

498,640

 

$

28,239

 

$

21,127

 

$

61,726

 

$

70,227

 

$

59,381

 

$

54,372

 

$

64,858

 

$

60,469

 

$

52,960

 

$

25,282

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Process Plant

 

$

282,711

 

$

7,820

 

$

9,637

 

$

29,638

 

$

34,408

 

$

34,509

 

$

32,714

 

$

34,774

 

$

34,558

 

$

34,558

 

$

30,098

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

General Administration

 

$

247,358

 

$

23,399

 

$

18,949

 

$

24,939

 

$

24,550

 

$

25,306

 

$

26,778

 

$

28,524

 

$

27,754

 

$

27,902

 

$

19,257

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Treatment & Refining Charges

 

$

6,760

 

$

371

 

$

333

 

$

777

 

$

727

 

$

719

 

$

723

 

$

838

 

$

942

 

$

785

 

$

543

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Total Operating Cost

 

$

1,035,469

 

59,828

 

50,046

 

117,080

 

129,912

 

119,915

 

114,587

 

128,994

 

123,722

 

116,204

 

75,180

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Production Taxes & Profit Share

 

$

60,842

 

$

3,056

 

$

1,535

 

$

6,828

 

$

5,783

 

$

6,058

 

$

6,406

 

$

9,087

 

$

11,277

 

$

7,416

 

$

3,397

 

$

0

 

$

 

$

 

$

 

$

 

$

 

$

 

Reclamation Accretion (non-cash)

 

$

24,038

 

$

2,577

 

$

1,386

 

$

1,455

 

$

1,528

 

$

1,604

 

$

1,684

 

$

1,769

 

$

1,848

 

$

1,940

 

$

2,028

 

$

2,050

 

$

1,251

 

$

1,145

 

$

893

 

$

758

 

$

122

 

$

 

Total Production Cost

 

$

1,120,349

 

$

65,461

 

$

52,967

 

$

125,363

 

$

137,222

 

$

127,578

 

$

122,677

 

$

139,850

 

$

136,848

 

$

125,560

 

$

80,605

 

$

2,050

 

$

1,251

 

$

1,145

 

$

893

 

$

758

 

$

122

 

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Operating Income

 

$

990,158

 

$

26,302

 

$

37,137

 

$

105,070

 

$

96,699

 

$

104,551

 

$

109,473

 

$

131,094

 

$

165,042

 

$

126,159

 

$

94,849

 

$

(2,050

)

$

(1,251

)

$

(1,145

)

$

(893

)

$

(758

)

$

(122

)

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Project Capital Depreciation

 

$

260,431

 

$

5,571

 

$

9,161

 

$

30,668

 

$

29,713

 

$

29,426

 

$

29,559

 

$

33,875

 

$

37,749

 

$

31,879

 

$

22,830

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Sustaining Capital Depreciation

 

$

140,676

 

$

1,355

 

$

2,169

 

$

7,383

 

$

8,853

 

$

10,376

 

$

14,114

 

$

17,166

 

$

19,287

 

$

16,074

 

$

11,120

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Total Depreciation

 

$

401,107

 

$

6,926

 

$

11,330

 

$

38,051

 

$

38,566

 

$

39,802

 

$

43,672

 

$

51,041

 

$

57,036

 

$

47,953

 

$

33,950

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Net Income After Depreciation

 

$

589,050

 

19,375

 

25,807

 

67,019

 

$

58,133

 

$

64,749

 

$

65,801

 

$

80,053

 

$

108,006

 

$

78,206

 

$

60,898

 

$

(2,050

)

$

(1,251

)

$

(1,145

)

$

(893

)

$

(758

)

$

(122

)

$

 

Tax Loss Carry Forward

 

$

(66,985

)

(19,375

)

(15,870

)

(15,870

)

(15,870

)

 

 

 

 

 

 

 

 

 

 

 

 

 

Taxable Income

 

$

522,065

 

$

 

$

9,937

 

$

51,149

 

$

42,263

 

$

64,749

 

$

65,801

 

$

80,053

 

$

108,006

 

$

78,206

 

$

60,898

 

$

(2,050

)

$

(1,251

)

$

(1,145

)

$

(893

)

$

(758

)

$

(122

)

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Current Income Taxes

 

$

196,186

 

2,198

 

2,492

 

20,106

 

15,499

 

21,072

 

22,450

 

32,926

 

41,732

 

26,278

 

11,432

 

 

 

 

 

 

 

 

Deferred Income Taxes

 

$

(12,740

)

720

 

2,479

 

(3,598

)

(1,281

)

(926

)

(1,808

)

(3,506

)

(4,918

)

(2,099

)

2,197

 

 

 

 

 

 

 

 

Total Taxes

 

$

183,445

 

$

2,918

 

$

4,971

 

$

16,508

 

$

14,218

 

$

20,146

 

$

20,642

 

$

29,420

 

$

36,814

 

$

24,179

 

$

13,628

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Net Income After Taxes

 

$

338,620

 

$

(2,918

)

$

4,966

 

$

34,641

 

$

28,045

 

$

44,603

 

$

45,158

 

$

50,633

 

$

71,192

 

$

54,027

 

$

47,270

 

$

(2,050

)

$

(1,251

)

$

(1,145

)

$

(893

)

$

(758

)

$

(122

)

$

 

 

238


 

Shahuindo Mine, Peru

NI 43-101 Technical Report

 

Table 22.13-2 (continued)        Shahuindo Life of Mine Financial Model

 

Base Case

 

Total

 

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

2030

 

2031

 

2032

 

Cash Flow

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Operating Income

 

$

990,158

 

 

$

26,302

 

$

37,137

 

$

105,070

 

$

96,699

 

$

104,551

 

$

109,473

 

$

131,094

 

$

165,042

 

$

126,159

 

$

94,849

 

$

(2,050

)

$

(1,251

)

$

(1,145

)

$

(893

)

$

(758

)

$

(122

)

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Working Capital

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Accounts Payable (30 days)

 

 

 

 

$

4,261

 

$

(804

)

$

5,510

 

$

1,055

 

$

(822

)

$

(438

)

$

1,196

 

$

(444

)

$

(607

)

$

(3,279

)

$

(197.62

)

$

(5,872

)

$

170

 

$

(165

)

$

587

 

$

(657

)

$

(150

)

IGV

 

 

 

 

$

(5,320

)

$

(16,693

)

$

14,380

 

$

15,688

 

$

4,978

 

$

(1,227

)

$

(388

)

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Closure Costs (Cash)

 

 

 

 

$

 

$

 

$

 

$

 

$

 

$

(3

)

$

(146

)

$

(15

)

$

(146

)

$

(1,277

)

$

(14,224

)

$

(2,607

)

$

(4,678

)

$

(2,672

)

$

(9,818

)

$

(1,829

)

$

 

Total Working Capital

 

 

 

 

(1,059

)

(17,497

)

19,889

 

16,742

 

4,156

 

(1,668

)

662

 

(459

)

(753

)

(4,556

)

(14,422

)

(8,479

)

(4,508

)

(2,837

)

(9,231

)

(2,486

)

(150

)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Capital Expenditures

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Project Capital

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mine

 

$

27,452

 

 

$

27,452

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Process Plant

 

$

105,568

 

 

$

18,943

 

$

86,625

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Other

 

$

46,609

 

 

$

28,537

 

$

11,811

 

$

6,261

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Sustaining Capital

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mining

 

$

130,305

 

 

$

 

$

28,140

 

$

21,890

 

$

17,045

 

$

17,696

 

$

13,762

 

$

10,052

 

$

14,674

 

$

4,332

 

$

2,713

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Process Plant & Other

 

$

10,372

 

 

$

338

 

$

4,301

 

$

2,787

 

$

1,240

 

$

382

 

$

368

 

$

174

 

$

266

 

$

262

 

$

254

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

Total Capital Expenditures

 

$

320,306

 

 

$

75,270

 

$

130,877

 

$

30,937

 

$

18,285

 

$

18,078

 

$

14,130

 

$

10,226

 

$

14,941

 

$

4,594

 

$

2,967

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cash Flow before Taxes

 

$

667,235

 

 

$

(47,451

)

$

(109,852

)

$

95,477

 

$

96,684

 

$

92,233

 

$

95,359

 

$

123,299

 

$

151,491

 

$

122,752

 

$

89,354

 

$

(14,422

)

$

(8,479

)

$

(4,508

)

$

(2,837

)

$

(9,231

)

$

(2,486

)

$

(150

)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Taxes

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Current Income Taxes

 

$

196,186

 

 

$

2,198

 

$

2,492

 

$

20,106

 

$

15,499

 

$

21,072

 

$

22,450

 

$

32,926

 

$

41,732

 

$

26,278

 

$

11,432

 

$

 

$

 

$

 

$

 

$

 

$

 

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cash Flow after Taxes

 

$

471,049

 

 

$

(49,649

)

$

(112,344

)

$

75,371

 

$

81,185

 

$

71,161

 

$

72,909

 

$

90,373

 

$

109,759

 

$

96,474

 

$

77,923

 

$

(14,422

)

$

(8,479

)

$

(4,508

)

$

(2,837

)

$

(9,231

)

$

(2,486

)

$

(150

)

Cummulative Cash Flow after Taxes

 

 

 

 

$

(49,649

)

$

(161,993

)

$

(86,622

)

$

(5,436

)

$

65,725

 

$

138,633

 

$

229,006

 

$

338,765

 

$

435,239

 

$

513,161

 

$

498,740

 

$

490,261

 

$

485,753

 

$

482,916

 

$

473,685

 

$

471,200

 

$

471,049

 

Payback (Years)

 

 

 

 

1

 

1

 

1

 

1

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Economic Indicators before Taxes

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NPV @ 0%

 

0

%

 

667,385

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NPV @ 5%

 

5

%

 

462,203

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NPV @ 10%

 

10

%

 

322,836

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Economic Indicators after Taxes

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NPV @ 0%

 

0

%

 

471,200

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NPV @ 5%

 

5

%

 

318,863

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NPV @ 10%

 

10

%

 

215,413

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

IRR

 

 

 

 

40.6

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Payback

 

 

 

 

4.1years

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Cash Cost per Ounce

 

$

686.35

 

 

$

749.24

 

$

678.71

 

$

682.65

 

$

791.34

 

$

735.32

 

$

707.48

 

$

686.22

 

$

602.16

 

$

665.08

 

$

596.77

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Operating Cost per Tonne Ore

 

110,890

 

 

5,756

 

5,602

 

10,289

 

13,412

 

13,039

 

12,352

 

16,066

 

14,405

 

12,732

 

7,236

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mining

 

$

4.50

 

 

$

4.91

 

$

3.77

 

$

6.00

 

$

5.24

 

$

4.55

 

$

4.40

 

$

4.04

 

$

4.20

 

$

4.16

 

$

3.49

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Process Plant

 

$

2.55

 

 

$

1.36

 

$

1.72

 

$

2.88

 

$

2.57

 

$

2.65

 

$

2.65

 

$

2.16

 

$

2.40

 

$

2.71

 

$

4.16

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

General Administration

 

$

2.23

 

 

$

4.06

 

$

3.38

 

$

2.42

 

$

1.83

 

$

1.94

 

$

2.17

 

$

1.78

 

$

1.93

 

$

2.19

 

$

2.66

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Refining

 

$

0.06

 

 

$

0.06

 

$

0.06

 

$

0.08

 

$

0.05

 

$

0.06

 

$

0.06

 

$

0.05

 

$

0.07

 

$

0.06

 

$

0.08

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

$

9.28

 

 

$

10.33

 

$

8.87

 

$

11.30

 

$

9.63

 

$

9.14

 

$

9.22

 

$

7.98

 

$

8.52

 

$

9.07

 

$

10.31

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mining Cost per Tonne Mined

 

$

1.91

 

 

$

2.64

 

$

2.17

 

$

1.92

 

$

2.17

 

$

1.84

 

$

1.69

 

$

2.00

 

$

1.99

 

$

1.75

 

$

1.38

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

239


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

23.0                        ADJACENT PROPERTIES

 

Other than prospects in the area previously exploited by informal miners (as discussed in this report), the Company is not aware of any mineral properties adjacent to the Shahuindo Project.

 

240


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

24.0                        OTHER RELEVANT DATA AND INFORMATION

 

24.1                        Construction and Mining Activities through 01 January 2016

 

24.1.1              Construction

 

Infrastructure and facilities construction to support mining operations at Shahuindo began in March 2015. Construction activity was sufficiently advanced to support plant commissioning and the commencement of Phase 1 mining operations in the fourth quarter of 2015.

 

24.1.1.1                            Access Road

 

A new access road to the Shahuindo mine site was constructed to accommodate trucks and equipment required for project construction. This involved construction of a new two kilometer road to link the existing access to the preexisting road. The preexisting road was regraded and widened to enable tanker trucks and low-bed trucks access to the site with materials and equipment. The access road was completed in May 2015, which significantly reduced travel time to the project site and impact to the townships of Chuquibamba, Araqueda & Pampachancas regarding dust, interaction with pedestrians, schools, animals and local vehicle traffic.

 

 

Figure 24.1-1                    Access Road Improvements

 

24.1.1.2                            Water Storage Pond

 

A water storage pond with a capacity of 18,000 m3 was completed in June 2015 to capture and store water from a local spring for use during plant commissioning and operation. A water well will be drilled and constructed in early 2016 to provide a constant source of inflow to the pond. Water from this pond will be distributed to the plant, camp facilities and other areas of the operation.

 

241


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 24.1-2                    Water Storage Pond

 

24.1.1.3                            Haul Roads

 

Two haul roads to facilitate the commencement of mining operations were completed in the second quarter of 2015. The first haul road connects the Phase 1 starter pit to the ROM leach pad (Pad 1); the second road was built to move mine waste from the starter pit to the base of the future second leach pad, where the foundation for the pad is currently under construction. These two haul roads were built to accommodate the start of mining operations, with each road having a 12 meter operational width and maximum grade of 12%. These roads will be widened in 2017 to accommodate the larger fleet required for Phase 2 operations; the steeper sections at the bottom of the valley will have been eliminated, reducing the maximum grade to 10%.

 

 

Figure 24.1-3                    Haul Road Construction

 

242


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

24.1.1.4                            Camp and Office Facilities

 

Construction of new camp and office facilities to support Phase 1 operations began in June 2015. The existing exploration camp will be decommissioned, with some of the buildings relocated to the new camp and others provided to the local San Jose community. The location of the new camp, close to the project entrance, also serves to reduce the interaction between mine traffic and local community traffic.

 

The new camp includes five workforce personnel modules with 16 rooms each, one staff personnel module with 16 rooms and two barracks modules for security staff. Construction of these facilities was completed in late November 2015, with electricity, water, and sewage facilities installed. An office building, kitchen and dining facilities, medical center and training room will be constructed in early 2016.

 

 

Figure 24.1-4                    New Camp under Construction

 

 

Figure 24.1-5                    Sewage Treatment Plant under Construction

 

243


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

A second phase of camp construction is planned for 2017 to accommodate the increased workforce required for Phase 2 operations scheduled to begin in 2018.

 

24.1.1.5                            Explosive Magazine

 

The explosives magazine facility includes one 60 tonne emulsion silo and two containers for explosives and accessories suitable for commissioning activities. An additional two silos will be in added in 2106, with another three silos erected in 2017 prior to Phase 2 operations.

 

 

Figure 24.1 -6                 Emulsion Silo

 

(MMU truck in foreground; explosives container in background)

 

24.1.1.6                            Temporary Workshop

 

A temporary relocatable workshop was constructed in the third quarter of 2015 to support construction activities and mining operations during the first two years of production. A more expansive permanent truck shop is planned for 2017 to support the larger equipment necessary for Phase 2 operations in 2018.

 

244


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 24.1-7                    Temporary Workshop under Construction

 

24.1.1.7                            Fuel Farm

 

Construction of the Phase 1 fuel farm facilities, consisting of two 60,000 gallon capacity tanks, was completed in the fourth quarter of 2015. Upon inspection and approval from MEM, the facility is expected to be operational in early 2016. Expansion of the fuel farm to 240,000 gallon capacity is scheduled for 2017.

 

 

Figure 24.1-8                    Fuel Farm under Construction

 

245


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

24.1.1.8                            Leach Pad 1A

 

The pilot leach pad (Pad 1A) was constructed in the second half of 2015. The pad has an area of 18 hectares and will accommodate approximately four million tonnes of ore; after which construction of the second ROM leach pad (Pad 2A) will be completed. The site was chosen based on the relative simplicity of construction (level ground) and proximity to the process plant and starter pit.

 

 

Figure 24.1-9                    Leach Pad 1A under Construction

 

 

Figure 24.1-10             Leach Pad 1A completed with Collection Piping

 

246


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 24.1-11             Leach Pad 1A with Overliner Being Placed

 

24.1.1.9                            Lime storage Shed

 

A lime storage shed with capacity of 500 tonnes was completed in November 2015. The structure is necessary to keep the lime dry during the rainy season and is a requirement for the storage of controlled substances in Peru. The lime storage shed was built adjacent to pad 1where the lime is mixed with the ore to maintain the cyanide solution at an optimal pH.

 

 

Figure 24.1-12             Lime Storage Shed

 

24.1.1.10                     ADR Plant and PLS Pond

 

Process plant and pregnant leach solution (PLS) pond construction for the Phase 1 operation was completed and commissioned in December 2015. Ongoing work into 2016 includes the installation of additional carbon columns to increase the adsorption capacity to 24,000 tpd, with continuing expansion in 2017 to increase capacity to the Phase 2 production rate of 36,000 tpd.

 

247


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 24.1-13             ADR Plant

 

 

Figure 24.1-14             PLS Pond

 

 

Figure 24.1-15             ADR Plant and PLS Pond

 

248


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

24.1.1.11                                             Leach Pad 2B

 

The Phase 2 leach pad (pad 2B) is located in a valley to the south/southwest of the pad 1A. Approximately five million cubic meters of compacted fill will be placed as a foundation to insure the stability of the pad. The foundation is being constructed using suitable material derived from construction activities and waste rock from the starter pit. The foundation is scheduled for completion in mid-2017 to enable pad construction to be completed to receive ore from Phase 2 mining. A second PLS pond and storm event pond will be constructed downstream of the pad.

 

 

Figure 24.1-16             Leach Pad 2B Foundation and Sub-Drain Excavation

 

249


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 24.1-17             Leach Pad 2B Foundation Construction

 

24.1.2              Mine and Plant Commissioning

 

Mining of the starter pit commenced in early November 2015. At the end of December 2015, approximately 184,000 tonnes with an average grade of 1.05 g/t Au had been mined from the pit, with 164,000 of these tonnes placed on the ROM pad.

 

Commissioning of the Pad 1A irrigation system began in mid-December 2015, with process plant commissioning initiated in the second half of December 2015. The Shahuindo mine poured its initial doré containing 581 ounces of gold and 347 ounces of silver on 22 December 2015. All commissioning activities are proceeding on schedule and the Company anticipates reaching commercial production in the second quarter of 2016.

 

250


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 24.1-18             Schematic of Starter Pit, ROM Pad and Haul Roads

 

 

Figure 24.1-19             Overview of Starter Pit, ROM Pad and Haul Roads

(View to the NE)

 

251


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 24.1-20             Initial Drill Pattern — November 2015

 

 

Figure 24.1-21             Ore Place on Pad 1A — December 2015

 

 

Figure 24.1-22             Pad 1A Irrigation Commissioning — December 2015

 

252


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

24.2                        Exploration Potential

 

Multiple exploration targets have been identified in the Shahuindo district based on surface mapping, rock-chip and soil surveys, geophysical surveys and drilling. These prospects include San Lorenzo, Choloque, Shahuindo Southeast Extension, El Sauce, La Chilca, Azules, Algamarca, Cantera and Malvas. The locations of the exploration targets are shown in Figure 24.2-1.

 

 

Figure 24.2-1                    Major Exploration Targets around the Shahuindo Project

 

24.2.1              San Lorenzo and Choloque

 

The San Lorenzo and Choloque targets are situated to the northeast of the currently-defined pit. The prospects were identified by mapping and sampling of surface exposures of hydrothermal breccia and mineralized sandstone along sub-parallel northeast-trending structures which are interpreted to be a secondary control to mineralization at the Shahuindo deposit. Tahoe conducted additional mapping and sampling prior to the initiation of reconnaissance drilling in the second half of 2015.

 

Drilling at San Lorenzo in 2015 included two core holes (422m) and 24 RC holes (4,076m); drilling at Choloque included one core hole (300m) and four RC holes (1,066m). Select drill results from San Lorenzo and Choloque are presented in Table 24.2-1 and Table 24.2-2, respectively. A complete

 

253


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

tabulation of significant intercepts from Tahoe’s 2015 drill program at San Lorenzo and Choloque is included in the Appendix. Figure 24.2-2 is a drill hole location map of the San Lorenzo and Choloque areas.

 

Table 24.2-1                         San Lorenzo — Select Drill Results

 

 

 

 

From

 

 

To

 

 

Drilled Length

 

 

Est. True

 

 

 

 

 

 

 

Hole ID

 

 

(m)

 

 

(m)

 

 

(m)

 

 

Width (m)

 

 

Au g/t

 

 

Ag g/t

 

SHA-D15-019

 

 

156.4

 

 

167.1

 

 

10.7

 

 

5.3

 

 

0.93

 

 

1.87

 

including

 

 

156.4

 

 

157.8

 

 

1.4

 

 

0.7

 

 

5.93

 

 

9.10

 

SHA-D20-020

 

 

50.0

 

 

56.9

 

 

6.9

 

 

3.4

 

 

0.70

 

 

1.30

 

 

 

 

113.9

 

 

117.2

 

 

3.3

 

 

1.7

 

 

4.30

 

 

6.00

 

including

 

 

113.9

 

 

117.2

 

 

1.5

 

 

0.8

 

 

9.14

 

 

8.40

 

 

 

 

129.6

 

 

133.6

 

 

4.0

 

 

2.0

 

 

1.61

 

 

12.10

 

 

 

 

142.5

 

 

153.0

 

 

10.5

 

 

5.3

 

 

0.96

 

 

5.54

 

SHA-R15-277

 

 

80.0

 

 

90.0

 

 

10.0

 

 

5.0

 

 

0.48

 

 

2.44

 

SHA-R15-279

 

 

12.0

 

 

50.0

 

 

38.0

 

 

19.0

 

 

0.58

 

 

6.05

 

 

 

 

62.0

 

 

82.0

 

 

20.0

 

 

10.0

 

 

0.40

 

 

3.12

 

 

 

 

120.0

 

 

138.0

 

 

18.0

 

 

9.0

 

 

0.69

 

 

7.17

 

 

 

 

152.0

 

 

156.0

 

 

4.0

 

 

2.0

 

 

7.13

 

 

22.25

 

 

 

 

180.0

 

 

212.0

 

 

32.0

 

 

16.0

 

 

0.51

 

 

3.87

 

including

 

 

194.0

 

 

196.0

 

 

2.0

 

 

1.0

 

 

3.19

 

 

11.20

 

SHA-R15-280

 

 

0

 

 

8.0

 

 

8.0

 

 

4.0

 

 

0.89

 

 

3.78

 

 

 

 

28.0

 

 

38.0

 

 

10.0

 

 

5.0

 

 

0.34

 

 

3.42

 

SHA-R15-281

 

 

46.0

 

 

74.0

 

 

28.0

 

 

14.0

 

 

0.98

 

 

2.88

 

including

 

 

60.0

 

 

62.0

 

 

2.0

 

 

1.0

 

 

9.13

 

 

6.50

 

SHA-R15-282

 

 

16.0

 

 

58.0

 

 

42.0

 

 

21.0

 

 

0.45

 

 

11.02

 

SHA-R15-283

 

 

16.0

 

 

48.0

 

 

32.0

 

 

16.0

 

 

0.42

 

 

3.79

 

SHA-R15-284

 

 

24.0

 

 

70.0

 

 

46.0

 

 

23.0

 

 

1.11

 

 

3.36

 

including

 

 

54.0

 

 

56.0

 

 

2.0

 

 

1.0

 

 

2.87

 

 

4.10

 

including

 

 

60.0

 

 

66.0

 

 

6.0

 

 

3.0

 

 

3.89

 

 

2.27

 

SHA-R15-286

 

 

154.0

 

 

166.0

 

 

12.0

 

 

6.0

 

 

3.84

 

 

6.38

 

including

 

 

160.0

 

 

164.0

 

 

4.0

 

 

2.0

 

 

10.97

 

 

15.10

 

SHA-R15-345

 

 

86.0

 

 

92.0

 

 

6.0

 

 

3.0

 

 

1.04

 

 

9.33

 

SHA-R15-347

 

 

50.0

 

 

80.0

 

 

30.0

 

 

15.0

 

 

1.07

 

 

3.08

 

including

 

 

52.0

 

 

54.0

 

 

2.0

 

 

1.0

 

 

2.82

 

 

2.20

 

including

 

 

74.0

 

 

78.0

 

 

4.0

 

 

2.0

 

 

2.74

 

 

6.60

 

SHA-R15-348

 

 

6.0

 

 

72.0

 

 

66.0

 

 

33.0

 

 

2.62

 

 

27.49

 

including

 

 

14.0

 

 

20.0

 

 

6.0

 

 

3.0

 

 

21.36

 

 

182.87

 

 

 

 

52.0

 

 

54.0

 

 

2.0

 

 

1.0

 

 

3.71

 

 

34.40

 

SHA-R15-349

 

 

0.0

 

 

34.0

 

 

34.0

 

 

17.0

 

 

0.61

 

 

6.94

 

SHA-R15-351

 

 

64.0

 

 

90.0

 

 

26.0

 

 

13.0

 

 

2.54

 

 

8.54

 

including

 

 

68.0

 

 

76.0

 

 

8.0

 

 

4.0

 

 

4.64

 

 

19.73

 

including

 

 

86.0

 

 

90.0

 

 

4.0

 

 

2.0

 

 

3.19

 

 

3.75

 

 

254


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 24.2-2                         Choloque — Select Drill Results

 

 

 

 

From

 

 

To

 

 

Drilled Length

 

 

Est. True

 

 

 

 

 

 

 

Hole ID

 

 

(m)

 

 

(m)

 

 

(m)

 

 

Width (m)

 

 

Au g/t

 

 

Ag g/t

 

SHA-R15-306

 

 

168.0

 

 

194.0

 

 

26.0

 

 

13.0

 

 

4.02

 

 

18.58

 

including

 

 

172.0

 

 

178.0

 

 

6.0

 

 

3.0

 

 

14.55

 

 

48.70

 

 

 

 

224.0

 

 

234.0

 

 

10.0

 

 

5.0

 

 

8.42

 

 

102.22

 

including

 

 

232.0

 

 

234.0

 

 

2.0

 

 

1.0

 

 

41.43

 

 

486.00

 

SHA-R15-327

 

 

140.0

 

 

176.0

 

 

36.0

 

 

18.0

 

 

2.27

 

 

53.54

 

including

 

 

150.0

 

 

152.0

 

 

2.0

 

 

1.0

 

 

26.91

 

 

344.00

 

including

 

 

160.0

 

 

164.0

 

 

4.0

 

 

2.0

 

 

4.02

 

 

83.70

 

 

 

 

244.0

 

 

260.0

 

 

16.0

 

 

8.0

 

 

2.89

 

 

98.84

 

including

 

 

244.0

 

 

252.0

 

 

8.0

 

 

4.0

 

 

5.43

 

 

116.48

 

 

 

Figure 24.2-2                    San Lorenzo and Choloque Drill Hole Location Map

 

note: map was created prior to the cessation of the 2015 drill program — all drill holes not shown

 

255


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

24.2.2              Shahuindo Southeast Extension and El Sauce

 

Condemnation drilling in 2015 identified two areas of mineralization in colluvium and bedrock sediments along the southeastern extension of the San Jose anticline. Mineralization at the Shahuindo Southeast Extension and El Sauce targets are outside of the current resource, but a portion of this mineralization will be mined and likely processed in 2016 prior to construction of the primary waste dump.

 

Condemnation drilling in 2015 included 19 core holes (3,631m) and 28 RC holes (2,814m). Additional drilling is planned for 2016 to further delineate the mineralization in these areas. Select drill results are presented in Tables 24.2-3 and 24.2-4. A complete tabulation of significant intercepts from the condemnation drilling at the Southeast Extension and El Sauce targets is included in the Appendix.

 

Table 24.2-3                         Southeast Extension — Select Drill Results

 

 

 

 

From

 

 

To

 

 

Drilled Length

 

 

Est. True

 

 

 

 

 

 

 

Hole ID

 

 

(m)

 

 

(m)

 

 

(m)

 

 

Width (m)

 

 

Au g/t

 

 

Ag g/t

 

SHA-D15-001S

 

 

62.0

 

 

69.0

 

 

7.0

 

 

n/a

 

 

1.20

 

 

12.57

 

including

 

 

67.2

 

 

69.0

 

 

1.8

 

 

n/a

 

 

3.48

 

 

4.70

 

SHA-D15-003S

 

 

0.0

 

 

24.3

 

 

24.3

 

 

21.0

 

 

0.79

 

 

1.85

 

 

 

 

42.0

 

 

50.0

 

 

8.0

 

 

n/a

 

 

0.35

 

 

4.15

 

SHA-D15-011S

 

 

167.0

 

 

200.2

 

 

33.2

 

 

n/a

 

 

0.42

 

 

2.55

 

SHA-D15-017S

 

 

12.7

 

 

32.2

 

 

19.5

 

 

n/a

 

 

0.70

 

 

10.88

 

including

 

 

22.8

 

 

26.5

 

 

3.7

 

 

n/a

 

 

2.53

 

 

50.78

 

SHA-D15-019S

 

 

47.5

 

 

58.2

 

 

10.7

 

 

n/a

 

 

1.00

 

 

8.73

 

including

 

 

47.5

 

 

49.0

 

 

1.5

 

 

n/a

 

 

3.05

 

 

6.00

 

SHA-R15-299

 

 

182.0

 

 

188.0

 

 

6.0

 

 

n/a

 

 

1.26

 

 

29.47

 

SHA-R15-304

 

 

6.0

 

 

22.0

 

 

16.0

 

 

9.2

 

 

0.37

 

 

0.24

 

 

Table 24.2-4                         El Sauce — Select Drill Results

 

 

 

 

From

 

 

To

 

 

Drilled Length

 

 

Est. True

 

 

 

 

 

 

 

Hole ID

 

 

(m)

 

 

(m)

 

 

(m)

 

 

Width (m)

 

 

Au g/t

 

 

Ag g/t

 

SHA-R15-292

 

 

38.0

 

 

42.0

 

 

4.0

 

 

n/a

 

 

0.88

 

 

0.10

 

SHA-R15-293

 

 

0.0

 

 

4.0

 

 

4.0

 

 

1.9

 

 

0.45

 

 

0.20

 

SHA-R15-295

 

 

32.0

 

 

64.0

 

 

32.0

 

 

n/a

 

 

1.49

 

 

6.10

 

including

 

 

32.0

 

 

38.0

 

 

6.0

 

 

n/a

 

 

5.73

 

 

25.33

 

SHA-R15-330

 

 

22.0

 

 

38.0

 

 

16.0

 

 

n/a

 

 

0.40

 

 

5.55

 

SHA-R15-334

 

 

2.0

 

 

14.0

 

 

12.0

 

 

6.9

 

 

0.56

 

 

1.90

 

 

 

 

46.0

 

 

58.0

 

 

12.0

 

 

n/a

 

 

0.50

 

 

1.13

 

SHA-R15-335

 

 

0.0

 

 

18.0

 

 

18.0

 

 

15.6

 

 

0.58

 

 

2.00

 

SHA-R15-336

 

 

12.0

 

 

26.0

 

 

14.0

 

 

n/a

 

 

0.56

 

 

1.63

 

 

 

 

44.0

 

 

54.0

 

 

10.0

 

 

n/a

 

 

1.26

 

 

1.76

 

including

 

 

48.0

 

 

50.0

 

 

2.0

 

 

n/a

 

 

3.45

 

 

3.10

 

 

256


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 24.2-4 (continued)              El Sauce — Select Drill Intercepts

 

 

 

 

From

 

 

To

 

 

Drilled Length

 

 

Est. True

 

 

 

 

 

 

 

Hole ID

 

 

(m)

 

 

(m)

 

 

(m)

 

 

Width (m)

 

 

Au g/t

 

 

Ag g/t

 

SHA-R15-337

 

 

42.0

 

 

58.0

 

 

16.0

 

 

n/a

 

 

1.28

 

 

4.44

 

SHA-R15-338

 

 

0.0

 

 

12.0

 

 

12.0

 

 

10.5

 

 

0.50

 

 

2.43

 

 

 

 

34.0

 

 

62.0

 

 

28.0

 

 

n/a

 

 

0.79

 

 

2.61

 

including

 

 

36.0

 

 

38.0

 

 

2.0

 

 

n/a

 

 

3.24

 

 

9.90

 

SHA-R15-339

 

 

10.0

 

 

24.0

 

 

14.0

 

 

n/a

 

 

0.46

 

 

2.23

 

SHA-R15-340

 

 

54.0

 

 

68.0

 

 

14.0

 

 

n/a

 

 

1.58

 

 

1.63

 

including

 

 

56.0

 

 

60.0

 

 

4.0

 

 

n/a

 

 

4.48

 

 

1.50

 

SHA-R15-341

 

 

16.0

 

 

22.0

 

 

6.0

 

 

n/a

 

 

0.51

 

 

0.97

 

 

24.2.3              La Chilca Baja Cu-Au porphyry

 

The La Chilca Baja target is a felsic intrusive with a surface expression approximately 200m in diameter located northwest of the Shahuindo resource. The intrusive has been pervasively altered to sericite with pyrite-chalcopyrite veinlets containing gold and silver values. Informal miners had been working underground in this area for the past ten years or so, exploiting narrow veins within the intrusive.

 

Tahoe drilled three exploratory core holes totaling 350m at La Chilca Baja in 2015. Select drill intercepts are shown in Table 24.2-5. A complete listing of significant intercepts is included in the Appendix. Tahoe will continue to explore this target in 2016.

 

Table 24.2-5                         La Chilca Baja — Select Drill Results

 

 

 

 

From

 

 

To

 

 

Drilled Length

 

 

Est. True

 

 

 

 

 

 

 

Hole ID

 

 

(m)

 

 

(m)

 

 

(m)

 

 

Width (m)

 

 

Au g/t

 

 

Ag g/t

 

SHA-D15-022

 

 

8.0

 

 

19.5

 

 

11.5

 

 

n/a

 

 

0.32

 

 

3.22

 

SHA-D15-023

 

 

4.0

 

 

73.4

 

 

69.4

 

 

n/a

 

 

1.36

 

 

13.64

 

including

 

 

26.0

 

 

35.9

 

 

9.9

 

 

n/a

 

 

7.13

 

 

64.16

 

SHA-D15-024

 

 

0.0

 

 

54.0

 

 

54.0

 

 

n/a

 

 

1.26

 

 

5.80

 

including

 

 

18.0

 

 

24.5

 

 

6.5

 

 

n/a

 

 

6.65

 

 

3.64

 

 

24.2.4              La Chilca Alta

 

Field observations in the La Chilca Alta area identified mineralization in the Chimu and Santa formations (the same host rocks as Shahuindo). Structurally, this area occurs along the northwest projection of the Algamarca anticline, where steep axial-plane parallel fracture patterns were recognized in Chimu quartzite and in weakly silicified dacite near the quartzite contact.

 

257


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Mineralization in the Chimu formation includess quartz-pyrite veinlets up to one cm wide and brecciated sandstone with pyrite, euhedral quartz druse lining vugs, and locally coarse-grained illite (sericite). Cubic and pyritohedron voids up to 3mm in diameter filled with hematitic iron oxides indicate the presence of significant pyrite.

 

Informal miners exploited northeast-striking veins that consisted of crackle- and rotated-clast breccia in Chimú quartzite; open-space hydrothermal fill consists of drusy quartz and various sulfides (pyrite, chalcopyrite, tennantite-tetrahedrite, and possibly chalcocite). Numerous breccia types similar to those encountered at Shahuindo have been recognized in this area, including monolithic-clast breccia (quartzite clasts), heterolithic igneous-matrix breccia (diatreme breccia with sedimentary and porphyry clasts), and monolithic igneous-matrix breccia with sedimentary clasts (along the Chimú-dacite contact).

 

Tahoe has not conducted any drilling at La Chilca Alta to date, though the mineralization is similar to that found in the main Shahuindo deposit and represents a significant exploration target in the district.

 

24.2.5     Azules

 

The Azules prospect (also referred to as the Northern Corridor Project) is a sediment-hosted gold target previously identified by the Minera Algamarca Company in the 1980s. Buenaventura Ingenieros completed a report in 1986 for Minera Algamarca Company that reportedly described a 35m long narrow (1.35m) northwest-striking vein, dipping 60° to the southwest with average grades of 12 g/t Au and 34 oz/t Ag and a second low angle structure approximately 1.2m wide and of unknown extent that averaged 27 g/t Au and 19 oz/t Ag (E. Garay, pers. comm.). The report also referenced a silicified dacitic sill, approximately 2m thick and of unknown extent, with average grades of 6.6 g/t Au and 2.6 oz/t Ag. Tahoe has not verified this information.

 

Sulliden conducted exploration activities in the Azules area and identified anomalous gold and silver values in hydrothermal breccia emplaced in sandstone beds of the Farrat Formation. During 2011, Sulliden drilled 6,178m of core at 29 locations (Figure 24.2-3) that returned numerous mineralized intercepts including 0.79 g/t Au and 77 g/t Ag over 59.5m (drill hole SHN11-328) and 0.41 g/t Au and 8.89 g/t Ag over 60m (drill hole SHN11-330). The oxidation boundary appears to be shallow (less than 50m depth). A summary of Sulliden’s drilling is shown in Table 24.2-6.

 

Tahoe has not conducted exploration activities at the Azules prospect to date.

 

258


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 24.2-6        Azules — Sulliden Drill Results

 

 

 

From

 

 

To

 

 

Drilled Length

 

 

Est. True

 

 

 

 

 

 

 

Hold ID

 

(m)

 

 

(m)

 

 

(m)

 

 

Width (m)

 

 

Au g/t

 

 

Ag g/t

 

SH04-56

 

43.5

 

 

55.5

 

 

12

 

 

n/a

 

 

0.35

 

 

19.63

 

 

97.5

 

 

106.5

 

 

9

 

 

n/a

 

 

0.32

 

 

19.71

 

SH04-57

 

18

 

 

33

 

 

15

 

 

n/a

 

 

0.35

 

 

40

 

SHN11-297

 

7.9

 

 

26.7

 

 

18.8

 

 

n/a

 

 

0.29

 

 

1.21

 

 

127.9

 

 

142.4

 

 

14.5

 

 

n/a

 

 

0.65

 

 

3.83

 

SHN11-301

 

88.7

 

 

99.2

 

 

10.5

 

 

n/a

 

 

0.27

 

 

9.49

 

SHN11-307

 

0

 

 

8.4

 

 

8.4

 

 

n/a

 

 

0.99

 

 

26.15

 

SHN11-308

 

40.7

 

 

49.7

 

 

9

 

 

n/a

 

 

0.16

 

 

4.64

 

SHN11-311

 

271.7

 

 

318.3

 

 

46.6

 

 

n/a

 

 

0.28

 

 

3.44

 

SHN11-312

 

94.7

 

 

114.9

 

 

20.2

 

 

n/a

 

 

0.3

 

 

7.26

 

 

129.2

 

 

148.7

 

 

19.5

 

 

n/a

 

 

0.22

 

 

5.4

 

 

177.2

 

 

199.7

 

 

22.5

 

 

n/a

 

 

0.18

 

 

4.13

 

SHN11-313

 

82.5

 

 

90

 

 

7.5

 

 

n/a

 

 

0.47

 

 

7

 

 

115.5

 

 

135

 

 

19.5

 

 

n/a

 

 

0.29

 

 

9.79

 

 

153

 

 

165

 

 

12

 

 

n/a

 

 

0.17

 

 

13.98

 

SHN11-317

 

192

 

 

205.5

 

 

13.5

 

 

n/a

 

 

0.18

 

 

2.94

 

SHN11-318

 

62.7

 

 

81.2

 

 

18.5

 

 

n/a

 

 

0.34

 

 

29.72

 

SHN11-319

 

234.1

 

 

268.6

 

 

34.5

 

 

n/a

 

 

0.16

 

 

3.14

 

SHN11-320

Including
Including

 

85.2

 

 

140.9

 

 

55.7

 

 

n/a

 

 

0.18

 

 

2.55

 

 

96.4

 

 

106.4

 

 

10

 

 

n/a

 

 

0.28

 

 

1.37

 

 

132.4

 

 

140.9

 

 

8.5

 

 

n/a

 

 

0.29

 

 

6.66

 

 

167.9

 

 

175.2

 

 

7.3

 

 

n/a

 

 

0.24

 

 

3.38

 

 

222.4

 

 

244.4

 

 

22

 

 

n/a

 

 

0.59

 

 

18.22

 

SHN11-323

 

47.9

 

 

81.6

 

 

33.7

 

 

n/a

 

 

0.2

 

 

7.16

 

 

112.7

 

 

127.4

 

 

14.7

 

 

n/a

 

 

0.27

 

 

10.41

 

 

163.7

 

 

173.3

 

 

9.6

 

 

n/a

 

 

0.28

 

 

1.8

 

SHN11-328

Including

 

0

 

 

59.5

 

 

59.5

 

 

n/a

 

 

0.79

 

 

76.61

 

 

27.2

 

 

46.7

 

 

19.5

 

 

n/a

 

 

1.55

 

 

127.04

 

SHN11-329

 

43.7

 

 

69.2

 

 

25.5

 

 

n/a

 

 

0.35

 

 

24.98

 

 

109.7

 

 

121.7

 

 

12

 

 

n/a

 

 

1.06

 

 

37.61

 

SHN11-330

 

119.5

 

 

179.5

 

 

60

 

 

n/a

 

 

0.41

 

 

8.89

 

 

187

 

 

200

 

 

13

 

 

n/a

 

 

0.18

 

 

6.11

 

SHN11-332

 

3

 

 

18.5

 

 

15.5

 

 

n/a

 

 

0.23

 

 

2.99

 

SHN11-335

 

60.1

 

 

93.1

 

 

33

 

 

n/a

 

 

1.01

 

 

15.21

 

 

166.75

 

 

195.1

 

 

28.35

 

 

n/a

 

 

0.25

 

 

6.91

 

 

217.6

 

 

261.1

 

 

43.5

 

 

n/a

 

 

0.39

 

 

18.29

 

 

259


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Figure 24.2-3       Azules Drill Hole Location Map

 

24.2.6     Algamarca Au-Ag-Cu Vein system

 

Algamarca is an underground mine that has been worked for over 40 years and is currently being exploited on a small scale by informal miners. At least six narrow veins have been recognized in thick sandstone beds of the Chimu formation. The veins generally strike northeast and dip 60˚ to 70˚ to the southeast (Figure 24.2-4), vary in thickness from 0.2m to 2m, and tend to bifurcate when they trend into host rocks other than the Chimu. The Algamarca veins have been identified over a 400m strike length and 200m down dip.

 

The most exploited vein at Algamarca is the Descubridora vein. The vein mineralogy is pyrite, galena, sphalerite, chalcopyrite, bornite, and Ag-sulfosalts (Figure 24.2-5). The wall rock has been pervasively altered to sericite. The wallrock alteration and mineral assemblage suggests Algamarca is an intermediate-sulfidation type deposit. Rio Alto geologists sampled the Descubridora vein at limited locations on the 4 and 5 levels of the mine. The sample results summarized in Table 24.2-7 are considered indicative only, as access was limited.

 

260


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Table 24.2-7        Algamarca — Sample Results from the Descubridora Vein

 

 

 

Sample

True Width

 

 

 

Location

Type

Length (m)

(m)

Au g/t

Ag g/t

Cu %

Level 5

Vein

1.2

1.2

5.70

4,298

15.59

Vein

0.6

0.6

8.31

860

5.81

Wallrock

1.5

n/a

0.16

19

0.07

Vein

0.6

0.6

9.30

1,782

5.57

Vein

0.4

0.4

13.90

2,740

24.55

Wallrock

1.0

n/a

1.21

66

0.22

Wallrock

1.0

n/a

6.15

617

2.26

Level 4

Vein

0.4

0.4

10.87

3,282

14.11

Wallrock

1.0

n/a

0.43

68

0.26

Wallrock

1.0

n/a

0.59

50

0.58

Vein

0.5

0.5

2.92

430

13.49

Wallrock

1.0

n/a

0.03

2

0.01

Vein

0.5

0.5

10.17

2,359

21.78

Vein

1.0

1.0

5.81

715

5.24

 

 

Figure 24.2-4       Algamarca Sample Location Map (4 and 5 Levels)

 

261


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

 

Figure 24.2-5       Algamarca — Descubridora Vein on Levels 4 and 5

 

(massive chalcopyrite as clasts and matrix)

 

24.2.7     Cantera

 

The Cantera prospect is a sediment-hosted gold target northwest of the Shahuindo deposit. Cantera was identified by IP surveys followed by reconnaissance surface mapping and limited surface geochemical sampling. Further field work is necessary to define drill targets.

 

262


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

24.2.8     Malvas

 

The Malvas base metal anomaly is located along a northwest-trending topographic ridge that follows the trend of the Algamarca anticline. Folded sedimentary rocks of the Carhuaz Formation are intruded by a large irregularly shaped body of heterolithic biotite diorite breccia about one kilometer in diameter, which is in turn intruded by foliated biotite quartz diorite porphyry and then cut by a circular body of heterolithic megabreccia 500m in diameter.

 

The heterolithic biotite diorite breccia displays strong quartz-illite-pyrite alteration for 30 to 40 meters along the southeast contact with foliated biotite quartz diorite porphyry. The foliated biotite quartz diorite and the heterolithic megabreccia are magnetic and show only traces of weak chlorite-epidote alteration.

 

At the northwest contact with foliated biotite quartz porphyry, heterolithic biotite diorite breccia is again strongly altered to quartz-illite assemblage and may include zones with pyrophyllite and alunite. Brecciated sandstone adjacent to the igneous matrix breccia appears to originally have had up to 10% pyrite in areas that now have abundant iron oxide and jarosite.

 

Tahoe considers the Malvas prospect as an important long-term exploration target. Focus on this prospect will commence when the extent of the oxide mineralization that could add to the economics of the current project are delineated.

 

263


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

25.0        INTERPRETATION AND CONCLUSIONS

 

The Shahuindo mine is registered in the name of Shahuindo SAC. Tahoe Resources is a sole proprietor of the Shahuindo mine through its subsidiary, Shahuindo SAC. The Shahuindo mine is currently completing Phase 1 construction which includes the development of the Phase 1 leach pads and processing facility. Commissioning is expected to be completed in January 2016 with commercial production anticipated by the second quarter of 2016.

 

The results of this study conclude:

 

·                  The Shahuindo mine prefeasibility study demonstrates the economic viability of the Shahuindo mine from 01 January 2016 through to the end of the estimated mine life and supports the declaration of Proven and Probable Mineral Reserves.

 

·                  The Mineral Resource Estimate for the Shahuindo deposit contains 1.55 million ounces of gold classified as Measured resources, 0.74 million ounces classified as Indicated resources and 0.62 million ounces of gold classified as Inferred resources. The cut-off grade for oxide of 0.14 g/t AuEq and sulfide of 0.5 g/t AuEq was used to equate the Resource. The effective date for the Mineral Resource is 15 April 2015.

 

·                  The Shahuindo Mineral Resource Estimated is supported by the geological model and is based on sufficient sample analytical and density measurements, detailed drill hole lithology and alteration data, and metallurgical testing.

 

·                  The recent infill drill program has increased the confidence in the resource resulting in an upgrade of material that was previously classified as Indicated to the Measured classification.

 

·                  The results of four data verification programs found that the QAQC is sufficient to ensure the dataset used in the resource estimate is reliable for estimation purposes of the Shahuindo Mineral Resources and the assignment of Measured and Indication classifications to the stated resource.

 

·                  The Shahuindo Proven and Probable Mineral Reserve for the Shahuindo mine using a cut-off grade of 0.14 g/t Au is 111.9 million tonnes with an average grade of 0.53 g/t Au and 6.82 g/t Ag, containing 1.91 million ounces of gold and 24.5 million ounces of silver. The effective date of the Mineral Reserve is 01 November 2015.

 

·                  The operating assumptions used in this study are based on operating results already achieved at Tahoe Resources’ La Arena mine which is very similar to the Shahuindo mine.

 

264


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                  The results of the laboratory testing program indicate very good gold recoveries at both run-of-mine (ROM) and moderate crush sizes with low to moderate reagent requirements implying amenability to heap leaching. Silver recoveries are generally low.

 

·                  The mining strategy at Shahuindo consists of two phases. The first phase consists of mining higher grade starter pits feeding the Phase 1 leach pads with run of mine material at an initial rate of 10,000 tonnes of ore per day and increasing plant capacity in mid-2016 to process an average of 12,200 tonnes of ore per day in 2016 and 16,500 tonnes of ore per day in 2017. The second phase includes the addition of a crushing and agglomeration facility, a large leach pad, and an increase in mining production to 36,000 tonnes of ore per day, which will require an upgraded mining fleet. The phased approach enables gold production as soon as possible with minimal capital expenditure, generating cash flow early in the project.

 

·                  The phased approach to mining and processing also allows the Company to conduct field-scale metallurgical testing to optimize the processing scheme for the remainder of the mine life (Phase 2). While there are clear benefits to metal recovery by the use of agglomeration, there may be opportunities to achieve lower operating and capital costs by reducing the amount of material in the current plan that are subject to agglomeration and/or crushing.

 

265


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

26.0        RECOMMENDATIONS

 

The recommendations for this report are as follows:

 

·                  Tahoe holds exploration licenses near the existing facility where the regional geology appears to be a favorable environment for the formation of mineral deposits. Tahoe has established numerous exploration prospects within Tahoe’s exploration area. The authors of this report recommend the Company continues to aggressively explore the Shahuindo district and accelerate district exploration with the goal of discovering additional oxide feed for the Shahuindo heap leach processing facility.

 

·                  The recent drilling conducted by Rio Alto in 2014-2015 and by Tahoe in 2015 has identified ore grade mineralization that is outside of the current oxide resource, beyond the limits of the current pit design. Tahoe should aggressively explore for extensions of the Shahuindo deposit and delineate the mineralization in these areas to expand the resource and incorporate these extensions into a new pit design.

 

·                  Assay standards should be validated and/or replaced. Validation should include consulting with CERTMIN in regards to the observed bias in the assay standards and also obtain the round-robin assays for the standards from SGS to determine the assay variance. In the event that no solution is found, it is recommended that the current standards be replaced with other commercially available standards. It is also recommended to incorporate standards into the sample stream that are either at or near the cut-off grades.

 

·                  Tahoe should investigate the practicality of creating new assay blanks from coarse RC rejects and begin using a second lab for check assays to improve the confidence in the current assay results.

 

·                  Continue to refine the geologic model to provide a more accurate prediction of material types to improve the predictability of the geometallurgical model.

 

·                  As additional drill data becomes available, the resource model should be refined and resource estimates updated. Additional infill drilling will lend further confidence in the resource model.

 

·      Update and refine the life of mine water balance as operational data becomes available.

 

·                  Maintaining heap permeability and minimizing channeling at higher heap heights constitutes a risk to the project as additional agglomeration and compacted permeability testing is required. The authors recommend Tahoe conduct pilot-scale heap leach tests on the current ROM leach pad to investigate field-scale performance on composites with varying degrees of coarse-to-fines ratios.

 

266


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                  The available data indicates that siltstones and breccia with high fines content will most likely not percolate in a ROM heap leach. The authors recommend conducting compacted permeability tests at the recommended coarse crush size, with no cement on these two material types. If the results of these tests are positive, then consideration should be given to conducting a pilot-scale test on a composite of these two rock types on the ROM pad. The splits from each composite tested in the pilot-scale tests should be taken and column leach tests conducted at a coarse crush size of approximately 80% passing 76mm.

 

·                  It is recommended that additional tests be conducted on samples taken from the drilling program, including:

 

·                  Column leach tests on both surface and large diameter core samples should be conducted on each of the rock types (except sulfides) at a p80 crush size of 76mm. The samples should be spatially representative of the orebody. Large diameter core holes should match the latest metallurgical drill holes so the results from the series of column leach tests on the -25mm tests can be compared to the 76mm test results. The gold grades of the individual rock types to be tested should be similar to those estimated in the mine plan.

 

·                  Compacted permeability tests on each rock type from the large core drilling program on composites crushed to 76mm should be conducted. The tests should include blended composites containing the different rock types at a ratio shown in the mining schedule. Tests at cement levels of 0 kg/t, 3 kg/t and 6 kg/t at varying simulated heap heights up to the maximum planned height above the liner should be completed. If any samples fail, then additional composites should be tested with increased levels of cement until acceptable percolation rates are achieved at all simulated heights.

 

·                  After reaching commercial production, the authors recommend the Company systematically evaluate mining, processing and other surface operations to optimize processes and procedures and reduce capital and operating costs. Example of these would include the following:

 

·                  Conduct a trade-off study to evaluate the potential to reduce or eliminate the requirements for crushing and/or agglomeration. It is recommended this be conducted by evaluating a series of material blends for leaching, percolation, and geotechnical stability characteristics. The analysis would need to review the operating and capital cost versus recovery. This would need to be conducted before the construction of the Phase 2 agglomeration and crushing circuit.

 

·                  The data for the secondary crusher indicated a recovery difference of 4-5% between a 76mm and 25mm crush size for the ROM material. A trade-off study should be conducted to determine if the additional recovery justifies the increased capital and operating costs of a secondary crushing circuit.

 

267


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

·                  Expand the geotechnical and hydrogeological evaluations to further optimize the overall slope angle of the final design of the Shahuindo open pit. This has the potential to increase the NPV of the overall project.

 

·                  There is potential to reduce the operating costs of the mine by evaluating the potential to place mined waste in the pit. This will require defining the underlying sulfide resource and understanding the economic potential (if any) of the sulfide mineralization.

 

The work completed to date demonstrates the project is technically and economically viable; the recommendations listed above are intended to provide the Company with guidance to optimize the Shahuindo mine.

 

268


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

27.0 REFERENCES

 

Anddes Asociados SAC, 2015a, Proyecto Shahuindo Ingenieria Basica del Pad N°2 - Criterio de Diseño, Revision 1.

 

Anddes Asociados SAC, 2015b, Proyecto Shahuindo Ingenieria Basica del Pad N°2 - Informe de Actualizacion de la Hidrologia, Revision B.

 

Anddes Asociados SAC, 2015c, Proyecto Shahuindo Ingenieria Basica del Pad N°2 - General Memorandum Tecnico, Revision 0.

 

Anddes Asociados SAC, 2015d, Proyecto Shahuindo Diseño de Taludes de Tajo - Informe Final Revision 0.

 

Anddes Asociados SAC, 2015e, Proyecto Shahuindo Ingenieria de Detalle del Pad N°01 - Criterio de Diseño, Revision 0.

 

Anddes Asociados SAC, 2015f, Proyecto Shahuindo Ingenieria de Detalle del Pad N°01 - Informe de Diseño Civil e Hidraulica , Revision 0.

 

Anddes Asociados SAC, 2015g, Proyecto Shahuindo Ingenieria de Detalle del Pad N°01 - Informe Geotecnico, Revision 0.

 

Anddes Asociados SAC, 2015h, Proyecto Shahuindo Ingenieria de Detalle del Pad N°01 - Resumen Ejecutivo, Revision 0.

 

Anddes Asociados SAC, 2015i, Proyecto Shahuindo Ingenieria Basica del Pad 2 - Shahuindo - Informe Geotecnico - Informe de Investigaciones Geotecnicas, Revision B.

 

Anddes Asociados SAC, 2015j, Proyecto Shahuindo Ingenieria de Detalle del Pad N°01 - Informe de Hidrologia y Balance de Agua, Revision 1.

 

Ausenco, 2012, Feasibility Study, Hydrogeology Report, prepared for Sulliden Gold Corporation.

 

Bussey, S., and Nelson, E., 2011, Geological Analysis of the Shahuindo district, Cajabamba Province, Peru, prepared by Western Mining Services LLC for Sulliden Gold Corporation.

 

Census National, 2007, http://censos.inei.gob.pe/cpv2007/tabulados.

 

Corbett, G.J., 2002, Epithermal Gold for Explorationists, AIG News No. 67.

 

269


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Defilippi, C., Dyer, T.L., and Tietz, P., 2012, Technical Report on the Shahuindo Heap Leach Project, Cajabamba, Peru, prepared for Sulliden Gold Corporation, Ltd.

 

Federal Emergency Management Agency of the U.S. Department of Homeland Security, 2009, NEHRP (National Earthquake Hazards Reduction Program) Recommended Seismic Provisions for New Buildings and Other Structures (FEMA P-750), 2009 Edition.

 

Fletcher, D. I., 1997, Boti Gold-silver Project, Department of Cajamarca, Peru, Internal Asarco Inc. report.

 

Golder Associates, 2012, Draft Feasibility-Level Pit Slope Investigation, prepared for Sulliden Gold Corporation.

 

Hatch, 2015, Rio Alto SAC Shahuindo Heap Leach Study Final Report.

 

Heap Leach Consultants, 2005, Proyecto San José de Algarmaca, Informe de Pruebas de Cianuracion en Botellas y Columnas a Escala Piloto, prepared for Cía. Minera Algamarca S.A.

 

Hedenquist, J. W., 1987, Mineralization Associated with Volcanic-related Hydrothermal Systems in the Circum-Pacific Basin, in Horn, M. K., ed., Transactions of the Fourth Circum-Pacific Energy and Mineral Resources Conference, Singapore: American Association of Petroleum Geologists, p. 513-524.

 

Hedenquist, J. W., and Arribas, A. R., Jr., 1999, I. Hydrothermal Processes in Intrusion-related Systems; II. Characteristics, Examples and Origin of Epithermal Gold Deposits, in Molnar, F., Lexa, J., and Hedenquist, J. W., eds., Epithermal Mineralization of the Western Carpathians: Society of Economic Geologists, Guidebook Series, no. 31, p. 13-61.

 

Hedenquist, J. W., Arribas, A. R., and Urien-Gonzales, E., 2000, Exploration for Epithermal Gold Deposits: SEG Reviews, v. 13, p. 245-277.

 

Hodder, R. W., et. al., 2010a, The Shahuindo Epithermal Gold Occurrence, Cajabamba Province, Peru; Petrographic Reconnaissance & Interpretation of Shape and Size, prepared for Sulliden Gold Corporation Ltd.

 

Hodder, R. W., 2010b, The Shahuindo Epithermal Gold Occurrence, addendum to the June 30, 2010 report by Hodder et al., prepared for Sulliden Gold Corporation Ltd.

 

Hoek E., Carranza-Torres C. & Corkum B., 2002, Hoek-Brown failure criterion - 2002 Edition, Proc. NARMS-TAC Conference, Toronto, 2002, 1, 267-273.

 

270


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

International Code Council, 2012 International Building Code, https://archive.org/stream/gov.law.icc.ibc.2012/icc.ibc.2012

 

International Commission on Large Dams, 2010, ICOLD Position Paper on Dam Safety and Earthquakes.

 

Kappes, Cassiday & Associates, January 2011, Drill Core Composites, Column Leach Test Program, Report of Metallurgical Test Work, prepared for Sulliden Gold Corporation.

 

Kappes, Cassiday & Associates, June 2011, All Rock Code Composites, Report of Metallurgical Test Work, prepared for Sulliden Gold Corporation.

 

Kappes, Cassiday & Associates, June 2011, Polymer Testing, Report of Metallurgical Test Work, prepared for Sulliden Gold Corporation.

 

Kappes, Cassiday & Associates, June 2011, Report of Metallurgical Test Work, Bottle Roll Tests, prepared for Sulliden Gold Corporation.

 

Kappes, Cassiday & Associates, March 2011, Report of Metallurgical Test Work, Bottle Roll Tests — 2010, SHM-10-116 — SHM-10-118, prepared for Sulliden Gold Corporation.

 

Kappes, Cassiday & Associates, May 2011, 116 & 118 Column Tests, Report of Metallurgical Test Work, prepared for Sulliden Gold Corporation.

 

Kappes, Cassiday & Associates, May 2012, Bulk ROM Material, Report of Metallurgical Test Work, prepared for Sulliden Gold Corporation.

 

Kappes, Cassiday & Associates, September 2012, HLC 6, 7, 8, 9 Composites, Report of Metallurgical Test Work, prepared for Sulliden Gold Corporation.

 

Montgomery Watson Harza Peru, 2015, Balance Hidrológico del Proyecto Shahuindo SHAHUINDO SAC, Final Version.

 

Montoya, D. E., Noble, D. C., Eyzaguirre, V. R., and Desrosiers, D. F., 1995, Sandstone-hosted Gold Deposits; A New Exploration Target is Recognized in Peru: Engineering and Mining Journal, June 1, 1995.

 

Pickmann and Ruiz, 2015, Title Opinion on the Shahuindo Mining Concessions, prepared for Tahoe Resources Inc. (unpublished).

 

Pickmann and Ruiz, 2015, Title Opinion on the Shahuindo Surface Lands, prepared for Tahoe Resources Inc. (unpublished).

 

271


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

Saucier, G., and Buchanan, M. J., 2005, Resources Estimation, Shahuindo Project, Peru, prepared for Sulliden Exploration Inc. by Met-Chem Canada Inc.

 

Saucier, G., and Poulin, L., 2004, Resources Estimation, Shahuindo Project, Peru, prepared for Sulliden Exploration by Met-Chem Canada Inc.

 

Silgado, E., 1978, Historia de los sismos mas notables ocurridos en el Pero (1513-1974), lnstituto de Geologîa y Minerîa, Boletin N° 3, Serie C, Geodinamica e Ingenierîa Geolégica, Lima-Peru.

 

Tietz, P., and Kappes, D., 2011, Technical Report on the Shahuindo Project, Cajabamba, Peru, prepared for Sulliden Gold Corporation, Ltd by Mine Development Associates and Kappes, Cassiday & Associates.

 

Val Dór Geofisica del Peru S.A.C., 2002, Geophysical Report on Induced Polarization, DGPS and Magnetic Surveys, Shahuindo Project, prepared for Exploration Sulliden Inc.

 

Wright, C., Melnyk, J., Gormely, L., Simpson, G., and Lupo, J., 2010a, Shahuindo Gold Project, Cajabamba Province, Peru, NI 43-101 Technical Report on Preliminary Assessment, prepared by AMEC Americas Inc. for Sulliden Gold Corporation.

 

Wright, C., Melnyk, J., Gormely, L., Simpson, G., and Lupo, J., 2010b, Shahuindo Gold Project, Cajabamba Province, Peru, Preliminary Assessment, prepared by AMEC Americas Inc. for Sulliden Gold Corporation.

 

272


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

28.0        AUTHORS CERTIFICATES

 

273


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

28.1        Certificate of Qualified Person — Carl E. Defilippi

 

I, Carl E. Defilippi, M.Sc., C.E.M., do hereby certify that I am currently employed as a Project Manager for Kappes, Cassiday & Associates, 7950 Security Circle, Reno, Nevada 89506.

 

1.              I graduated with a Bachelor of Science degree in Chemical Engineering from the University of Nevada in 1978 and a Master of Science degree in Metallurgical Engineering from the University of Nevada in 1981. I have practiced my profession continuously since 1981.

 

2.              I am a Registered Member in good standing of the Society for Mining, Metallurgy and Exploration (775870RM).

 

3.              I have read National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association as defined in NI 43-101 and past relevant work experience, I fulfil the requirements to be a “Qualified Person” for the purposes of NI 43-101.

 

4.              I am independent of Tahoe Resources Inc. and its related companies, as independence is described in Section 1.5 of NI 43-101.

 

5.              I am one of the authors of this Technical Report titled Technical Report on the Shahuindo Mine, Cajabamba, Peru prepared for Tahoe Resources Inc., with an effective date of 01 January 2016 and dated 25 January 2016. I am responsible for Sections 13 and 17 and the corresponding items in Sections 1, 25 and 26 of this report. This technical report has been prepared in compliance with NI 43-101 and Form 43-101F1.

 

6.              I am the co-author of two previous technical reports completed on the Shahuindo property on behalf of Sulliden Gold titled Updated Technical Report on the Shahuindo Project, Cajabamba, Peru, dated 15 October 2012, and Technical Report on the Shahuindo Heap Leach Project, Cajabamba, Peru, dated 09 November 2012.

 

7.     I visited the Shahuindo project site on April 6-8, 2010; May 4-7, 2010; and September 2-3, 2015.

 

8.              At the effective date of this Technical Report, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

9.              I hereby consent to the filing of this Technical Report with any stock exchange and other regulatory authority and any publication by them, including electronic publication in the public company files on their website accessible by the public, of the Technical Report.

 

Dated 25 January 2016

 

/s/ Carl E. Defilippi

 

Carl E. Defilippi, SME Registered Member

 

 

274


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

28.2        Certificate of Qualified Person — Charles V. Muerhoff

 

I, Charles V. Muerhoff, B.Sc., do hereby certify that I am currently employed as Vice President Technical Services for Tahoe Resources Inc., 5310 Kietzke Lane, Reno, Nevada 89511

 

1.              I graduated with a Bachelor of Science Degree in Geology and Geophysics from the University of Missouri-Rolla in 1989. I have practiced my profession continuously since 1990.

 

2.              I am a Registered Member in good standing of the Society for Mining, Metallurgy and Exploration (4182272RM).

 

3.              I have read National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association as defined in NI 43-101 and past relevant work experience, I fulfil the requirements to be a “Qualified Person” for the purposes of NI 43-101.

 

4.              I am not independent of Tahoe Resources Inc. and its related companies, as independence is described in Section 1.5 of NI 43-101.

 

5.              I am one of the authors of this Technical Report titled Technical Report on the Shahuindo Mine, Cajabamba, Peru prepared for Tahoe Resources Inc., with an effective date of 01 January 2016 and dated 25 January 2016. I am responsible for Sections 2, 3, 6, 7, 8, 9, 10, 11, 12, 14, 19, 21, 22, 23 and 24, and the corresponding items in Sections 1, 25 and 26 of this report. This technical report has been prepared in compliance with NI 43-101 and Form 43-101F1.

 

6.              I visited the Shahuindo property May 19-20, 2015 and November 13-14, 2015.

 

7.              At the effective date of this Technical Report, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

8.              I hereby consent to the filing of this Technical Report with any stock exchange and other regulatory authority and any publication by them, including electronic publication in the public company files on their website accessible by the public, of the Technical Report.

 

Dated 25 January 2016

 

/s/ Charles V. Muerhoff

 

Charles V Muerhoff, SME Registered Member

 

 

275


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

28.3 Certificate of Qualified Person — Tim Williams

 

I, Tim Williams, M.Sc., do hereby certify that I am currently employed as Vice President Operations & Peru Country Manager for Tahoe Resources Inc., 5310 Kietzke Lane, Reno, Nevada 89511.

 

1.              I graduated with a Bachelor of Engineering (Geology) degree from Curtin University, Western Australian School of Mines in 1991, a Masters of Engineering Science degree from Curtin University in 2000 and a Graduate Diploma in Mining from Curtin University in 2006. I have practiced my profession continuously since 1991.

 

2.     I am a Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM).

 

3.              I have read National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association as defined in NI 43-101 and past relevant work experience, I fulfil the requirements to be a “Qualified Person” for the purposes of NI 43-101.

 

4.              I am not independent of Tahoe Resources Inc. and its related companies, as independence is described in Section 1.5 of NI 43-101.

 

9.              I am one of the authors of this Technical Report titled Technical Report on the Shahuindo Mine, Cajabamba, Peru prepared for Tahoe Resources Inc., with an effective date of 01 January 2016, and dated 25 January 2016. I am responsible for Sections 4, 5, 15, 16, 18, and 20 and corresponding items in Sections 1, 25 and 26 of this report. This technical report has been prepared in compliance with NI 43-101 and Form 43-101F1.

 

5.              I have visited and worked at the Shahuindo property regularly and on numerous occasions in 2014 and 2015.

 

6.              At the effective date of this Technical Report, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

7.              I hereby consent to the filing of this Technical Report with any stock exchange and other regulatory authority and any publication by them, including electronic publication in the public company files on their website accessible by the public, of the Technical Report.

 

Dated January 25, 2016

 

/s/ Tim Williams

 

Tim Williams, FAusIMM

 

 

276


 

Shahuindo Mine, Peru
NI 43-101 Technical Report

 

APPENDIX

 

POST-RESOURCE DRILL INTERCEPTS

 


 

STEPOUT DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

SHA-D15-003

808,033.1

9,156,523.2

2935.2

-60.0°

35°

235.9

core

99.5

122.5

23.0

n/a

0.25

2.57

 

 

 

 

 

 

 

 

198.1

200.0

1.9

n/a

0.24

1.30

 

 

 

 

 

 

 

 

216.5

220.2

3.7

n/a

0.35

0.99

SHA-D15-004

808,357.6

9,156,461.9

2846.2

-63.4°

36°

260

core

146.5

158.0

11.5

n/a

0.43

1.88

 

 

 

 

 

 

 

 

175.5

177.5

2.0

n/a

0.51

1.70

 

 

 

 

 

 

 

 

235.8

237.0

1.2

n/a

0.26

0.50

 

 

 

 

 

 

 

 

253.0

258.0

5.0

n/a

0.94

1.66

SHA-D15-005

807,932.0

9,156,546.5

2972.2

-60°

43°

200

core

16.7

18.4

1.7

n/a

0.24

0.30

 

 

 

 

 

 

 

 

27.0

28.4

1.4

n/a

0.38

0.10

SHA-D15-006

807,870.5

9,156,659.8

2948.5

-52°

30°

230.1

core

52.4

69.0

16.6

n/a

0.79

10.00

 

 

 

 

 

 

 

including

59.4

63.0

3.6

n/a

2.48

30.28

 

 

 

 

 

 

 

 

83.6

91.7

8.1

n/a

0.28

1.73

 

 

 

 

 

 

 

 

143.6

144.8

1.2

n/a

0.64

0.30

 

 

 

 

 

 

 

 

151.0

157.5

6.5

n/a

0.32

0.99

 

 

 

 

 

 

 

 

161.9

163.4

1.5

n/a

0.41

0.40

 

 

 

 

 

 

 

 

176.7

178.3

1.6

n/a

0.20

0.30

 

 

 

 

 

 

 

 

187.2

191.1

3.9

n/a

0.32

0.63

 

 

 

 

 

 

 

 

215.9

217.0

1.1

n/a

0.37

1.20

SHA-D15-007

807,856.0

9,157,737.0

2842.5

-59°

35°

210.1

core

0.0

32.0

32.0

n/a

0.26

2.11

 

 

 

 

 

 

 

 

38.0

40.0

2.0

n/a

0.26

1.40

 

 

 

 

 

 

 

 

180.3

181.6

1.3

n/a

1.13

15.70

SHA-D15-008

807,932.4

9,157,697.8

2830.6

-61°

35°

239.4

core

0.0

10.0

10.0

n/a

0.25

2.74

 

 

 

 

 

 

 

 

16.0

31.0

15.0

n/a

0.31

2.02

 

 

 

 

 

 

 

 

43.8

45.8

2.0

n/a

0.23

1.40

 

 

 

 

 

 

 

 

203.5

214.2

10.7

n/a

0.50

24.83

SHA-D15-009

807,870.5

9,156,659.8

2948.5

-52°

213°

213.7

core

no significant intercepts

SHA-D15-010

808,020.4

9,157,623.5

2802.3

-56°

30°

260.3

core

24.5

29.1

4.6

n/a

0.26

6.46

 

 

 

 

 

 

 

 

90.0

97.1

7.1

n/a

0.55

5.27

 

 

 

 

 

 

 

 

218.0

222.0

4.0

n/a

0.38

7.50

 

 

 

 

 

 

 

 

232.0

235.5

3.4

n/a

0.37

1.51

SHA-D15-011

807,521.9

9,156,913.1

2974.0

-61°

37°

306.9

core

119.4

121.0

1.6

n/a

0.25

0.10

 

 

 

 

 

 

 

 

174.0

177.5

3.5

n/a

0.28

1.18

 

 

 

 

 

 

 

 

204.0

223.0

19.0

n/a

0.26

1.83

 

 

 

 

 

 

 

 

235.0

306.9

71.9

n/a

0.50

13.49

SHA-D15-012

807,931.6

9,156,630.2

2965.9

-60°

35°

700

core

160.5

162.0

1.5

n/a

0.25

0.10

 

 

 

 

 

 

 

 

169.7

171.0

1.3

n/a

0.31

0.10

 

 

 

 

 

 

 

 

181.0

182.9

1.9

n/a

0.32

1.00

 

 

 

 

 

 

 

 

300.0

302.0

2.0

n/a

0.49

0.60

 

 

 

 

 

 

 

 

421.0

422.0

1.0

n/a

0.22

0.70

 

 

 

 

 

 

 

 

430.0

443.3

13.3

n/a

1.09

0.85

 

 

 

 

 

 

 

including

441.3

443.3

2.0

n/a

4.50

1.10

 

 

 

 

 

 

 

 

462.0

480.0

18.0

n/a

0.72

3.75

 

 

 

 

 

 

 

including

472.0

476.0

4.0

n/a

2.33

7.30

 

 

 

 

 

 

 

 

502.0

509.0

7.0

n/a

0.62

7.17

 

 

 

 

 

 

 

 

520.0

540.9

20.9

n/a

0.34

3.65

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

1


 

STEPOUT DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

 

 

 

 

 

 

 

 

548.0

580.0

32.0

n/a

0.48

2.33

 

 

 

 

 

 

 

 

589.6

608.0

18.4

n/a

0.75

7.36

 

 

 

 

 

 

 

including

589.6

591.0

1.4

n/a

5.6

14.0

SHA-R15-235

807,932.1

9,156,630.7

2965.0

-64°

41°

242

RC

124.0

126.0

2.0

n/a

0.21

1.70

 

 

 

 

 

 

 

 

156.0

158.0

2.0

n/a

0.29

0.40

 

 

 

 

 

 

 

 

166.0

176.0

10.0

n/a

0.22

1.16

 

 

 

 

 

 

 

 

182.0

184.0

2.0

n/a

0.20

0.10

 

 

 

 

 

 

 

 

186.0

188.0

2.0

n/a

0.23

0.10

SHA-R15-236

807,894.6

9,156,563.7

2975.4

-61°

37°

298

RC

24.0

26.0

2.0

n/a

0.52

0.10

 

 

 

 

 

 

 

 

124.0

126.0

2.0

n/a

0.16

0.10

 

 

 

 

 

 

 

 

132.0

134.0

2.0

n/a

0.35

0.30

 

 

 

 

 

 

 

 

144.0

146.0

2.0

n/a

0.44

0.70

SHA-R15-237

807,890.7

9,156,493.2

2980.8

-60°

35°

242

RC

36.0

38.0

2.0

n/a

0.26

0.10

 

 

 

 

 

 

 

 

176.0

182.0

6.0

n/a

0.23

0.90

SHA-R15-238

807,971.7

9,156,597.0

2962.3

-60°

34°

240

RC

40.0

46.0

6.0

n/a

0.24

0.60

 

 

 

 

 

 

 

 

108.0

110.0

2.0

n/a

0.21

2.80

 

 

 

 

 

 

 

 

124.0

126.0

2.0

n/a

0.31

1.40

 

 

 

 

 

 

 

 

134.0

136.0

2.0

n/a

0.21

1.40

 

 

 

 

 

 

 

 

156.0

162.0

6.0

n/a

0.79

0.83

 

 

 

 

 

 

 

 

192.0

194.0

2.0

n/a

0.20

0.80

SHA-R15-239

807,995.2

9,156,550.4

2955.0

-61°

34°

268

RC

122.0

124.0

2.0

n/a

0.20

0.60

 

 

 

 

 

 

 

 

130.0

138.0

8.0

n/a

0.26

1.93

 

 

 

 

 

 

 

 

210.0

212.0

2.0

n/a

0.20

0.50

 

 

 

 

 

 

 

 

220.0

222.0

2.0

n/a

0.25

0.70

 

 

 

 

 

 

 

 

230.0

232.0

2.0

n/a

0.59

1.40

 

 

 

 

 

 

 

 

240.0

242.0

2.0

n/a

0.22

0.50

SHA-R15-240

808,074.2

9,156,549.2

2926.5

-61°

36°

210

RC

88.0

108.0

20.0

n/a

0.66

2.75

 

 

 

 

 

 

 

 

132.0

178.0

46.0

n/a

0.30

1.84

 

 

 

 

 

 

 

 

186.0

194.0

8.0

n/a

0.26

1.45

 

 

 

 

 

 

 

 

204

206

2.0

n/a

0.408

30.9

SHA-R15-241

808,083.5

9,156,490.0

2912.4

-62°

36°

300

RC

88.0

96.0

8.0

n/a

0.23

0.28

 

 

 

 

 

 

 

 

186.0

190.0

4.0

n/a

0.44

0.50

 

 

 

 

 

 

 

 

196.0

198.0

2.0

n/a

0.23

0.10

 

 

 

 

 

 

 

 

210.0

212.0

2.0

n/a

0.38

0.20

SHA-R15-242

808,226.9

9,156,449.3

2872.3

-61°

39°

258

RC

32.0

50.0

18.0

n/a

0.27

1.87

 

 

 

 

 

 

 

 

60.0

72.0

12.0

n/a

0.51

1.03

 

 

 

 

 

 

 

 

78.0

80.0

2.0

n/a

0.22

0.40

 

 

 

 

 

 

 

 

102.0

112.0

10.0

n/a

0.36

0.46

 

 

 

 

 

 

 

 

190.0

218.0

28.0

n/a

0.23

1.06

 

 

 

 

 

 

 

 

228.0

230.0

2.0

n/a

0.39

0.80

 

 

 

 

 

 

 

 

92.0

94.0

2.0

n/a

1.63

0.70

SHA-R15-243

808,297.9

9,156,487.8

2872.7

-59°

25°

230

RC

174.0

188.0

14.0

n/a

0.25

2.11

SHA-R15-244

808,136.0

9,156,396.0

2893.0

-59°

37°

300

RC

no significant intercepts

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

2


 

STEPOUT DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

SHA-R15-245

808,186.0

9,156,463.3

2883.8

-60°

36°

260

RC

52.0

68.0

16.0

n/a

0.23

1.08

 

 

 

 

 

 

 

 

86.0

98.0

12.0

n/a

0.39

0.78

 

 

 

 

 

 

 

 

106.0

116.0

10.0

n/a

0.24

0.74

 

 

 

 

 

 

 

 

196.0

198.0

2.0

n/a

0.20

0.90

 

 

 

 

 

 

 

 

230.0

232.0

2.0

n/a

0.24

1.30

SHA-R15-246

807,970.1

9,156,518.2

2960.3

-60°

55°

272

RC

110.0

114.0

4.0

n/a

0.34

0.30

 

 

 

 

 

 

 

 

214.0

218.0

4.0

n/a

0.21

1.95

SHA-R15-247

807,992.9

9,156,455.4

2952.2

-60°

35°

300

RC

18.0

20.0

2.0

n/a

0.37

0.10

 

 

 

 

 

 

 

 

166.0

168.0

2.0

n/a

0.26

20.10

 

 

 

 

 

 

 

 

172.0

174.0

2.0

n/a

0.22

84.10

 

 

 

 

 

 

 

 

182.0

194.0

12.0

n/a

0.23

21.77

 

 

 

 

 

 

 

 

210.0

212.0

2.0

n/a

0.42

5.10

SHA-R15-248

808,105.3

9,156,457.8

2899.9

-60°

35°

250

RC

104.0

106.0

2.0

n/a

0.54

0.50

 

 

 

 

 

 

 

 

170.0

174.0

4.0

n/a

0.50

1.75

 

 

 

 

 

 

 

 

188.0

196.0

8.0

n/a

0.20

2.63

 

 

 

 

 

 

 

 

202.0

204.0

2.0

n/a

0.24

0.70

SHA-R15-249

807,770.4

9,156,759.9

2914.9

-60°

35°

210

RC

60.0

66.0

6.0

n/a

0.67

4.10

 

 

 

 

 

 

 

 

72.0

76.0

4.0

n/a

0.22

0.75

SHA-R15-250

807,771.6

9,156,762.3

2914.4

-60°

75°

210

RC

102.0

104.0

2.0

n/a

0.20

0.30

 

 

 

 

 

 

 

 

116.0

120.0

4.0

n/a

0.24

0.75

 

 

 

 

 

 

 

 

186.0

190.0

4.0

n/a

1.29

2.05

SHA-R15-251

807,756.7

9,156,808.8

2912.0

-59°

35°

300

RC

94.0

98.0

4.0

n/a

0.26

1.30

 

 

 

 

 

 

 

 

202.0

220.0

18.0

n/a

0.40

6.92

 

 

 

 

 

 

 

 

228.0

300.0

72.0

n/a

0.30

3.36

SHA-R15-252

807,816.4

9,156,797.2

2897.5

-61°

35°

210

RC

46.0

48.0

2.0

n/a

0.36

6.10

 

 

 

 

 

 

 

 

58.0

60.0

2.0

n/a

0.33

1.00

 

 

 

 

 

 

 

 

98.0

102.0

4.0

n/a

0.29

1.30

 

 

 

 

 

 

 

 

108.0

110.0

2.0

n/a

0.22

0.90

 

 

 

 

 

 

 

 

176.0

182.0

6.0

n/a

0.44

6.77

 

 

 

 

 

 

 

 

204.0

208.0

4.0

n/a

0.32

1.30

SHA-R15-254

807,824.0

9,156,819.1

2895.2

-61°

90°

180

RC

50.0

60.0

10.0

n/a

0.26

0.74

 

 

 

 

 

 

 

 

142.0

146.0

4.0

n/a

0.30

0.25

SHA-R15-256

807,520.1

9,157,000.6

2966.0

-61°

35°

246

RC

84.0

88.0

4.0

n/a

1.03

7.45

 

 

 

 

 

 

 

 

136.0

150.0

14.0

n/a

0.20

0.77

 

 

 

 

 

 

 

 

156.0

158.0

2.0

n/a

0.24

0.30

 

 

 

 

 

 

 

 

174.0

176.0

2.0

n/a

0.20

0.70

 

 

 

 

 

 

 

 

192.0

244.0

52.0

n/a

0.55

20.41

SHA-R15-257

807,584.4

9,156,897.8

2955.6

-59°

35°

300

RC

104.0

106.0

2.0

n/a

0.34

0.80

 

 

 

 

 

 

 

 

118.0

120.0

2.0

n/a

0.60

0.10

 

 

 

 

 

 

 

 

216.0

238.0

22.0

n/a

0.22

0.36

 

 

 

 

 

 

 

 

252.0

262.0

10.0

n/a

0.48

42.50

 

 

 

 

 

 

 

 

288.0

290.0

2.0

n/a

0.20

2.50

 

 

 

 

 

 

 

 

294.0

298.0

4.0

n/a

0.32

6.65

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

3


 

STEPOUT DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

SHA-R15-258

807,557.9

9,156,976.5

2953.9

-61°

35°

230

RC

22.0

24.0

2.0

n/a

0.24

2.70

 

 

 

 

 

 

 

 

30.0

36.0

6.0

n/a

0.35

2.57

 

 

 

 

 

 

 

 

44.0

46.0

2.0

n/a

0.25

0.60

 

 

 

 

 

 

 

 

54.0

58.0

4.0

n/a

0.20

0.70

 

 

 

 

 

 

 

 

124.0

126.0

2.0

n/a

0.30

0.40

 

 

 

 

 

 

 

 

168.0

226.0

58.0

n/a

0.39

9.44

SHA-R15-259

807,597.0

9,156,969.3

2948.2

-60°

35°

80

RC

no significant intercepts

SHA-R15-260

807,131.0

9,156,877.0

3025.0

-60°

35°

30

RC

no significant intercepts

SHA-R15-261

807,943.5

9,157,603.9

2828.3

-60°

35°

172

RC

14.0

18.0

4.0

n/a

0.31

0.55

 

 

 

 

 

 

 

 

24.0

30.0

6.0

n/a

0.71

1.10

 

 

 

 

 

 

 

 

40.0

42.0

2.0

n/a

0.30

1.80

 

 

 

 

 

 

 

 

60.0

62.0

2.0

n/a

0.25

0.70

 

 

 

 

 

 

 

 

94.0

98.0

4.0

n/a

0.32

2.90

SHA-R15-262

807,894.3

9,157,624.2

2839.7

-60°

35°

230

RC

10.0

14.0

4.0

n/a

0.21

1.80

SHA-R15-263

807,744.1

9,157,747.2

2845.5

-59°

35°

200

RC

no significant intercepts

SHA-R15-264

807,802.8

9,157,733.5

2848.0

-60°

35°

270

RC

12.0

16.0

4.0

n/a

0.20

2.60

 

 

 

 

 

 

 

 

24.0

26.0

2.0

n/a

1.49

48.30

 

 

 

 

 

 

 

 

66.0

74.0

8.0

n/a

0.36

2.53

 

 

 

 

 

 

 

 

80.0

84.0

4.0

n/a

0.54

1.65

 

 

 

 

 

 

 

 

92.0

178.0

86.0

n/a

0.59

2.76

 

 

 

 

 

 

 

 

234.0

238.0

4.0

n/a

0.36

4.30

SHA-R15-265

807,520.5

9,157,663.4

2866.8

-60°

35°

200

RC

0.0

2.0

2.0

n/a

0.25

2.10

 

 

 

 

 

 

 

 

10.0

12.0

2.0

n/a

0.23

1.30

 

 

 

 

 

 

 

 

28.0

54.0

26.0

n/a

0.32

2.88

SHA-R15-266

807,597.4

9,157,696.9

2860.9

-59°

35°

168

RC

no significant intercepts

SHA-R15-267

807,662.1

9,157,719.1

2858.0

-60°

35°

200

RC

no significant intercepts

SHA-R15-268

807,672.5

9,157,678.6

2871.3

-61°

35°

200

RC

no significant intercepts

SHA-R15-269

807,981.6

9,157,666.9

2809.2

-60°

35°

218

RC

no significant intercepts

SHA-R15-270

808,038.7

9,156,603.8

2942.2

-62°

35°

204

RC

8.0

10.0

2.0

n/a

0.21

0.20

 

 

 

 

 

 

 

 

170.0

172.0

2.0

n/a

0.25

0.90

SHA-R15-271

807,729.0

9,156,880.4

2913.9

-61°

35°

240

RC

166.0

168.0

2.0

n/a

0.20

0.10

SHA-R15-272

807,130.8

9,156,883.0

3024.7

-60°

35°

300

RC

194.0

196.0

2.0

n/a

0.29

3.30

 

 

 

 

 

 

 

 

218.0

220.0

2.0

n/a

0.38

8.30

 

 

 

 

 

 

 

 

234.0

236.0

2.0

n/a

0.31

2.70

SHA-R15-273

807,186.1

9,156,867.8

3016.7

-59°

35°

270

RC

no significant intercepts

SHA-R15-274

807,148.5

9,157,010.8

3030.9

-60°

35°

284

RC

162.0

164.0

2.0

n/a

0.27

18.20

 

 

 

 

 

 

 

 

190.0

192.0

2.0

n/a

0.23

0.60

SHA-R15-287

807,548.8

9,157,739.5

2858.9

-62°

35°

180

RC

no significant intercepts

SHA-R15-288

807,435.2

9,157,819.9

2898.0

-59°

35°

184

RC

no significant intercepts

SHA-D15-001S

809,501.3

9,156,274.2

2552.4

-60°

32°

202.2

core

2.2

4.3

2.1

n/a

0.25

6.00

 

 

 

 

 

 

 

 

62.0

69.0

7.0

n/a

1.20

12.57

 

 

 

 

 

 

 

including

67.2

69.0

1.8

n/a

3.48

4.70

SHA-D15-003S

809,137.5

9,156,153.6

2697.9

-60°

35°

155.2

core

0.0

24.3

24.3

n/a

0.79

1.85

 

 

 

 

 

 

 

 

42.0

50.0

8.0

n/a

0.35

4.15

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

 

4


 

STEPOUT DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length

(m)

Est True Width

(m)

Au g/t

Ag g/t

SHA-D15-009S

808,756.3

9,156,768.9

2795.3

-61

216

200.2

core

166.9

168.9

 

n/a

0.21

0.90

 

 

 

 

 

 

 

 

175.8

176.3

0.5

n/a

0.27

3.30

 

 

 

 

 

 

 

 

185.7

200.2

14.5

n/a

0.29

5.59

SHA-D15-010S

808,981.2

9,156,403.9

2735.7

-61

34

200

core

108.9

113.6

4.7

n/a

0.44

0.56

 

 

 

 

 

 

 

 

150.1

159.9

9.8

n/a

0.44

1.79

 

 

 

 

 

 

 

 

173.9

175.5

1.6

n/a

0.20

0.70

 

 

 

 

 

 

 

 

192.1

200.0

7.9

n/a

0.41

1.78

SHA-D15-011S

808,840.6

9,156,715.5

2771.9

-61

213

200.2

core

92.5

100.5

8.0

n/a

0.16

1.14

 

 

 

 

 

 

 

 

140.1

141.9

1.8

n/a

0.23

0.70

 

 

 

 

 

 

 

 

154.7

156.7

2.0

n/a

0.24

2.40

 

 

 

 

 

 

 

 

167.0

200.2

33.2

n/a

0.42

2.55

SHA-D15-012S

808,597.0

9,156,535.8

2796.3

-61

31

203.5

core

50.0

52.0

2.0

n/a

0.29

4.20

 

 

 

 

 

 

 

 

186.2

191.2

5.0

n/a

0.27

0.87

 

 

 

 

 

 

 

 

197.0

202.0

5.0

n/a

0.23

0.88

SHA-D15-013S

808,442.2

9,156,566.5

2835.1

-62

33

200

core

95.9

97.6

1.7

n/a

0.38

7.30

SHA-D15-017S

808,969.8

9,156,117.0

2725.1

-60

36

200

core

12.7

32.2

19.5

n/a

0.70

10.88

 

 

 

 

 

 

 

including

22.8

26.5

3.7

n/a

2.53

50.78

 

 

 

 

 

 

 

 

70.4

90.8

20.4

n/a

0.20

0.99

SHA-D15-018S

808,890.1

9,156,184.4

2707.8

-60

35

200.5

core

54.0

61.6

7.6

n/a

0.27

0.71

SHA-D15-019S

809,232.9

9,156,407.7

2667.7

-62

37

200.7

core

31.3

36.0

4.7

n/a

0.33

0.21

 

 

 

 

 

 

 

 

47.5

58.2

10.7

n/a

1.00

8.73

 

 

 

 

 

 

 

including

47.5

49.0

1.5

n/a

3.05

6.00

SHA-R15-299

808,348.9

9,156,337.3

2834.7

-60

35

200

RC

182.0

188.0

6.0

n/a

1.26

29.47

 

 

 

 

 

 

 

including

182.0

184.0

2.0

n/a

3.38

84.30

SHA-R15-301

808,646.6

9,155,975.6

2827.9

-60

35

96

RC

50.0

56.0

6.0

n/a

0.29

1.53

SHA-R15-304

808,229.9

9,156,329.0

2868.5

-61

35

156

RC

6.0

22.0

16.0

n/a

0.37

0.24

 

 

 

 

 

 

 

 

94.0

96.0

2.0

n/a

1.03

45.20

 

 

 

 

 

 

 

 

144.0

154.0

10.0

n/a

0.24

0.60

SHA-R15-328

809,015.5

9,156,085.3

2714.4

-62

35

100

RC

26.0

32.0

6.0

n/a

0.27

1.20

 

 

 

 

 

 

 

 

40.0

42.0

2.0

n/a

0.21

1.00

 

 

 

 

 

 

 

 

52.0

66.0

14.0

n/a

0.37

1.90

SHA-R15-329

808,993.9

9,156,093.8

2714.2

-61

35

100

RC

48.0

52.0

4.0

n/a

0.30

0.70

SHA-R15-330

809,055.1

9,156,170.9

2684.8

-61

35

84

RC

8.0

10.0

2.0

n/a

2.99

52.40

 

 

 

 

 

 

 

 

22.0

38.0

16.0

n/a

0.40

5.55

SHA-R15-333

809,103.3

9,156,167.9

2686.0

-60

35

96

RC

26.0

34.0

8.0

n/a

0.24

1.88

SHA-R15-334

809,122.8

9,156,126.0

2695.7

-60

35

70

RC

2.0

14.0

12.0

n/a

0.56

1.90

 

 

 

 

 

 

 

 

30.0

32.0

2.0

n/a

0.48

0.90

 

 

 

 

 

 

 

 

46.0

58.0

12.0

n/a

0.50

1.13

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

5


 

CONDEMNATION DRILLING - SOUTHEAST EXTENSION

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

SHA-D15-001S

809,501.3

9,156,274.2

2552.4

-60°

32°

202.2

core

2.2

4.3

2.1

1.8

0.25

6.00

 

 

 

 

 

 

 

 

62.0

69.0

7.0

n/a

1.20

12.57

 

 

 

 

 

 

 

including

67.2

69.0

1.8

n/a

3.48

4.70

SHA-D15-003S

809,137.5

9,156,153.6

2697.9

-60°

35°

155.2

core

0.0

24.3

24.3

21.0

0.79

1.85

 

 

 

 

 

 

 

 

42.0

50.0

8.0

n/a

0.35

4.15

SHA-D15-009S

808,756.3

9,156,768.9

2795.3

-61°

216°

200.2

core

166.9

168.9

2.0

n/a

0.21

0.90

 

 

 

 

 

 

 

 

175.8

176.3

0.5

n/a

0.27

3.30

 

 

 

 

 

 

 

 

185.7

200.2

14.5

n/a

0.29

5.59

SHA-D15-010S

808,981.2

9,156,403.9

2735.7

-61°

34°

200

core

108.9

113.6

4.7

n/a

0.44

0.56

 

 

 

 

 

 

 

 

150.1

159.9

9.8

n/a

0.44

1.79

 

 

 

 

 

 

 

 

173.9

175.5

1.6

n/a

0.20

0.70

 

 

 

 

 

 

 

 

192.1

200.0

7.9

n/a

0.41

1.78

SHA-D15-011S

808,840.6

9,156,715.5

2771.9

-61°

213°

200.2

core

92.5

94.0

1.5

n/a

0.20

2.20

 

 

 

 

 

 

 

 

95.3

97.0

1.7

n/a

0.28

1.00

 

 

 

 

 

 

 

 

99.0

100.5

1.5

n/a

0.21

0.40

 

 

 

 

 

 

 

 

140.1

141.9

1.8

n/a

0.23

0.70

 

 

 

 

 

 

 

 

154.7

156.7

2.0

n/a

0.24

2.40

 

 

 

 

 

 

 

 

167.0

200.2

33.2

n/a

0.42

2.55

SHA-D15-012S

808,597.0

9,156,535.8

2796.3

-61°

31°

203.5

core

50.0

52.0

2.0

n/a

0.29

4.20

 

 

 

 

 

 

 

 

186.2

191.2

5.0

n/a

0.27

0.87

 

 

 

 

 

 

 

 

197.0

202.0

5.0

n/a

0.23

0.88

SHA-D15-013S

808,442.2

9,156,566.5

2835.1

-62°

33°

200

core

95.9

97.6

1.7

n/a

0.38

7.30

SHA-D15-017S

808,969.8

9,156,117.0

2725.1

-60°

36°

200

core

12.7

32.2

19.5

n/a

0.70

10.88

 

 

 

 

 

 

 

including

22.8

26.5

3.7

n/a

2.53

50.78

 

 

 

 

 

 

 

 

70.4

72.4

2.0

n/a

0.33

0.90

 

 

 

 

 

 

 

 

77.6

90.8

13.2

n/a

0.22

1.02

SHA-D15-018S

808,890.1

9,156,184.4

2707.8

-59°

35°

200.5

core

52.0

55.5

3.5

n/a

0.37

0.51

 

 

 

 

 

 

 

 

60.0

61.6

1.6

n/a

0.45

1.00

SHA-D15-019S

809,232.9

9,156,407.7

2667.7

-62°

37°

200.7

core

31.3

36.0

4.7

n/a

0.33

0.21

 

 

 

 

 

 

 

 

47.5

58.2

10.7

n/a

1.00

8.73

 

 

 

 

 

 

 

including

47.5

49.0

1.5

n/a

3.05

6.00

SHA-R15-299

808,348.9

9,156,337.3

2834.7

-60°

35°

200

RC

182.0

188.0

6.0

n/a

1.26

29.47

 

 

 

 

 

 

 

including

182.0

184.0

2.0

n/a

3.38

84.30

SHA-R15-301

808,646.6

9,155,975.6

2827.9

-60°

35°

96

RC

50.0

56.0

6.0

n/a

0.29

1.53

SHA-R15-304

808,229.9

9,156,329.0

2868.5

-61°

35°

156

RC

6.0

22.0

16.0

9.2

0.37

0.24

 

 

 

 

 

 

 

 

94.0

96.0

2.0

n/a

1.03

45.20

 

 

 

 

 

 

 

 

144.0

154.0

10.0

n/a

0.24

0.60

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

6


 

CONDEMNATION DRILLING - EL SAUCE

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

SHA-R15-292

809,121.5

9,156,052.1

2739.2

-59°

35°

102

RC

18.0

20.0

2.0

n/a

0.56

0.10

 

 

 

 

 

 

 

 

38.0

42.0

4.0

n/a

0.88

0.10

 

 

 

 

 

 

 

 

52.0

54.0

2.0

n/a

0.41

1.30

 

 

 

 

 

 

 

 

78.0

80.0

2.0

n/a

0.69

6.60

SHA-R15-293

809,212.5

9,156,074.3

2700.1

-62°

36°

76

RC

0.0

4.0

4.0

1.9

0.45

0.20

SHA-R15-294

808,917.3

9,156,033.9

2761.9

-61°

35°

78

RC

20.0

22.0

2.0

n/a

0.26

0.50

SHA-R15-295

809,184.6

9,156,125.1

2699.1

-60°

35°

78

RC

0.0

4.0

4.0

3.5

0.26

1.15

 

 

 

 

 

 

 

 

32.0

64.0

32.0

n/a

1.49

6.10

 

 

 

 

 

 

 

including

32.0

38.0

6.0

n/a

5.73

25.33

SHA-R15-297

809,057.4

9,156,093.8

2725.3

-60°

35°

78

RC

56.0

64.0

8.0

n/a

0.27

1.60

 

 

 

 

 

 

 

 

74.0

78.0

4.0

n/a

0.20

1.25

SHA-R15-328

809,015.5

9,156,085.3

2714.4

-61°

35°

100

RC

26.0

32.0

6.0

n/a

0.27

1.20

 

 

 

 

 

 

 

 

40.0

42.0

2.0

n/a

0.21

1.00

 

 

 

 

 

 

 

 

52.0

54.0

2.0

n/a

0.34

1.50

 

 

 

 

 

 

 

 

58.0

66.0

8.0

n/a

0.50

2.65

SHA-R15-329

808,993.9

9,156,093.8

2714.2

-62°

35°

100

RC

48.0

52.0

4.0

n/a

0.30

0.70

SHA-R15-330

809,055.1

9,156,170.9

2684.8

-61°

35°

84

RC

8.0

10.0

2.0

n/a

2.99

52.40

 

 

 

 

 

 

 

 

22.0

38.0

16.0

n/a

0.40

5.55

 

 

 

 

 

 

 

 

26.0

34.0

8.0

n/a

0.24

1.88

SHA-R15-334

809,122.8

9,156,126.0

2695.7

-59.58°

35°

70

RC

2.0

14.0

12.0

6.9

0.56

1.90

 

 

 

 

 

 

 

 

30.0

32.0

2.0

n/a

0.48

0.90

 

 

 

 

 

 

 

 

46.0

58.0

12.0

n/a

0.50

1.13

SHA-R15-335

809,173.9

9,156,156.2

2697.9

-60°

35°

70

RC

0.0

18.0

18.0

15.6

0.58

2.00

 

 

 

 

 

 

 

 

44.0

50.0

6.0

n/a

0.38

1.17

SHA-R15-336

809,199.6

9,156,138.5

2695.3

-60°

35°

70

RC

0.0

6.0

6.0

5.2

0.25

0.73

 

 

 

 

 

 

 

 

12.0

26.0

14.0

n/a

0.56

1.63

 

 

 

 

 

 

 

 

44.0

54.0

10.0

n/a

1.26

1.76

 

 

 

 

 

 

 

including

48.0

50.0

2.0

n/a

3.45

3.10

SHA-R15-337

809,208.3

9,156,108.8

2696.2

-60°

35°

84

RC

42.0

58.0

16.0

n/a

1.28

4.44

SHA-R15-338

809,157.6

9,156,133.6

2702.6

-61°

35°

70

RC

0.0

12.0

12.0

10.5

0.50

2.43

 

 

 

 

 

 

 

 

24.0

26.0

2.0

n/a

0.55

0.80

 

 

 

 

 

 

 

 

34.0

62.0

28.0

n/a

0.79

2.61

 

 

 

 

 

 

 

including

36.0

38.0

2.0

n/a

3.24

9.90

SHA-R15-339

809,174.6

9,156,097.7

2707.7

-60°

35°

120

RC

10.0

24.0

14.0

n/a

0.46

2.23

SHA-R15-340

809,136.2

9,156,070.6

2734.8

-60°

35°

132

RC

16.0

18.0

2.0

n/a

0.22

0.10

 

 

 

 

 

 

 

 

54.0

68.0

14.0

n/a

1.58

1.63

 

 

 

 

 

 

 

including

56.0

60.0

4.0

n/a

4.48

1.50

SHA-R15-341

809,076.6

9,156,084.5

2728.5

-62°

35°

120

RC

16.0

22.0

6.0

n/a

0.51

0.97

 

 

 

 

 

 

 

 

42.0

70.0

28.0

n/a

0.27

5.91

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

7


 

SAN LORENZO DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

SHA-D15-019

807,965.0

9,157,899.2

2824.3

-61°

270°

221.3

core

20.0

22.0

2.0

1.0

0.29

3.60

 

 

 

 

 

 

 

 

32.5

46.9

14.4

7.2

0.30

6.75

 

 

 

 

 

 

 

 

76.0

78.0

2.0

1.0

0.31

8.20

 

 

 

 

 

 

 

 

131.5

133.5

2.0

1.0

0.69

20.50

 

 

 

 

 

 

 

 

138.0

140.0

2.0

1.0

0.25

3.20

 

 

 

 

 

 

 

 

156.4

167.1

10.7

5.3

0.93

1.87

 

 

 

 

 

 

 

including

156.4

157.8

1.4

0.7

5.93

9.10

 

 

 

 

 

 

 

 

197.5

198.7

1.2

0.6

0.20

3.40

SHA-D15-020

807,792.1

9,157,949.1

2840.3

-61°

90°

200.8

core

18.0

20.0

2.0

1.0

0.21

1.80

 

 

 

 

 

 

 

 

31.0

36.0

5.0

2.5

0.32

2.30

 

 

 

 

 

 

 

 

50.0

56.9

6.9

3.4

0.70

1.30

 

 

 

 

 

 

 

 

105.0

107.0

2.0

1.0

0.72

17.10

 

 

 

 

 

 

 

 

113.9

117.2

3.3

1.7

4.30

6.00

 

 

 

 

 

 

 

 

129.6

133.6

4.0

2.0

1.61

12.10

 

 

 

 

 

 

 

 

142.5

153.0

10.5

5.3

0.96

5.54

SHA-R15-275

807,643.4

9,157,867.4

2848.1

-60°

35°

212

RC

2.0

4.0

2.0

1.0

0.18

1.00

 

 

 

 

 

 

 

 

40.0

56.0

16.0

8.0

0.22

0.86

 

 

 

 

 

 

 

 

60.0

62.0

2.0

1.0

0.23

0.60

SHA-R15-276

807,794.6

9,158,054.2

2889.6

-60°

300°

200

RC

6.0

8.0

2.0

1.0

0.21

1.00

 

 

 

 

 

 

 

 

68.0

70.0

2.0

1.0

0.25

0.60

 

 

 

 

 

 

 

 

146.0

148.0

2.0

1.0

0.20

0.70

SHA-R15-277

807,793.6

9,157,997.1

2867.4

-60°

120°

180

RC

12.0

14.0

2.0

1.0

0.29

1.10

 

 

 

 

 

 

 

 

28.0

32.0

4.0

2.0

0.34

2.05

 

 

 

 

 

 

 

 

64.0

70.0

6.0

3.0

0.21

0.70

 

 

 

 

 

 

 

 

80.0

90.0

10.0

5.0

0.48

2.44

SHA-R15-278

807,852.4

9,158,053.1

2874.7

-59°

300°

200

RC

4.0

6.0

2.0

1.0

0.41

2.20

SHA-R15-279

807,853.4

9,157,992.6

2871.8

-59°

120°

250

RC

12.0

50.0

38.0

19.0

0.58

6.05

 

 

 

 

 

 

 

 

56.0

58.0

2.0

1.0

0.21

3.00

 

 

 

 

 

 

 

 

62.0

82.0

20.0

10.0

0.40

3.12

 

 

 

 

 

 

 

 

90.0

96.0

6.0

3.0

0.25

4.13

 

 

 

 

 

 

 

 

100.0

106.0

6.0

3.0

0.56

2.43

 

 

 

 

 

 

 

 

120.0

138.0

18.0

9.0

0.69

7.17

 

 

 

 

 

 

 

 

152.0

156.0

4.0

2.0

7.13

22.25

 

 

 

 

 

 

 

 

180.0

212.0

32.0

16.0

0.51

3.87

 

 

 

 

 

 

 

including

194.0

196.0

2.0

1.0

3.19

11.20

 

 

 

 

 

 

 

 

216.0

226.0

10.0

5.0

0.22

1.24

 

 

 

 

 

 

 

 

234.0

238.0

4.0

2.0

0.21

1.70

SHA-R15-280

807,894.2

9,157,944.6

2848.3

-62°

120°

200

RC

0.0

8.0

8.0

4.0

0.89

3.78

 

 

 

 

 

 

 

 

18.0

22.0

4.0

2.0

0.38

10.45

 

 

 

 

 

 

 

 

28.0

38.0

10.0

5.0

0.34

3.42

 

 

 

 

 

 

 

 

46.0

50.0

4.0

2.0

0.38

10.55

 

 

 

 

 

 

 

 

94.0

96.0

2.0

1.0

0.22

1.90

 

 

 

 

 

 

 

 

98.0

100.0

2.0

1.0

0.22

4.10

 

 

 

 

 

 

 

 

120.0

122.0

2.0

1.0

0.23

2.70

 

 

 

 

 

 

 

 

162.0

168.0

6.0

3.0

0.85

15.07

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

8


 

SAN LORENZO DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

SHA-R15-281

807,972.8

9,158,052.6

2835.4

-59°

300°

180

RC

34.0

36.0

2.0

1.0

0.59

2.50

 

 

 

 

 

 

 

 

46.0

74.0

28.0

14.0

0.98

2.88

 

 

 

 

 

 

 

including

60.0

62.0

2.0

1.0

9.13

6.50

 

 

 

 

 

 

 

 

120.0

122.0

2.0

1.0

0.20

0.50

SHA-R15-282

807,920.9

9,157,898.7

2831.8

-60°

120°

200

RC

10.0

12.0

2.0

1.0

0.28

13.30

 

 

 

 

 

 

 

 

16.0

58.0

42.0

21.0

0.45

11.02

 

 

 

 

 

 

 

 

186.0

190.0

4.0

2.0

0.44

1.90

SHA-R15-283

807,833.0

9,157,911.5

2833.6

-60°

120°

224

RC

4.0

6.0

2.0

1.0

0.28

1.50

 

 

 

 

 

 

 

 

16.0

48.0

32.0

16.0

0.42

3.79

 

 

 

 

 

 

 

 

54.0

60.0

6.0

3.0

0.29

9.40

 

 

 

 

 

 

 

 

80.0

82.0

2.0

1.0

1.36

3.90

 

 

 

 

 

 

 

 

134.0

138.0

4.0

2.0

0.53

36.05

 

 

 

 

 

 

 

 

144.0

146.0

2.0

1.0

0.20

5.90

 

 

 

 

 

 

 

 

160.0

162.0

2.0

1.0

0.20

1.40

 

 

 

 

 

 

 

 

176.0

186.0

10.0

5.0

0.26

4.74

SHA-R15-284

807,939.9

9,157,991.8

2840.1

-61°

300°

150

RC

14.0

16.0

2.0

1.0

0.21

8.20

 

 

 

 

 

 

 

 

24.0

70.0

46.0

23.0

1.11

3.36

 

 

 

 

 

 

 

including

54.0

56.0

2.0

1.0

2.87

4.10

 

 

 

 

 

 

 

including

60.0

66.0

6.0

3.0

3.89

2.27

 

 

 

 

 

 

 

 

84.0

86.0

2.0

1.0

0.21

2.10

SHA-R15-285

807,693.9

9,157,845.7

2833.7

-61°

35°

180

RC

72.0

76.0

4.0

2.0

0.28

5.10

SHA-R15-286

807,985.8

9,157,946.7

2821.7

-60°

300°

180

RC

36.0

42.0

6.0

3.0

0.64

21.30

 

 

 

 

 

 

 

 

62.0

64.0

2.0

1.0

0.22

2.30

 

 

 

 

 

 

 

 

66.0

68.0

2.0

1.0

0.28

1.00

 

 

 

 

 

 

 

 

78.0

80.0

2.0

1.0

0.39

2.20

 

 

 

 

 

 

 

 

154.0

166.0

12.0

6.0

3.84

6.38

 

 

 

 

 

 

 

including

160.0

164.0

4.0

2.0

10.97

15.10

SHA-R15-326

808,037.9

9,157,793.0

2788.3

-66°

125°

300

RC

164.0

166.0

2.0

1.0

0.22

2.50

 

 

 

 

 

 

 

 

174.0

182.0

8.0

4.0

0.24

100.48

SHA-R15-331

808,037.1

9,157,793.3

2788.2

-61°

300°

220

RC

56.0

58.0

2.0

1.0

0.37

2.40

 

 

 

 

 

 

 

 

76.0

78.0

2.0

1.0

0.91

1.80

SHA-R15-342

807,792.8

9,157,998.8

2868.3

-61°

300°

120

RC

22.0

24.0

2.0

1.0

0.93

0.90

 

 

 

 

 

 

 

 

64.0

66.0

2.0

1.0

0.21

3.50

SHA-R15-343

807,800.2

9,158,052.5

2889.6

-61°

120°

120

RC

60.0

62.0

2.0

1.0

0.58

0.10

 

 

 

 

 

 

 

 

68.0

72.0

4.0

2.0

0.50

1.65

 

 

 

 

 

 

 

 

110.0

116.0

6.0

3.0

0.41

1.10

SHA-R15-344

807,876.0

9,158,102.9

2885.4

-60°

120°

120

RC

72.0

76.0

4.0

2.0

0.47

1.15

 

 

 

 

 

 

 

 

100.0

104.0

4.0

2.0

0.23

1.60

SHA-R15-345

807,853.6

9,158,051.2

2875.3

-60°

120°

120

RC

68.0

70.0

2.0

1.0

0.40

0.90

 

 

 

 

 

 

 

 

86.0

92.0

6.0

3.0

1.04

9.33

 

 

 

 

 

 

 

 

118.0

120.0

2.0

1.0

0.44

0.30

SHA-R15-346

807,840.1

9,158,027.5

2877.2

-60°

120°

120

RC

4.0

10.0

6.0

3.0

0.47

0.97

 

 

 

 

 

 

 

 

22.0

24.0

2.0

1.0

0.30

2.80

 

 

 

 

 

 

 

 

60.0

64.0

4.0

2.0

0.56

4.30

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

9


 

SAN LORENZO DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length

(m)

Est True Width

(m)

Au g/t

Ag g/t

SHA-R15-346

807,840.1

9,158,027.5

2877.2

-60°

120°

120

RC

70.0

72.0

2.0

1.0

0.20

1.80

(continued)

 

 

 

 

 

 

 

94.0

96.0

2.0

1.0

0.30

2.30

 

 

 

 

 

 

 

 

108.0

110.0

2.0

1.0

0.21

1.10

 

 

 

 

 

 

 

 

114.0

130.0

16.0

8.0

0.40

1.66

SHA-R15-347

807,933.4

9,158,133.5

2856.0

-61°

120°

120

RC

36.0

44.0

8.0

4.0

0.20

1.08

 

 

 

 

 

 

 

 

50.0

80.0

30.0

15.0

1.07

3.08

 

 

 

 

 

 

 

including

52.0

54.0

2.0

1.0

2.82

2.20

 

 

 

 

 

 

 

including

74.0

78.0

4.0

2.0

2.74

6.60

 

 

 

 

 

 

 

 

140.0

142.0

2.0

1.0

0.21

0.80

SHA-R15-348

807,900.7

9,157,995.4

2855.6

-61°

120°

120

RC

6.0

72.0

66.0

33.0

2.62

27.49

 

 

 

 

 

 

 

including

14.0

20.0

6.0

3.0

21.36

182.87

 

 

 

 

 

 

 

 

84.0

86.0

2.0

1.0

0.50

5.00

SHA-R15-349

807,882.0

9,157,921.0

2842.0

-60°

120°

120

RC

0.0

34.0

34.0

17.0

0.61

6.94

 

 

 

 

 

 

 

 

46.0

48.0

2.0

1.0

0.37

4.90

 

 

 

 

 

 

 

 

90.0

92.0

2.0

1.0

0.25

5.30

SHA-R15-350

808,000.0

9,158,000.0

2821.0

-61°

300°

120

RC

8.0

10.0

2.0

1.0

0.61

1.10

 

 

 

 

 

 

 

 

26.0

28.0

2.0

1.0

0.33

1.50

 

 

 

 

 

 

 

 

34.0

44.0

10.0

5.0

0.39

1.74

 

 

 

 

 

 

 

 

56.0

58.0

2.0

1.0

0.69

6.80

 

 

 

 

 

 

 

 

74.0

76.0

2.0

1.0

0.23

1.20

 

 

 

 

 

 

 

 

102.0

106.0

4.0

2.0

0.50

8.60

SHA-R15-351

807,902.0

9,158,052.0

2859.0

-61°

120°

120

RC

24.0

26.0

2.0

1.0

0.74

11.30

 

 

 

 

 

 

 

 

38.0

46.0

8.0

4.0

0.23

0.90

 

 

 

 

 

 

 

 

64.0

90.0

26.0

13.0

2.54

8.54

 

 

 

 

 

 

 

including

68.0

76.0

8.0

4.0

4.64

19.73

 

 

 

 

 

 

 

including

86.0

90.0

4.0

2.0

3.19

3.75

 

 

 

 

 

 

 

 

100.0

102.0

2.0

1.0

0.20

1.70

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

10


 

CHOLOQUE DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

SHA-D15-021

808,333.1

9,157,947.0

2774.5

-61°

270°

300

core

129.9

131.4

1.5

0.8

0.35

4.20

SHA-R15-305

808,320.0

9,157,900.0

2777.0

-60°

270°

270

RC

32.0

34.0

2.0

1.0

0.20

52.40

 

 

 

 

 

 

 

 

116.0

118.0

2.0

1.0

0.26

5.90

 

 

 

 

 

 

 

 

150.0

156.0

6.0

3.0

0.28

4.03

 

 

 

 

 

 

 

 

258.0

260.0

2.0

1.0

0.20

3.40

SHA-R15-306

808,232.0

9,157,749.0

2821.0

-60°

270°

234

RC

26.0

28.0

2.0

1.0

0.23

13.40

 

 

 

 

 

 

 

 

42.0

44.0

2.0

1.0

0.20

5.40

 

 

 

 

 

 

 

 

150.0

154.0

4.0

2.0

0.25

34.35

 

 

 

 

 

 

 

 

168.0

194.0

26.0

13.0

4.02

18.58

 

 

 

 

 

 

 

including

172.0

178.0

6.0

3.0

14.55

48.70

 

 

 

 

 

 

 

 

224.0

234.0

10.0

5.0

8.42

102.22

 

 

 

 

 

 

 

including

232.0

234.0

2.0

1.0

41.43

486.00

SHA-R15-327

808,199.6

9,157,646.3

2838.4

-60°

270°

300

RC

140.0

176.0

36.0

18.0

2.27

53.54

 

 

 

 

 

 

 

including

150.0

152.0

2.0

1.0

26.91

344.00

 

 

 

 

 

 

 

including

160.0

164.0

4.0

2.0

4.02

83.70

 

 

 

 

 

 

 

 

226.0

228.0

2.0

1.0

0.45

13.80

 

 

 

 

 

 

 

 

244.0

260.0

16.0

8.0

2.89

98.84

 

 

 

 

 

 

 

including

244.0

252.0

8.0

4.0

5.43

116.48

 

 

 

 

 

 

 

including

244.0

246.0

2.0

1.0

18.07

413.00

 

 

 

 

 

 

 

 

294.0

296.0

2.0

1.0

0.24

12.10

SHA-R15-332

808,271.3

9,157,825.7

2801.1

-62°

270°

262

RC

4.0

6.0

2.0

1.0

0.40

0.30

 

 

 

 

 

 

 

 

12.0

14.0

2.0

1.0

0.20

1.90

 

 

 

 

 

 

 

 

146.0

152.0

6.0

3.0

0.58

6.40

 

 

 

 

 

 

 

 

178.0

182.0

4.0

2.0

0.22

3.10

 

 

 

 

 

 

 

 

218.0

220.0

2.0

1.0

0.57

12.70

 

LA CHILCA DRILLING

 

Hole ID

Easting

Northing

Elevation

Inclination

Azimuth

Depth (m)

Drill Type

From (m)

To (m)

Drilled Length
(m)

Est True Width
(m)

Au g/t

Ag g/t

SHA-D15-022

806,220.0

9,158,278.0

3054.0

-61°

305°

100

core

8.0

19.5

11.5

n/a

0.32

3.22

SHA-D15-023

806,235.0

9,158,348.0

3039.0

-59°

305°

150

core

4.0

73.4

69.4

n/a

1.36

13.64

 

 

 

 

 

 

 

including

26.0

35.9

9.9

n/a

7.13

64.16

SHA-D15-024

806,235.0

9,158,348.0

3039.0

-61°

100

core

0.0

54.0

54.0

n/a

1.26

5.80

 

 

 

 

 

 

 

including

18.0

24.5

6.5

n/a

6.65

3.64

 

 

 

 

 

 

 

 

57.0

62.0

5.0

n/a

0.20

3.22

 

drill interval composites reported using 0.2 g/t Au Cut-off

 

11