Note 15.  Commitments and Contingencies

We are involved in certain contractual disputes in the ordinary course of business. We do not believe the ultimate resolution of any of these existing matters will have a material adverse effect on our financial position, results of operations or cash flows.

In August 2010, we were awarded a National Telecommunications Information Administration (NTIA) Broadband Technology Opportunities Program (BTOP) grant to extend our middle mile fiber-optic network across greater Minnesota connecting health care facilities, schools, libraries, higher education institutions and public offices with an advanced high-capacity broadband network. This project involves approximately $24,000,000 of capital expenditures of which $16,800,000 is funded by the NTIA grant. We began capitalizing costs associated with this project in 2010 and began receiving grant funds in June 2011. The table below provides an overview of the capital expenditures incurred on this project along with reimbursements pending or received from the program.

   
Project Activity
    
(Dollars in thousands) 
YTD March 31, 2012
  
YTD December 31, 2011
  
Project Total
 
Capital Expenditures Incurred
 $383  $12,664  $13,047 
Capital Expenditures Pending Reimbursement
 $867  $-  $867 
NTIA Reimbursements Received
 $1,321  $6,945  $8,266 

We anticipate the completion of this project by August 2013.