Future minimum payments for commitments as of December 31, 2021 (in millions):
 
Aircraft Commitments(a)
Capacity Purchase Agreements(b)
2022$1,339 $173 
20231,686 178 
2024389 183 
202579 188 
202613 189 
Thereafter— 688 
Total$3,506 $1,599 
(a)Includes non-cancelable contractual commitments for aircraft and engines, aircraft maintenance and parts management.
(b)Includes all non-aircraft lease costs associated with capacity purchase agreements.

Aircraft Commitments
 
Aircraft purchase commitments include non-cancelable contractual commitments for aircrafts and engines. As of December 31, 2021, Alaska had commitments to purchase 74 Boeing 737-9 aircraft with deliveries in 2022 through 2024. Horizon also has commitments to purchase seven E175 aircraft with deliveries in 2023 through 2025. Subsequent to December 31, 2021, Horizon added an additional five commitments with deliveries in 2022 and 2023. Alaska has options to purchase 52 737-9 aircraft and Horizon has options to purchase 15 E175 aircraft. Option payments are not reflected in the table above.
Aircraft Maintenance and Parts Management

Through its acquisition of Virgin America, the Company has a separate maintenance-cost-per-hour contract for management and repair of certain rotable parts to support Airbus airframe and engine maintenance and repair. In 2017, Alaska entered into a similar contract for maintenance on its B737-800 aircraft engines. These agreements require monthly payments based upon utilization, such as flight hours, cycles and age of the aircraft, and, in turn, the agreement transfers certain risks to the third-party service provider. There are minimum payments under both agreements, which are reflected in the table above. Accordingly, payments could differ materially based on actual aircraft utilization.

Aircraft Maintenance Deposits

Certain Airbus leases include contractually required maintenance deposit payments to the lessor, which collateralize the lessor for future maintenance events should the Company not perform required maintenance. Payments of such deposits follow contractual terms and timing, regardless of operating status of the respective aircraft. Most of the lease agreements provide that maintenance deposits are reimbursable upon completion of the major maintenance event in an amount equal to the lesser of (i) the amount qualified for reimbursement from maintenance deposits held by the lessor associated with the specific major maintenance event or (ii) the qualifying costs related to the specific major maintenance event.

Los Angeles International Airport (LAX) Construction

In May 2019, we executed an amended lease agreement with Los Angeles World Airports, which includes an agreement to renovate and upgrade the fuel system, jet bridges and concourse facilities at Terminal 6 of LAX. Project terms and pre-construction readiness was approved and finalized in 2020. We expect construction will be completed by mid 2024. Under the terms of the agreement, we expect to have total reimbursable cash outlays for the project of approximately $230 million. To date, we have made total cash outlays of $71 million and have received reimbursement for $8.7 million of that total.

Contingencies
 
The Company is a party to routine litigation matters incidental to its business and with respect to which no material liability is expected. Liabilities for litigation related contingencies are recorded when a loss is determined to be probable and estimable.

In 2015, three flight attendants filed a class action lawsuit seeking to represent all Virgin America flight attendants for damages based on alleged violations of California and City of San Francisco wage and hour laws. The court certified a class of approximately 1,800 flight attendants in November 2016. The Company believes the claims in this case are without factual and legal merit.

In July 2018, the Court granted in part Plaintiffs' motion for summary judgment, finding Virgin America, and Alaska Airlines, as a successor-in-interest to Virgin America, responsible for various damages and penalties sought by the class members. On February 4, 2019, the Court entered final judgment against Virgin America and Alaska Airlines in the amount of approximately $78 million. It did not award injunctive relief against Alaska Airlines. In February 2021, an appellate court reversed portions of the lower court decision and significantly reduced the judgment, again without awarding injunctive relief against Alaska. The determination of total judgment has not been completed as of the date of this filing. Based on the facts and circumstances available, the Company believes the range of potential loss to be between $0 and $22 million, and holds an accrual for $22 million in Other accrued liabilities on the consolidated balance sheets.

The Company has asked the U.S. Supreme Court to review the case on the basis that the California laws on which the judgment is based are invalid as applied to airlines pursuant to the U.S. Constitution and provisions of federal law that were enacted to shield inter-state common carriers from a patchwork of state and local wage and hour regulations such as those at issue in this case. If appeal efforts are unsuccessful, compliance with the California laws may have an adverse impact on the Company's operations and financial position, and collective bargaining agreements.

The Company is involved in other litigation around the application of state and local employment laws, like many air carriers. Our defenses are similar to those identified above, including that the state and local laws are preempted by federal law and are unconstitutional because they impede interstate commerce. None of these additional disputes are material.