XML 133 R93.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
Jointly-Owned Facilities (Details) - ARIZONA PUBLIC SERVICE COMPANY
$ in Thousands
Dec. 31, 2019
USD ($)
Palo Verde Units 1 and 3  
Interests in jointly-owned facilities  
Percent Owned 29.10%
Plant in Service $ 1,877,748
Accumulated Depreciation 1,102,609
Construction work in progress $ 22,071
Palo Verde Unit 2  
Interests in jointly-owned facilities  
Percent Owned 16.80%
Plant in Service $ 634,545
Accumulated Depreciation 377,722
Construction work in progress $ 11,831
Palo Verde Common  
Interests in jointly-owned facilities  
Percent Owned 28.00%
Plant in Service $ 746,653
Accumulated Depreciation 290,084
Construction work in progress 46,570
Palo Verde Sale Leaseback  
Interests in jointly-owned facilities  
Plant in Service 351,050
Accumulated Depreciation 249,144
Construction work in progress $ 0
Four Corners Generating Station  
Interests in jointly-owned facilities  
Percent Owned 63.00%
Plant in Service $ 1,520,171
Accumulated Depreciation 559,272
Construction work in progress $ 44,842
Cholla Common Facilities  
Interests in jointly-owned facilities  
Percent Owned 50.50%
Plant in Service $ 184,608
Accumulated Depreciation 95,720
Construction work in progress $ 1,323
ANPP 500kV System  
Interests in jointly-owned facilities  
Percent Owned 33.50%
Plant in Service $ 133,396
Accumulated Depreciation 51,248
Construction work in progress $ 2,723
Navajo Southern System  
Interests in jointly-owned facilities  
Percent Owned 26.70%
Plant in Service $ 89,672
Accumulated Depreciation 31,985
Construction work in progress $ 194
Palo Verde — Yuma 500kV System  
Interests in jointly-owned facilities  
Percent Owned 19.00%
Plant in Service $ 15,274
Accumulated Depreciation 6,486
Construction work in progress $ 4,886
Four Corners Switchyards  
Interests in jointly-owned facilities  
Percent Owned 63.00%
Plant in Service $ 69,994
Accumulated Depreciation 16,674
Construction work in progress $ 2,395
Phoenix — Mead System  
Interests in jointly-owned facilities  
Percent Owned 17.10%
Plant in Service $ 39,355
Accumulated Depreciation 18,570
Construction work in progress $ 53
Palo Verde — Rudd 500kV System  
Interests in jointly-owned facilities  
Percent Owned 50.00%
Plant in Service $ 93,112
Accumulated Depreciation 26,719
Construction work in progress $ 317
Morgan — Pinnacle Peak System  
Interests in jointly-owned facilities  
Percent Owned 64.60%
Plant in Service $ 117,752
Accumulated Depreciation 18,822
Construction work in progress $ 0
Round Valley System  
Interests in jointly-owned facilities  
Percent Owned 50.00%
Plant in Service $ 515
Accumulated Depreciation 164
Construction work in progress $ 0
Palo Verde — Morgan System  
Interests in jointly-owned facilities  
Percent Owned 88.90%
Plant in Service $ 238,689
Accumulated Depreciation 13,146
Construction work in progress $ 0
Hassayampa — North Gila System  
Interests in jointly-owned facilities  
Percent Owned 80.00%
Plant in Service $ 143,422
Accumulated Depreciation 12,676
Construction work in progress $ 0
Cholla 500kV Switchyard  
Interests in jointly-owned facilities  
Percent Owned 85.70%
Plant in Service $ 7,651
Accumulated Depreciation 1,597
Construction work in progress $ 535
Saguaro 500kV Switchyard  
Interests in jointly-owned facilities  
Percent Owned 60.00%
Plant in Service $ 20,425
Accumulated Depreciation 12,949
Construction work in progress $ 0
Kyrene — Knox System  
Interests in jointly-owned facilities  
Percent Owned 50.00%
Plant in Service $ 578
Accumulated Depreciation 315
Construction work in progress $ 0